Kingston Housing Authority v. Sandonato & Bogue, Inc.

577 N.E.2d 1, 31 Mass. App. Ct. 270
CourtMassachusetts Appeals Court
DecidedAugust 23, 1991
Docket89-P-604
StatusPublished
Cited by11 cases

This text of 577 N.E.2d 1 (Kingston Housing Authority v. Sandonato & Bogue, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kingston Housing Authority v. Sandonato & Bogue, Inc., 577 N.E.2d 1, 31 Mass. App. Ct. 270 (Mass. Ct. App. 1991).

Opinion

Kass, J.

Much of what the Kingston Housing Authority (the KHA) has strenuously argued on its appeal is governed by Melrose Hous. Authy. v. New Hampshire Ins. Co., 402 Mass. 27 (1988). As in Melrose, the KHA had a clerk of the works inspecting construction as it went up and may not claim that the defects which plague the project concerned were inherently unknowable. What remains in the case is KHA’s contention that the obligations of Sandonato & Bogue, Inc. (Sandonato), the general contractor on the project, extend beyond the limitation — six years — established by G. L. c. 260, § 2B. The applicable limitations period, KHA urges, is twenty years after its cause accrued because its contract with Sandonato is under seal. See G. L. c. 260, § 1, First.

After hearing the case on defense motions for summary judgment, supported by. affidavits, interrogatories, depositions, and documents, a judge of the Superior Court decided KHA’s claims were time barred under G. L. c. 260, § 2B, except for a count which alleged an intentional breach of the general contract by Sandonato, as to which the judge thought the longer period applied. As to all other counts in the complaint, the motions for summary judgment were allowed. The judge reported the case to us under G. L. c. 213, § IB, G. L. c. 231, § 111, and Mass.R.Civ.P. 64, 365 Mass. 831 (1974). We conclude that all counts in the complaint are time barred.

In outline, these are the facts. KHA entered into a contract with Sandonato on March 21, 1975, to have the latter construct forty-eight units of housing, distributed among six separate buildings. Also included in the contract was a community building. Sandonato substantially completed the job in 1976, and KHA at that time accepted the project, except for punch list items. At once, however, ominous difficulties surfaced. Keeping out rain and cold is the most fundamental function of housing and these buildings did neither. As one *272 witness described them, “They leaked like an eel basket.” The KHA held money back from the contractor until things should be put right. Through 1976 and 1977, the architect and Sandonato made a variety of efforts to remedy the leakage but enjoyed little success. The KHA thought in 1979 that an attempt at waterproofing was working and voted to “close out” the contract with Sandonato. Leakage difficulties persisted, however, and in 1984, the KHA hired independent engineers to diagnose the problem and prescribe a cure.

As part of their study, the engineers opened up several walls and discovered significant deviations from contract specifications. The construction drawings had called for a load bearing composite wall consisting of a brick exterior and a block interior with high strength mortar binding the two. A system of horizontal steel rods was further to tie. the exterior bricks and interior blocks together. The corners of each wall were to be reinforced and the roof trusses were to rest on plate bearings which were, in turn, to be bolted to the composite mortar between the interior blocks and exterior bricks. Many of these specifications had been violated. The engineers found a one-half inch air space between the exterior brick and block walls; the reinforcing rods were not spaced as called for; the corners were not reinforced; the blocks in the interior wall were not solidly grouted, and the bolts for the plate bearings were not in place.

How these deviations contributed to the leaky walls, if they did, is of no consequence in the litigation if the statute of repose (G. L. c. 260, § 2B) and all other applicable limitations periods have run, and this is so whether the claim is cast in the form of tort or implied warranty, as we shall later explicate. Klein v. Catalano, 386 Mass. 701, 718-720 (1982). In Melrose Hous. Authy. v. New Hampshire Ins. Co., 402 Mass, at 32-35, it was decided that if an owner retained for itself or its representative the right to inspect the work and to order uncovered any work which had not been inspected, the owner could not later take the position that a defect was inherently undiscoverable until ultimately uncovered and diagnosed. It is not disputed that the KHA, as owner, had the *273 right, under the general conditions of its construction contract, to inspect and to order work uncovered. Full-time inspection was the duty of a clerk of the works and periodic inspection was the duty of the architect. See also Hanson Hous. Authy. v. Dryvit Sys., Inc., 29 Mass. App. Ct. 440, 443-444 (1990). Able to keep an eye on construction as it proceeded, the KHA may not later attempt to show that the defects were latent and undiscoverable. 2

Owners hoping to jump over the bar of G. L. c. 260, § 2B, observed that the statute was directed to actions of tort. They, therefore, attempted casting their claims in contract terms, i.e., breach of warranty, see, e.g., Klein v. Catalano, 386 Mass, at 718, in hope of applying a longer statute of limitations. That effort, as already noted, met with no success because the act of unintentionally failing to conform with contract specifications is not different from negligent workmanship. Unless breach of warranty in this context were read as just another label for negligent workmanship, the statute, which was curative in the sense that it sought to establish a special limitation for the litigation of construction disputes, would be nullified by the simple expedient of giving the action a different label. Klein v. Catalano, 386 Mass, at 718-720.

Perhaps mindful of that difficulty, the KHA included in its complaint the allegation that the contractor intentionally deviated from the contract specifications and concealed the deviation. The construction contract, the KHA contends, was under seal, and, therefore, the applicable statute of limitations is twenty years. G. L. c. 260, § 1, First. That artifice is also too facile a circumvention of G. L. c. 260, § 2B. An action for damages based on a covert and intentional switch of the contract specifications has the ingredients of a familiar *274 tort, misrepresentation with intent to deceive. 3 See, e.g., Yorke v. Taylor, 332 Mass. 368, 373-374 (1955). The misrepresentation may be effected by a construction contractor through its conduct. Henderson v. D’Arnolfo, 15 Mass. App. Ct. 413, 422-423 (1983). Once again it seems implausible that the legislative policy underlying § 2B, to establish a special deadline for filing a complaint alleging defective design or construction of a building project, should be so easily eluded. Cf. Klein v. Catalano, 386 Mass, at 718-720. We read the complaint by its gist, rather than its label.

As the Klein v. Catalano opinion remarks, one may not pretend that the language of § 2B confining its application to an action of tort does not exist. Id. at 720. See Devaney v. Watertown, 13 Mass. App. Ct. 927, 928 (1982) (court ought.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berish v. Bornstein
21 Mass. L. Rptr. 530 (Massachusetts Superior Court, 2006)
Knott v. Racicot
442 Mass. 314 (Massachusetts Supreme Judicial Court, 2004)
Massachusetts Highway Department v. Walsh Construction Co.
16 Mass. L. Rptr. 15 (Massachusetts Superior Court, 2003)
McGuire v. Woyciechouski
12 Mass. L. Rptr. 568 (Massachusetts Superior Court, 2000)
Arthaud v. Brignati
10 Mass. L. Rptr. 403 (Massachusetts Superior Court, 1999)
Mosesian v. Franki Foundation Corp.
8 Mass. L. Rptr. 629 (Massachusetts Superior Court, 1998)
Lemrise v. Koska
5 Mass. L. Rptr. 589 (Massachusetts Superior Court, 1996)
Campanile v. Suffolk Construction Co.
1 Mass. L. Rptr. 486 (Massachusetts Superior Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
577 N.E.2d 1, 31 Mass. App. Ct. 270, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kingston-housing-authority-v-sandonato-bogue-inc-massappct-1991.