Robert A. Saurber Gen. Cont. v. McAndrews, Unpublished Decision (12-20-2004)

2004 Ohio 6927
CourtOhio Court of Appeals
DecidedDecember 20, 2004
DocketCase No. CA2003-09-239.
StatusUnpublished
Cited by10 cases

This text of 2004 Ohio 6927 (Robert A. Saurber Gen. Cont. v. McAndrews, Unpublished Decision (12-20-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Robert A. Saurber Gen. Cont. v. McAndrews, Unpublished Decision (12-20-2004), 2004 Ohio 6927 (Ohio Ct. App. 2004).

Opinion

OPINION
{¶ 1} Appellants, Robert McAndrews ("McAndrews") and RTBH, Inc. ("RTBH"), appeal the decision of the Butler County Court of Common Pleas to grant judgment in favor of appellee, Robert A. Saurber. We affirm the decision of the trial court.

{¶ 2} McAndrews is the sole officer and shareholder of RTBH, a glass window and door installation company.1 Appellee is a general contractor who was hired by the Trenton-Bloomfield School Board in 1999 to do some remodeling at the school. Pursuant to a purchase order with appellee, appellants, as a subcontractor, agreed to install windows and doors in the Trenton-Bloomfield school for a fee of $290,200.

{¶ 3} When appellants ordered materials or completed a portion of the work, they, like all the subcontractors on the job, submitted a request for a draw on the total price of the contract. Appellants did not have good credit with the material suppliers, however, so when a draw for materials was submitted and approved, appellants and appellee agreed that appellee would issue joint checks to McAndrews and his material suppliers. During the time his company worked on the school project, McAndrews submitted several draws for material and labor. Appellee, in return, issued checks to McAndrews to cover the costs of the materials ordered and the labor performed.

{¶ 4} The evidence offered at trial indicates that at some point during the project McAndrews took two of the joint checks appellee issued and deposited them into his own corporate bank account, rather than obtain the required joint signatures and pay his suppliers. Consequently, two of the suppliers did not get paid and filed liens against appellee and the school project. To get the liens released, appellee had to pay the suppliers directly, causing appellee to have to pay for material twice.

{¶ 5} Testimony at trial also indicated that the work completed by appellants was done in an unworkmanlike manner. Furthermore, when appellants were released from the project, they had received draws from appellee totaling an overpayment of approximately $30,000.

{¶ 6} Soon after appellants were terminated from the project, appellee filed a lawsuit alleging, among other things, breach of contract, fraud, and conversion. The pre-trial process continued for approximately two years, and during that time appellants' initial attorney, Sal Scrofano, filed a motion to withdraw as counsel. The court denied this motion. However, on April 16, 2003, the day of trial, attorney Scrofano informed the court that appellants were willing to release him and, if need be, proceed to trial without the necessity of a continuance. In response, the trial court granted attorney Scrofano's request to be dismissed.

{¶ 7} With attorney Scrofano dismissed, McAndrews then requested a continuance in order to obtain new counsel. He indicated to the court that attorney Edward McTigue was willing to represent appellants but was unable to appear in court that day. The court denied the request and the trial commenced with McAndrews proceeding pro se.

{¶ 8} After a two-day bench trial, the court found that RTBH breached its contract with appellee, and that the evidence warranted piercing the corporate veil and holding McAndrews personally liable for the actions of RTBH.

{¶ 9} This appeal followed, in which appellants raise two assignments of error.

{¶ 10} Assignment of Error No. 1:

{¶ 11} "The trial court erred to the prejudice of appellant[s] in granting entry of judgment for plaintiff."

{¶ 12} In their first assignment of error, appellants challenge the trial court's decision to deny a continuance on the day of trial, and the trial court's finding that enough evidence was presented at trial to justify a piercing of the corporate veil. We begin by addressing appellants' contention that the trial court erred in denying the request for a continuance on the day of trial.

{¶ 13} Appellants first contend that the trial court abused its discretion in denying the request for a continuance on the day of trial because the totality of the circumstances indicated that a delay would not be unreasonable.

