Hanson Housing Authority v. Dryvit System, Inc.

560 N.E.2d 1290, 29 Mass. App. Ct. 440, 1990 Mass. App. LEXIS 577
CourtMassachusetts Appeals Court
DecidedOctober 23, 1990
Docket89-P-150
StatusPublished
Cited by34 cases

This text of 560 N.E.2d 1290 (Hanson Housing Authority v. Dryvit System, Inc.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hanson Housing Authority v. Dryvit System, Inc., 560 N.E.2d 1290, 29 Mass. App. Ct. 440, 1990 Mass. App. LEXIS 577 (Mass. Ct. App. 1990).

Opinion

Jacobs, J.

Before us is the issue of the timeliness of the claims against the defendant, Dryvit System, Inc. (Dryvit). On May 21, 1987, the plaintiff, Hanson Housing Authority, *441 filed a complaint in the Superior Court against a contractor, Concrete Construction Co. of Everett, Inc. (Concrete), Concrete’s bond surety, and Dryvit. The plaintiff appeals from a summary judgment entered on the stated ground that all of the claims asserted by it against Dryvit were barred by various applicable statutes of limitation.

The plaintiff had engaged Concrete to construct a housing project containing seventeen apartment buildings, a garage, and a community building. Among other things, the contract documents required Concrete to install an exterior wall system designed and supplied by Dryvit (the Dryvit System). 2 Concrete retained a subcontractor (who was ultimately im-pleaded in this action) to install the Dryvit System. Dryvit, other than supplying the components, was not involved in the physical installation of the Dryvit System. A certificate of completion of the project was issued by the plaintiff to Concrete on June 16, 1981.The plaintiff, in its complaint, alleged generally that the walls of the project were improperly constructed; that cracks developed in the exterior finish, joints, and caulking; and that, as a result, water penetrated the buildings causing “serious structural and cosmetic damage” to the project. The plaintiff’s complaint, in addition to stating claims against Concrete and its surety, contained the following described eight counts against Dryvit: Count VI, for negligent design; Count VII, for negligent failure to warn and provide adequate instructions; Count VIII, for negligent training and certification; Count IX, for negligent inspection and supervision; Count X, for breach of implied warranties; Count XI, for breach of express warranties; Count XII, for misrepresentation; and Count XIII, for violation of G. L. c. 93A, § 11. Dryvit, in its answer and motion for summary judgment, asserted that all of the claims against it were time barred by the applicable statutes of limitation. 3

*442 The materials properly before the judge establish the following uncontroverted facts. An architect and a full-time clerk of the works were on the project site on behalf of the plaintiff during construction. The contract documents gave the architect the right to inspect and uncover any of the construction work. In 1980, the project’s maintenance supervisor observed that some caulking on an expansion joint between buildings numbered seven and eight was “falling out.” 4 In 1982, the maintenance supervisor noticed some bubbling in the Dryvit System finish coat at a spot in the end wall of building nine. At the time, he pushed against the wall in the area of the bubbling and “felt it moving back and forth.” The plaintiff had the bubbling repaired shortly thereafter. Also, in 1982, the maintenance supervisor noticed “a couple of big cracks,” one where buildings thirteen and fourteen were joined and the other where buildings fifteen and sixteen were joined.

On May 17, 1982, the maintenance supervisor and a representative of Dryvit inspected the exterior wall system of the project. The Dryvit inspector observed “some bubbling and cracking of an exterior wall . . ., some vertical cracks at right angle intersections of some walls [and] some failure of the caulking.” He also observed that, “[w]here finish was removed from bubbled area, fiberglass mesh was not imbedded into the primus adhesive and was totally exposed above the primus adhesive.” Although these observations are not imputed directly to the plaintiff, they confirm the existence and detectability, in 1982, of the physical signs observed. By a letter dated July 8, 1982, an architect notified the Department of Community Affairs of the Commonwealth that the *443 plaintiff had inquired of him if it had any recourse with respect to “Dryvit leaks” at the project. 5

Between 1982 and 1985, the plaintiff was not informed of any aggravation of the condition of the exterior wall system or of any evidence of water penetration or other deficiency. In 1985, a consultant reported to the plaintiff that he observed some exterior cracks and mesh protrusion in the exterior walls of the project. In 1986, he concluded, on the basis of testing and laboratory analysis, that water had penetrated the exterior walls through the cracks in the project’s walls and caused damage to portions of the walls interior to the Dryvit System. He reported these conclusions to the plaintiff.

