Rasnick v. Tubbs

710 N.E.2d 750, 126 Ohio App. 3d 431
CourtOhio Court of Appeals
DecidedFebruary 25, 1998
DocketCASE NO: 9-97-46.
StatusPublished
Cited by35 cases

This text of 710 N.E.2d 750 (Rasnick v. Tubbs) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Rasnick v. Tubbs, 710 N.E.2d 750, 126 Ohio App. 3d 431 (Ohio Ct. App. 1998).

Opinion

Evans, Judge.

This appeal is brought by Dennis Tubbs, d.b.a. Denny’s Street Shop (“appellant”), from a judgment of the Marion County Court of Common Pleas finding appellant liable to Charles and Tonyua Rasnick, d.b.a. Bennett & Sieg Auto Wrecking and d.b.a. The Rasnick Family Racing Team (“Rasnicks”), for $15,-903.68 in damages for breach of a contract.

The parties in this case entered into a contract for the construction of a race car. In December 1994, appellant orally agreed to construct a 1952 Chevy Pro Modified Race Car from a 1952 Sports Coupe already owned by the Rasnicks. In addition to paying appellant $52,820 for the job, the Rasnicks were to supply the engine, transmission, and clutch assembly for the race car. Any other parts purchased by the Rasnicks would be counted toward the agreed purchase price of $52,820. 1 The construction of the car was to be completed over twenty weeks’ time. The Rasnicks agreed to make installments of $1,000 each week for appellant’s labor, although the contract did not allocate a part of the purchase price for labor.

By May 12, 1995, the car was not completed and the parties saw the need to enter into a written contract. The written contract embodied substantially the same terms as the oral agreement; however, it provided that appellant would complete construction of the race car within six weeks of receiving the wheels and tires. When the completed race car was finished, as defined in the contract, the Rasnicks would pay the balance due under the contract in a lump sum.

The evidence produced at trial reveals that the wheels and tires were delivered to appellant’s shop on or about May 26, 1995. Six weeks after this date the car *434 was still not completed. Nevertheless, the Rasnicks continued to make $1,000 payments to appellant, and appellant continued to work intermittently on the car. By February 29, 1996, the Rasnicks had paid approximately $49,619.25 toward the contract price, 2 and the car was still not finished. A meeting was called by the parties. According to the Rasnicks and one other witness, appellant informed the Rasnicks that he would not finish construction of the race car unless he was paid an additional $20,000. Furthermore, appellant stated that he could not guarantee that the costs to complete the car would not exceed this amount. Refusing to pay more than the contracted price, the Rasnicks removed the partially constructed race car from appellant’s shop, with appellant’s consent, and subsequently took it to another mechanic for completion. At trial, appellant denied these statements and claimed that he could have finished the car for $5,609.70.

On April 4, 1996, the Rasnicks filed a complaint in the Court of Common Pleas of Marion County, claiming that appellant was in breach of contract and seeking damages in the amount of $25,000, which represented their cost to have the car completed at another shop. A three-day bench trial commenced on February 27, 1997. On June 5, 1997, the trial court issued its judgment entry, granting the Rasnicks $15,903.68 in damages.

Appellant now appeals this decision, asserting two assignments of error.

“Assignment of Error No. One
“The judgment below is contrary to the manifest weight of the evidence and should be reversed because there was no competent credible evidence to establish that the parties had a meeting of the minds and therefore a specific contract that defendant breached that would entitle plaintiffis] to damages.”

Appellant’s first assignment of error alleges that the trial court erred in finding a binding contract existed in this case. To the contrary, we find that the trial court had ample evidence before it to determine the existence of a contract.

“A contract is a promise or a set of promises for the breach of which the law gives a remedy, or the performance of which the law in some way recognizes a duty.” Ford v. Tandy Transp., Inc. (1993), 86 Ohio App.3d 364, 380, 620 N.E.2d 996, 1006, citing Restatement of the Law 2d, Contracts (1981) 5, Section 1. In order for a party to be bound to a contract, the party must consent to its terms, the contract must be certain and definite, and there must be a meeting of the minds of both parties. Episcopal Retirement Homes, Inc. v. Ohio Dept. of *435 Indus. Relations (1991), 61 Ohio St.3d 366, 369, 575 N.E.2d 134, 137. Manifestation of mutual assent to an exchange requires that each party either make a promise or begin or render a performance. Ford, 86 Ohio App.3d at 380, 620 N.E.2d at 1006. Normally, mutual assent is effected by offer and acceptance. Id.