{¶ 14} "The grant or denial of a continuance is a matter that is entrusted to the broad, sound discretion of the trial judge."State v. Unger (1981), 67 Ohio St.2d 65, syllabus. A reviewing court should not reverse the trial court's decision, therefore, unless there has been an abuse of that discretion. Id. at 67. "The term discretion * * * involves the idea of a choice, of an exercise of the will, of a determination made between competing considerations." State v. Jenkins (1984), 15 Ohio St.3d 164,222. Merely disagreeing with the trial court's choice to deny appellants a continuance, therefore, would not be adequate grounds for this court to reverse. In order to reverse a decision within the sound discretion of the trial court, we must determine that the trial court's choice between the competing considerations was unreasonable, arbitrary, or unconscionable.Blakemore v. Blakemore (1983), 5 Ohio St.3d 217, 219.

{¶ 15} When a continuance is requested, the competing interests to be considered are the court's right to control its own docket, the plaintiff's and the public's interest in the prompt and efficient administration of justice, and the potential prejudice that could result to the moving party if the request is denied. Unger, 67 Ohio St.2d at 67. In balancing these interests, a court must consider such things as: the length of the delay requested; whether other continuances have been requested and received; the inconvenience to litigants, witnesses, opposing counsel and the court; whether the requested delay is for legitimate reasons or whether it is dilatory, purposeful, or contrived; whether the defendant contributed to the circumstance which gave rise to the request, and any other factors relevant to the particular circumstances of each case. Id. at 67-68.

{¶ 16} Turning to the circumstances of this case, we note that over two years had passed since the initial complaint was filed. Appellants also had knowledge of attorney Scrofano's desire to withdraw well in advance of the day of trial. Nevertheless, when McAndrews made his request for a continuance, he had not yet even secured an entry of appearance from attorney McTigue. Furthermore, McAndrews stated before attorney Scrofano was released that he was prepared to proceed pro se even if he were not granted a continuance.

{¶ 17} Additionally, the trial court noted, and we agree, that a tremendous amount of effort is required for the court and an opposing party to prepare for a trial. Granting a continuance requested on the day of trial would have been a substantial burden to all other parties involved. Finally, the record contains no indication of how long the delay would have been if appellant had successfully obtained a continuance.

{¶ 18} After carefully considering all of the foregoing circumstances of this case, we find that denying appellants' request for a continuance was not unreasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Momentum Freight Logistics Corp. v. Benie Logistics, Inc.
2025 Ohio 5738 (Ohio Court of Appeals, 2025)
City of Cleveland v. Embassy Realty Invs., Inc.
2018 Ohio 2513 (Ohio Court of Appeals, 2018)
Advantage Bank v. Waldo Pub., L.L.C.
2009 Ohio 2816 (Ohio Court of Appeals, 2009)
Dombroski v. WellPoint, Inc.
895 N.E.2d 538 (Ohio Supreme Court, 2008)
Wilson v. Superior Foundations, Inc., Ca2007-03-043 (3-24-2008)
2008 Ohio 1359 (Ohio Court of Appeals, 2008)
Dombroski v. Wellpoint, Inc.
879 N.E.2d 225 (Ohio Court of Appeals, 2007)
Siva v. 1138 L.L.C., 06ap-959 (9-11-2007)
2007 Ohio 4667 (Ohio Court of Appeals, 2007)
Sabin Wholesale v. Hilton, Unpublished Decision (3-12-2007)
2007 Ohio 1097 (Ohio Court of Appeals, 2007)
Mohme v. Deaton, Unpublished Decision (12-28-2006)
2006 Ohio 7042 (Ohio Court of Appeals, 2006)
Vilardo v. Sheets, Unpublished Decision (7-3-2006)
2006 Ohio 3473 (Ohio Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 6927, Counsel Stack Legal Research, https://law.counselstack.com/opinion/robert-a-saurber-gen-cont-v-mcandrews-unpublished-decision-ohioctapp-2004.