Denny v. Breawick, L.L.C.

2019 Ohio 2066
CourtOhio Court of Appeals
DecidedMay 28, 2019
Docket5-18-12
StatusPublished
Cited by8 cases

This text of 2019 Ohio 2066 (Denny v. Breawick, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Denny v. Breawick, L.L.C., 2019 Ohio 2066 (Ohio Ct. App. 2019).

Opinion

[Cite as Denny v. Breawick, L.L.C., 2019-Ohio-2066.]

IN THE COURT OF APPEALS OF OHIO THIRD APPELLATE DISTRICT HANCOCK COUNTY

CHERYL DENNY, CASE NO. 5-18-12 PLAINTIFF-APPELLEE,

v.

BREAWICK, LLC, ET AL., OPINION

DEFENDANTS-APPELLANTS.

Appeal from Hancock County Common Pleas Court Trial Court No. 2014CV446

Judgment Affirmed

Date of Decision: May 28, 2019

APPEARANCES:

Howard Elliott for Appellant

William E. Clark for Appellee Case No. 5-18-12

WILLAMOWSKI, J.

{¶1} Defendants-appellants Breawick, LLC (“Breawick”); Buren Trace

Development, LLC (“Buren Trace”); and Timothy Hunsaker (“Hunsaker”) appeal

the judgment of the Hancock County Court of Common Pleas, alleging that the trial

court should not have allowed the corporate veil to be pierced. For the reasons set

forth below, the judgment of the trial court is affirmed.

Facts and Procedural History

{¶2} Hunsaker is a building contractor who is the sole member of two limited

liability companies: Breawick and Buren Trace. September 16 Tr. 14, 29. Hunsaker

did construction work through Breawick in the Buren Trace Development. Id. at

39. March 1 Tr. 38. On February 24, 2013, Cheryl Denny (“Denny”) entered into

a contract for the construction of a house. Doc. 1, Ex. A. Denny had nine meetings

with Hunsaker before she signed this contract. September 16 Tr. 74. Through these

meetings, Denny and Hunsaker worked out the exact specifications of the house that

was to be built. Doc. 1, Ex. A. Hunsaker signed the contract on behalf of Breawick

and agreed to furnish all labor and materials for this project. Doc. 1, Ex. A. The

contract price for the house was $397,400.00. September 16 Tr. 26. Construction

on the house began on April 26, 2013. Id. at 87.

{¶3} During the course of construction, a number of disagreements arose

between Hunsaker and Denny over the work that he was performing. Id. at 83, 86.

Denny testified that she never agreed to any alterations to the original building

-2- Case No. 5-18-12

specifications. Id. at 88. However, she said that Hunsaker deviated from the plans,

in one instance placing a kitchen wall where an open space was supposed to be. Id.

at 88. Denny further testified that she was charged for this work even though she

did not approve this change. Id. at 88-89.

{¶4} Denny also stated that Hunsaker made requests for additional payments

for “extras” that amounted to around $20,000.00. Id. at 85. Denny testified that

Hunsaker would threaten to stop working on the house if his requests for these

payments were not met. Id. at 86, 91. The change orders and “extras” were not

submitted to Denny in writing and were not approved by Denny. Id. at 85. Denny

testified that she felt “under pressure” to pay for the “extras” because Hunsaker was

behind on the construction schedule and she wanted to end that particular fight. Id.

at 86.

{¶5} Denny also testified that several liens were placed on the house during

the course of the construction by several suppliers. September 16 Tr. 95. Denny

further testified that she had to pay one lien, though she also said that Hunsaker was

able to address another lien without her intervention. Id. at 95. At one point, Denny

was made a party to a legal action that was filed by a supplier against Hunsaker. Id.

Denny testified that she was released from this action but did have to pay some

attorney’s fees. Id. at 96. She could not pay for these various expenses with funds

from her bank loan and had to draw on other lines of credit to cover these costs. Id.

at 96.