In ordering summary judgment, the judge relied on Melrose Hous. Authy. v. New Hampshire Ins. Co., 402 Mass. 27 (1988). He noted that the plaintiff, during construction, was in a situation similar to that presented in Melrose, in that it had available to it the services of an architect with authority to inspect and test the work and a clerk of the works who was employed on a full-time basis to inspect the work. He found that the plaintiff “had the means at its disposal to learn of the defects while construction was in progress,” and that, “[tjherefore, the discovery rule does not apply, because the defects were not inherently unknowable at the time of construction.” The “discovery rule” holds that “certain causes of action based on inherently unknowable wrongs do not accrue until the plaintiff learns, or reasonably should have learned, that he has been harmed by the defendant’s conduct.” White v. Peabody Constr. Co., 386 Mass. 121, 129 (1982), citing Hendrickson v. Sears, 365 Mass. 83 (1974). *444 The judge concluded that the applicable statutes of limitation began running when the certificate of completion was issued (1981), and that the plaintiffs claims were barred by the operation of those limitations well before the complaint was filed.

The plaintiff argues that the judge mistakenly read its complaint against Dryvit as being grounded on- improper installation of the exterior wall system rather than defects in its design; that its complaint presents essentially a products liability case; that the design defects were inherently unknowable at the time of construction and installation; that the discovery rule was, therefore, applicable to this action; and that summary judgment should not have been granted since genuine issues exist as to when the plaintiff knew or should have known that it had been harmed by the defendant’s conduct. 6

In the main, the judge’s reliance on Melrose was appropriate. Most of the plaintiffs claims against Dryvit relate to matters which could have been discovered by the architect and clerk of the works during the construction phase of the project. Any negligence of Dryvit in providing instructions (Count VII), in training and certification of installers (Count VIII), and in inspecting the wall construction (Count IX) was readily discoverable before completion of construction and, therefore, was not inherently unknowable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cooper v. Shabshelowitz
D. Massachusetts, 2025
Town of Princeton v. Monsanto Co., Solutia
202 F. Supp. 3d 181 (D. Massachusetts, 2016)
Insituform Technologies, Inc. v. Jacobs Civil, Inc.
30 Mass. L. Rptr. 384 (Massachusetts Superior Court, 2012)
Weiss v. Grolman
30 Mass. L. Rptr. 295 (Massachusetts Superior Court, 2012)
Downey v. Chutehall Construction Co.
30 Mass. L. Rptr. 403 (Massachusetts Superior Court, 2012)
Stewart Title Insurance v. Kelley
30 Mass. L. Rptr. 78 (Massachusetts Superior Court, 2012)
Graham v. Just A Start Corp.
28 Mass. L. Rptr. 569 (Massachusetts Superior Court, 2011)
Thelemaque v. Fremont Investment & Loan nka Fremont Reorganizing Corp.
28 Mass. L. Rptr. 430 (Massachusetts Superior Court, 2011)
FINANCIAL RESOURCES NETWORK, INC. v. Brown & Brown, Inc.
754 F. Supp. 2d 128 (D. Massachusetts, 2010)
Ellis v. DiPasquale
25 Mass. L. Rptr. 315 (Massachusetts Superior Court, 2009)
Trans-Spec Truck Service, Inc. v. Caterpillar Inc.
524 F.3d 315 (First Circuit, 2008)
Lambert v. Fleet National Bank
865 N.E.2d 1091 (Massachusetts Supreme Judicial Court, 2007)
Jones v. Hughey
794 N.E.2d 79 (Ohio Court of Appeals, 2003)
Barron v. Fidelity Magellan Fund
784 N.E.2d 634 (Massachusetts Appeals Court, 2003)
Fine v. Huygens, DiMella, Shaffer & Associates
783 N.E.2d 842 (Massachusetts Appeals Court, 2003)
Colameta v. Harris
13 Mass. L. Rptr. 701 (Massachusetts Superior Court, 2001)
Coady v. Marvin Lumber and Cedar Co.
167 F. Supp. 2d 166 (D. Massachusetts, 2001)
Eck v. Kellem
748 N.E.2d 1047 (Massachusetts Appeals Court, 2001)
Cigna Insurance v. OY Saunatec, Ltd.
241 F.3d 1 (First Circuit, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
560 N.E.2d 1290, 29 Mass. App. Ct. 440, 1990 Mass. App. LEXIS 577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hanson-housing-authority-v-dryvit-system-inc-massappct-1990.