Denny v. Breawick, L.L.C.

2019 Ohio 2066
Ohio Court of Appeals·Decided May 28, 2019·No. 5-18-12·Published·Cited by 8 cases

Opinion

IN THE COURT OF APPEALS OF OHIO THIRD APPELLATE DISTRICT

HANCOCK COUNTY

CHERYL DENNY, CASE NO. 5-18-12

PLAINTIFF-APPELLEE,

v.

BREAWICK, LLC, ET AL., OPINION DEFENDANTS-APPELLANTS.

Appeal from Hancock County Common Pleas Court Trial Court No. 2014CV446

Judgment Affirmed

Date of Decision: May 28, 2019

APPEARANCES:

Howard Elliott for Appellant William E. Clark for Appellee

WILLAMOWSKI, J.

{¶1} Defendants-appellants Breawick, LLC (“Breawick”); Buren Trace Development, LLC (“Buren Trace”); and Timothy Hunsaker (“Hunsaker”) appeal the judgment of the Hancock County Court of Common Pleas, alleging that the trial court should not have allowed the corporate veil to be pierced. For the reasons set forth below, the judgment of the trial court is affirmed.

Facts and Procedural History

{¶2} Hunsaker is a building contractor who is the sole member of two limited liability companies: Breawick and Buren Trace. September 16 Tr. 14, 29. Hunsaker did construction work through Breawick in the Buren Trace Development. Id. at 39. March 1 Tr. 38. On February 24, 2013, Cheryl Denny (“Denny”) entered into a contract for the construction of a house. Doc. 1, Ex. A. Denny had nine meetings with Hunsaker before she signed this contract. September 16 Tr. 74. Through these meetings, Denny and Hunsaker worked out the exact specifications of the house that was to be built. Doc. 1, Ex. A. Hunsaker signed the contract on behalf of Breawick and agreed to furnish all labor and materials for this project. Doc. 1, Ex. A. The contract price for the house was $397,400.00. September 16 Tr. 26. Construction on the house began on April 26, 2013. Id. at 87.

{¶3} During the course of construction, a number of disagreements arose between Hunsaker and Denny over the work that he was performing. Id. at 83, 86. Denny testified that she never agreed to any alterations to the original building

specifications. Id. at 88. However, she said that Hunsaker deviated from the plans, in one instance placing a kitchen wall where an open space was supposed to be. Id. at 88. Denny further testified that she was charged for this work even though she did not approve this change. Id. at 88-89.

{¶4} Denny also stated that Hunsaker made requests for additional payments for “extras” that amounted to around $20,000.00. Id. at 85. Denny testified that Hunsaker would threaten to stop working on the house if his requests for these payments were not met. Id. at 86, 91. The change orders and “extras” were not submitted to Denny in writing and were not approved by Denny. Id. at 85. Denny testified that she felt “under pressure” to pay for the “extras” because Hunsaker was behind on the construction schedule and she wanted to end that particular fight. Id. at 86.

{¶5} Denny also testified that several liens were placed on the house during the course of the construction by several suppliers. September 16 Tr. 95. Denny further testified that she had to pay one lien, though she also said that Hunsaker was able to address another lien without her intervention. Id. at 95. At one point, Denny was made a party to a legal action that was filed by a supplier against Hunsaker. Id. Denny testified that she was released from this action but did have to pay some attorney’s fees. Id. at 96. She could not pay for these various expenses with funds from her bank loan and had to draw on other lines of credit to cover these costs. Id. at 96.

{¶6} Hunsaker claimed that one of Denny’s friends, Clinton Johnson (“Johnson”), functioned as a superintendent of sorts during the course of this project. March 3 Tr. 67. Hunsaker had previously built a house in Buren Trace for Johnson, who was knowledgeable about electrical; plumbing; and heating, ventilation and air conditioning work. Id. at 67. March 1 Tr. 24, 52. Johnson offered to help Denny in the process of building this house and was involved in overseeing various aspects of this project. March 1 Tr. 24. Hunsaker testified that Johnson was very involved with subcontractors and even directed some of their work. March 3 Tr. 10, 69-70. He further blamed Johnson’s work on the house for some of the construction defects.1 Id. at 91.