-3- Case No. 5-18-12

{¶6} Hunsaker claimed that one of Denny’s friends, Clinton Johnson

(“Johnson”), functioned as a superintendent of sorts during the course of this

project. March 3 Tr. 67. Hunsaker had previously built a house in Buren Trace for

Johnson, who was knowledgeable about electrical; plumbing; and heating,

ventilation and air conditioning work. Id. at 67. March 1 Tr. 24, 52. Johnson

offered to help Denny in the process of building this house and was involved in

overseeing various aspects of this project. March 1 Tr. 24. Hunsaker testified that

Johnson was very involved with subcontractors and even directed some of their

work. March 3 Tr. 10, 69-70. He further blamed Johnson’s work on the house for

some of the construction defects.1 Id. at 91.

{¶7} Hunsaker claimed that he was at the construction site on every workday

from April to December of 2013, though Denny claimed that Hunsaker worked

much less frequently on the house. March 1 Tr. 21, 71. September 16 Tr. 90. On

December 30, 2013, Hunsaker quit working on the house. Id. at 34. At that time,

the house was not completed, but Denny had paid a total of $341,696.27 to the

defendants. Doc. 100. See Id. at 47. At trial, Hunsaker said that the house was

ninety to ninety-five percent complete at the time that he quit. Id. Claiming he was

1 On December 1, 2014, the defendants filed a third party complaint against Johnson, arguing that Johnson should be liable to Breawick if a judgment is entered against Breawick. Doc. 28. Johnson filed a motion for summary judgment on December 4, 2015. Doc. 57. On January 12, 2016, the trial court granted Johnson’s motion for summary judgment. Doc. 65.

-4- Case No. 5-18-12

not getting paid, Hunsaker filed for a mechanic’s lien on Denny’s house on January

22, 2014.2 Doc. 1.

{¶8} On January 5, 2014, Denny compiled a list of contract specifications

that had not been finished. September 16 Tr. 99. At this point, the house was not

completed to the point that Denny could move into it. Id. at 92. She then hired S.E.

Hile General Contracting, LLC, to continue working on the house. Id. Doc. 100.

Subsequently, Denny had to spend $46,057.48 to make the house habitable, though

these improvements still did not complete the house to the point where it satisfied

the original contract specifications. Id. at 82.

{¶9} Denny filed a complaint against Breawick, Buren Trace, and Hunsaker

on September 17, 2014. Doc. 1. The complaint alleged that the defendants violated

the Ohio Consumer Sales Practices Act (“CSPA”); were in breach of contract;

converted funds; committed fraud; benefitted from unjust enrichment; and violated

provisions of the Home Construction Service Law (“HCSL”). Doc. 1. Denny also

alleged that Buren Trace and Breawick were Hunsaker’s alter egos and that the trial

court should pierce the corporate veil in order to hold Hunsaker personally liable

for damages. Doc. 1.

{¶10} At trial, an expert in home construction—Steven E. Hile (“Hile”)—

testified about the costs of finishing the Denny’s home. September 29 Tr. 9, 12.

2 Hunsaker claimed that Denny owed him $71,212.39 for work that he performed before he quit working on the house. Doc. 100. On October 20, 2017, in its judgment entry, the trial court declared that this lien was unenforceable and void as the defendants could not prove that Denny owed this amount. Doc. 100.

-5- Case No. 5-18-12

During his testimony, Hile outlined all of the deficiencies in the construction of the

home that had to be rectified and the building specifications that had yet to be

completed. Id. at 20-78. Altogether, he estimated that the total cost of getting the

home to meet the contract specifications would be $125,216.00 more than what

Denny paid Hunsaker. Id. at 82. He testified that Denny had already spent

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Yost v. D&L Ferguson, L.L.C.
2025 Ohio 1307 (Ohio Court of Appeals, 2025)
Best Fin. Solutions, L.L.C. v. Tifton Custom Parking, L.L.C.
2024 Ohio 4458 (Ohio Court of Appeals, 2024)
Han v. Coutts
E.D. Texas, 2023
Vara v. Motil
N.D. Ohio, 2023
U.S. Bank Natl. Assn. v. MMCO, L.L.C.
2021 Ohio 4605 (Ohio Court of Appeals, 2021)
Weaner & Assocs., L.L.C. v. 369 W. First, L.L.C.
2020 Ohio 48 (Ohio Court of Appeals, 2020)
Binsara, L.L.C.. v. Bolog
2019 Ohio 4040 (Ohio Court of Appeals, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 2066, Counsel Stack Legal Research, https://law.counselstack.com/opinion/denny-v-breawick-llc-ohioctapp-2019.