The record in this case is replete with evidence that the parties were of one mind concerning the agreement for the construction of the race car. What began as an oral agreement wherein one party agreed to build a race car and the other party agreed to pay a sum of money in exchange was subsequently put down in a written document entitled a “contract.” The terms of the contract were certain and definite. It was stated that the total expenditure by the Rasnicks was to be $52,820, for which they would receive a race car. This price included the cost of parts necessary to complete the car with the exception of the motor, transmission, and clutch assembly. Other parts supplied by the Rasnicks would be deducted from the total purchase price. The Rasnicks agreed to make weekly payments of $1,000 for appellant’s labor costs, 3 and appellant was to complete the car within six weeks of receiving the wheels and tires. While the deadline for completion of the car was continually extended, this modification was by agreement of the parties. The parties had a meeting of the minds as to these terms. We find that the record, supports the trial court’s determination that the parties entered into a binding contract for the construction of a race car. Consequently, appellant’s first assignment of error is overruled.

“Assignment of Error No. Two
“The court below erred as a matter of law by failing to deduct the costs of the parts provided by defendant Tubbs in determining the amount of damages awarded.”

It is axiomatic that a claimant seeking to recover for a breach of contract must show injuries as a result of the breach in order to recover damages from the breaching party. Metro. Life Ins. Co. v. Triskett Illinois, Inc. (1994), 97 Ohio App.3d 228, 235, 646 N.E.2d 528, 532. Damages are not awarded for a mere breach alone. In this case, appellant’s failure to fulfill his obligations under the *436 contract resulted in damage to the Rasnicks. The Rasnicks were forced to find another mechanic to finish their car and were faced with thousands of dollars of additional expense.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United Assn. Local 168, Apprentice Educational Fund v. Robinson
2025 Ohio 2421 (Ohio Court of Appeals, 2025)
Durnell's RV Sales, Inc. v. Beckler
2023 Ohio 3565 (Ohio Court of Appeals, 2023)
Erie Cty. Bd. of Commrs. v. Hintz
2023 Ohio 1595 (Ohio Court of Appeals, 2023)
Csizmadia v. Gilkey
2021 Ohio 2760 (Ohio Court of Appeals, 2021)
Certain Care, L.L.C. v. Mikitka
2020 Ohio 3544 (Ohio Court of Appeals, 2020)
Walters v. Goddard
2020 Ohio 870 (Ohio Court of Appeals, 2020)
Delta Fuels, Inc. v. Ohio Dept. of Transp.
2015 Ohio 5545 (Ohio Court of Appeals, 2015)
Ineos USA L.L.C. v. Furmanite America, Inc.
2014 Ohio 4996 (Ohio Court of Appeals, 2014)
Anadarko E & P Co. LP v. Northwood Energy Corp.
970 F. Supp. 2d 764 (S.D. Ohio, 2013)
Younglove Construction, LLC v. PSD Development, LLC
782 F. Supp. 2d 457 (N.D. Ohio, 2011)
Nieman v. Bunnell Hill Dev. Co., Inc., Ca2007-07-174 (10-27-2008)
2008 Ohio 5541 (Ohio Court of Appeals, 2008)
Short v. Greenfield Meadows Assoc., 07ca14 (6-24-2008)
2008 Ohio 3311 (Ohio Court of Appeals, 2008)
Doe v. SexSearch. Com
502 F. Supp. 2d 719 (N.D. Ohio, 2007)
Hugh v. Wills, Unpublished Decision (3-17-2006)
2006 Ohio 1282 (Ohio Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
710 N.E.2d 750, 126 Ohio App. 3d 431, Counsel Stack Legal Research, https://law.counselstack.com/opinion/rasnick-v-tubbs-ohioctapp-1998.