Longo Construction, Inc. v. ASAP Technical Services, Inc.

140 Ohio App. 3d 665
CourtOhio Court of Appeals
DecidedDecember 11, 2000
DocketNo. 77533
StatusPublished
Cited by13 cases

This text of 140 Ohio App. 3d 665 (Longo Construction, Inc. v. ASAP Technical Services, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Longo Construction, Inc. v. ASAP Technical Services, Inc., 140 Ohio App. 3d 665 (Ohio Ct. App. 2000).

Opinion

John T. Patton, Presiding Judge.

A jury awarded plaintiff Longo Construction, Inc. $108,800.45 on its breach-of-contract claim against defendant ASAP Technical Services, Inc. The primary issue on appeal concerns the amount of damages.

ASAP is a general contractor specializing in remediation or cleanup of environmentally contaminated sites. A company called Advanced Medical Systems contracted with ASAP to remove an underground storage tank. ASAP, in turn, subcontracted with Longo to perform the excavation work. As relevant here, ASAP’s contract with Longo called for a lump sum price of $26,800.

During the course of its work, Longo discovered that radioactive discharge had contaminated the worksite. The presence of radiation changed the nature of the project, requiring additional remediation of the site. To that end, ASAP contracted with Longo on a time-and-material basis to perform the bulk of additional excavation work. Longo billed ASAP $44,321.95 for the additional work.

ASAP paid Longo only $20,000. The evidence at trial showed that ASAP received $144,000 for the additional work Longo performed. Longo made repeated demands for payment of the $51,121.95 owed to it ($26,800 + $44,-321.95 - $20,000 = $51,121.95), but did not receive payment. ASAP claimed that it experienced financial difficulties that prevented it from paying all its creditors. Longo discovered that Advanced Medical Systems had paid ASAP for the work.

Longo filed this action against ASAP setting forth claims of breach of contract, quantum meruit, fraud, fraudulent conveyance, and individual liability on behalf of Inderjit Soni, the majority shareholder and chief executive officer of ASAP. It asked for $51,121.95 in damages. The court directed verdicts on the fraud and fraudulent conveyance claims for relief. The jury found that ASAP breached the contract with Longo by refusing to pay for services performed on a time-and-materials basis, and awarded $108,800.45 in damages. The jury also found that Soni exercised such dominion and control over ASAP that the corporate veil should be pierced and he should be held individually liable. Finally, the court ordered prejudgment interest of $43,579.76. The court denied an ASAP motion for judgment notwithstanding the verdict.

Both parties appeal. ASAP claims that the jury erred by awarding breach of contract damages that exceeded the contract price. It also challenges the imposition of prejudgment interest. Longo cross-appeals, claiming that the court erred by directing verdicts on the fraud and fraudulent-conveyance claims for relief.

[669]*669The Appeal

I & II

The first and second assignments of error both contest the damages award that exceeded the price of the contract. ASAP maintains that the jury could not have awarded an amount in excess of the contract price. Longo counters that the jury’s damage award corresponds to that amount that ASAP received from Advanced Medical.

The applicable measure of damages in this case was Longo’s expectancy interest, that is, its interest in being put in as good a position as it would have been had the contract been performed. Brads v. First Baptist Church of Germantown (1993), 89 Ohio App.3d 328, 338-339, 624 N.E.2d 737, 744-745, citing the Restatement of the Law 2d, Contracts (1981) 102-103, Remedies, Section 344; Rasnick v. Tubbs (1998), 126 Ohio App.3d 431, 437, 710 N.E.2d 750, 753-754. Based on the time-and-material basis agreed upon by the parties and verified by Longo’s submitted invoices, the unpaid contract price was $51,121.95, not the $108,800.45 awarded by the jury.

Longo argues that the time-and-material basis left the price term open and subject to a reasonable value by the trier of fact. To that end, it maintains that ASAP inflated the value of Longo’s work to Advanced Medical Systems by billing Advanced Medical Systems $144,800 for the work Longo performed. Longo thus insists that the damage award should be the value of the contract to ASAP.

We easily reject Longo’s argument because the measure of damages is what Longo expected to be paid pursuant to the contract. Longo memorialized this expectancy in its billings- — the total sum of $71,121.25, less the $20,000 ASAP did pay.