{¶7} Hunsaker claimed that he was at the construction site on every workday from April to December of 2013, though Denny claimed that Hunsaker worked much less frequently on the house. March 1 Tr. 21, 71. September 16 Tr. 90. On December 30, 2013, Hunsaker quit working on the house. Id. at 34. At that time, the house was not completed, but Denny had paid a total of $341,696.27 to the defendants. Doc. 100. See Id. at 47. At trial, Hunsaker said that the house was ninety to ninety-five percent complete at the time that he quit. Id. Claiming he was

1 On December 1, 2014, the defendants filed a third party complaint against Johnson, arguing that Johnson should be liable to Breawick if a judgment is entered against Breawick. Doc. 28. Johnson filed a motion for summary judgment on December 4, 2015. Doc. 57. On January 12, 2016, the trial court granted Johnson’s motion for summary judgment. Doc. 65.

not getting paid, Hunsaker filed for a mechanic’s lien on Denny’s house on January 22, 2014.2 Doc. 1.

{¶8} On January 5, 2014, Denny compiled a list of contract specifications that had not been finished. September 16 Tr. 99. At this point, the house was not completed to the point that Denny could move into it. Id. at 92. She then hired S.E. Hile General Contracting, LLC, to continue working on the house. Id. Doc. 100. Subsequently, Denny had to spend $46,057.48 to make the house habitable, though these improvements still did not complete the house to the point where it satisfied the original contract specifications. Id. at 82.

{¶9} Denny filed a complaint against Breawick, Buren Trace, and Hunsaker on September 17, 2014. Doc. 1. The complaint alleged that the defendants violated the Ohio Consumer Sales Practices Act (“CSPA”); were in breach of contract; converted funds; committed fraud; benefitted from unjust enrichment; and violated provisions of the Home Construction Service Law (“HCSL”). Doc. 1. Denny also alleged that Buren Trace and Breawick were Hunsaker’s alter egos and that the trial court should pierce the corporate veil in order to hold Hunsaker personally liable for damages. Doc. 1.

{¶10} At trial, an expert in home construction—Steven E. Hile (“Hile”)—

testified about the costs of finishing the Denny’s home. September 29 Tr. 9, 12.

2 Hunsaker claimed that Denny owed him $71,212.39 for work that he performed before he quit working on the house. Doc. 100. On October 20, 2017, in its judgment entry, the trial court declared that this lien was unenforceable and void as the defendants could not prove that Denny owed this amount. Doc. 100.

During his testimony, Hile outlined all of the deficiencies in the construction of the home that had to be rectified and the building specifications that had yet to be completed. Id. at 20-78. Altogether, he estimated that the total cost of getting the home to meet the contract specifications would be $125,216.00 more than what Denny paid Hunsaker. Id. at 82. He testified that Denny had already spent $46,057.00 to make some repairs in order to make the house habitable but that more repairs had to be made. Id.

{¶11} At trial, Denny’s husband introduced a video of the premises that documented many of the construction flaws in the house. March 1 Tr. 16. There were issues with the gutters, downspouts, rough grade, drainage system, sidewalk, vinyl siding, ceiling, foyer, crown molding, walls, and trim. September 29 Tr. 20, 24, 31, 40, 57, 58, 72, 74, 75, 78. In particular, Denny mentioned the problem of water leaks in various parts of the house, though Hunsaker claimed that the basement windows were not leaking. March 1 Tr. 74.

Free access — add to your briefcase to read the full text and ask questions with AI

Denny v. Breawick, L.L.C., 2019 Ohio 2066 (Ohio Ct. App. 2019).

2019 Ohio 2066 (Denny v. Breawick, L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State ex rel. Yost v. D&L Ferguson, L.L.C.
2025 Ohio 1307 (Ohio Court of Appeals, 2025)
Best Fin. Solutions, L.L.C. v. Tifton Custom Parking, L.L.C.
2024 Ohio 4458 (Ohio Court of Appeals, 2024)
Han v. Coutts
E.D. Texas, 2023
Vara v. Motil
N.D. Ohio, 2023
U.S. Bank Natl. Assn. v. MMCO, L.L.C.
2021 Ohio 4605 (Ohio Court of Appeals, 2021)
Weaner & Assocs., L.L.C. v. 369 W. First, L.L.C.
2020 Ohio 48 (Ohio Court of Appeals, 2020)
Binsara, L.L.C.. v. Bolog
2019 Ohio 4040 (Ohio Court of Appeals, 2019)