Longo cannot argue a price based on the contractual relationship between ASAP and Advanced Medical Systems. Longo made a separate and distinct contract with ASAP- — -it had no contractual relationship with Advanced Medical Systems. What ASAP did in its contract with Advanced Medical Systems has no bearing on Longo’s performance or payment. As a subcontractor to ASAP, Longo dealt exclusively with ASAP, not Advanced Medical Systems. If Advanced was willing to pay ASAP’s invoices, that benefit would accrue only to ASAP, not Longo.

This assumes that ASAP purposely inflated its invoices to Advanced Medical Systems. Without expressing any opinion on that point, we note that if ASAP inflated the price of Longo’s work, that fact would not affect Longo’s contract damages. In Stranahan Bros. Catering Co. v. Coit (1896), 55 Ohio St. 398, 407-408, 45 N.E. 634, 636-637, the Supreme Court of Ohio stated:

[670]*670“It is also well settled that where the injury results from the default of the contracting party himself, the motive which induces the act or the omission, unless the circumstances raise a claim for exemplary damages, is of no consequence. In such case, evidence of the defaulting party’s motives, or of anything which affects only the moral character of the transaction, can have no weight, and is, therefore, inadmissible. Unless the intention belongs directly to the issue, it is not an element in the case. Compensation for breach of contract in relation to the payment of money, or in relation to property, ordinarily does not involve motive, for in the first case the failure to pay, as agreed, is measured absolutely by the sum and interest, no matter what vicious purpose induced the failure, and in the second, compensation, that is, to be placed in the same position he would have been in had the other party performed his contract, is the injured party’s right, no matter how earnest the unavailing efforts to perform may have been, nor how free from intent to injure the motive of the defaulting party. 3 Parsons on Contracts, 167, and authorities cited.”

Were we to hold otherwise, we would permit Longo to benefit from ASAP’s conduct — conduct that Longo itself has characterized as gross overbilling. Since Longo justified its time and materials spent on the additional work in the amount of $51,121.95, the court erred by permitting the jury to return a verdict in excess of that amount. The first and second assignments of error are sustained, and judgment is entered in Longo’s favor in the amount of $51,121.95.

Ill

The third assignment of error complains that the court erred by awarding prejudgment interest on a $108,800.45 award. Our disposition of the first and second assignments of error necessarily changes the amount of interest due, since the principal balance has changed. We remand to the court for this recalculation.

Moreover, the court’s December 23,1999 journal entry contains a clerical error. It awards prejudgment interest from October 30, 1995 to November 1, 1995.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Yost v. D&L Ferguson, L.L.C.
2025 Ohio 1307 (Ohio Court of Appeals, 2025)
Francisco A. Mateo M.D., Inc. v. Proia
2023 Ohio 3908 (Ohio Court of Appeals, 2023)
U.S. Bank Natl. Assn. v. MMCO, L.L.C.
2021 Ohio 4605 (Ohio Court of Appeals, 2021)
Binsara, L.L.C.. v. Bolog
2019 Ohio 4040 (Ohio Court of Appeals, 2019)
Denny v. Breawick, L.L.C.
2019 Ohio 2066 (Ohio Court of Appeals, 2019)
Woehler v. Brandenburg
2012 Ohio 5355 (Ohio Court of Appeals, 2012)
State Ex Rel. DeWine v. S & R Recycling, Inc.
2011 Ohio 3371 (Ohio Court of Appeals, 2011)
Unencumbered Assets v. JP Morgan Chase Bank
783 F. Supp. 2d 1003 (S.D. Ohio, 2011)
Siva v. 1138 L.L.C., 06ap-959 (9-11-2007)
2007 Ohio 4667 (Ohio Court of Appeals, 2007)
State Ex Rel. Petro v. Mercomp, Inc.
853 N.E.2d 1193 (Ohio Court of Appeals, 2006)
State v. Tri-State Group, Inc., Unpublished Decision (8-20-2004)
2004 Ohio 4441 (Ohio Court of Appeals, 2004)
Yo-Can, Inc. v. Yogurt Exchange, Inc.
778 N.E.2d 80 (Ohio Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
140 Ohio App. 3d 665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/longo-construction-inc-v-asap-technical-services-inc-ohioctapp-2000.