Downey v. Chutehall Construction Co.

30 Mass. L. Rptr. 403
CourtMassachusetts Superior Court
DecidedMay 18, 2012
DocketNo. SUCV201002671A
StatusPublished

This text of 30 Mass. L. Rptr. 403 (Downey v. Chutehall Construction Co.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Downey v. Chutehall Construction Co., 30 Mass. L. Rptr. 403 (Mass. Ct. App. 2012).

Opinion

Fabricant, Judith, J.

This action arises from a dispute between plaintiffs Christopher and Mairead Downey, defendant Chutehall Construction Co. Ltd. (Chutehall), and third-party defendant The Follett Company, Inc. (Follett), regarding the installation of a rubber roof system on the Downeys’ residence in 2005. Before the Court are each party’s motion for summary judgment and related motions to strike and to supplement the record. For reasons that will be explained, the Downeys’ and Chutehall’s summary judgment motions will be denied, and Follett’s motion will be allowed.

BACKGROUND

The summary judgment record establishes the following facts as undisputed, except as indicated.1 Christopher and his wife Mairead Downey own a home in the Beacon Hill neighborhood of Boston. Sometime in 2004, the Downeys noticed a water stain on the ceiling of their fourth-floor bedroom. In or about September 2004, James Chute of Chutehall and Mr. Downey met to discuss the Downeys’ roof; they offer [404]*404varying versions of that conversation. As a result of that conversation, Chutehall submitted a written proposal to the Downeys, on Chutehall’s form, which described the proposed work as follows:

1. Supply, install & remove access scaffolding.

2. Remove & dispose of existing deck.

3. Strip off & dispose of existing roof system.

4. Supply & install a new fully adhered .060 EPDM rubber roofing membrane on 1 in. mechanically fastened “ISO” recovery board, including copper flashings & drip edges, termination bar, pipe boots, lap caulk seams etc.

5. Replace the deck, including P.T. sub framing, mahogany decking, and iron hand rail.

Next to each item was an estimated price. The proposal form stated, “All work to be completed in a professional manner according to standard practices. Any alteration or deviation from above specifications involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate.” Christopher Downey signed the form, accepting the proposal, on June 13, 2005.

Chutehall proceeded with roofing work on the Downeys’ house in June or July 2005. It did not strip off and remove the existing roof, as proposed; instead, it laid the new roof on top of the old. How and why that occurred is a matter of dispute between the parties. According to Chute’s deposition testimony, Downey told him that the roof had been stripped 10 to 12 years earlier, so that it had only one roofing layer. Downey also, according to Chute, prohibited Chutehall from stripping the existing roof, or even making test cuts in it to determine how many layers existed. Downey denies having made any such statements, and denies having done anything to prevent Chutehall from stripping the existing roof.

At the completion of its work in July 2005, Chutehall sent the Downeys a document entitled “Application for Payment,” which listed the completed work, with an amount for each item:

1. Supply and install scaffolding.

2. Remove and dispose of existing deck.

3. Strip & slit existing roof system for ventilition [sic], install pressure treated sleepers to support new deck & drip edges, dispose of debris.

4. Supply and install new rubber roof.
5. Replace deck and hand rail etc.

Additional cost of hand rail over and above that allowed for in our proposal (40ft @ $55.00. v. 56ft @ $70.00./ft. [sic].

The total amount claimed corresponded to the amount set forth in the original proposal, plus the additional amount indicated for the handrail that had not been included in the original proposal.

Shortly after Chutehall completed its job, the Downeys again noticed a water stain on the ceiling in the fourth-floor bedroom. They notified Chutehall. Attributing the stain to a blocked gutter, Chutehall cleared the gutter. The stain nevertheless continued to grow, according to the Downeys, but they did not so inform Chutehall. The Downeys paid Chutehall’s bill in October 2005.

Four years later, in the summer of 2009, the Downeys sought to install an HVAC unit in an area over the fourth-floor bedroom. The Downeys’ contractor, John Canavan, cut a hole in the roof to install the HVAC unit, and noticed, according to his deposition testimony, that the roof insulation was wet. On Canavan’s suggestion, the Downeys engaged Follett and J.M. Lydon Corp. (Lydon), both roofing contractors, to inspect the roof.

Follett performed test cuts, and submitted a report to the Downeys dated August 11, 2009. The Follett report stated, in its entirety:2

1. The flat roof system consist of 4 different roof systems. There are 2 tar and gravel roof and 2 EPDM roofs. The top roof consist [sic] of .060 EPDM fully adhered to isosuranurate insulation. This roof was installed over a EPDM roof system that had. fiberboard roof insulation that was soaking wet The wet insulation will cause the newer roof system to fail. When the new roofs insulation is secured the screw penetrate the secondary EPDM roof and allow the water to infiltrate the new roof system. Also wetness around securement screws and heat from the summer will cause the screws to back out and puncture the new roof system.

2. Because of the wetness of the existing roof there will problems [sic] under the wood deck. The weight of the wood deck over a wet roof system will eventually compress the area under its supports and puncture the roof system.

We recommend removing all the roof systems in their entirety so as to expose the wood substrate. After this is completed a new EPDM roof can be installed in a clean, diy and correct manor.

Lydon provided the Downeys with a written proposal for installation of a new roof. That document included the following:

Existing surface has three different roofs the first one being a three/four ply asphalt roof mopped directly to wood deck, the second one is a EPDM roof on half inch fibreboard [sic] which is saturated and the top one being EPDM over one inch polyisocyanurate insulation. This roof would be adequate if it was not installed over a wet roof It has a leak at base of roof access stair enclosure were roof membrane was installed over metal panels.

(Emphasis added.) Lydon’s second affidavit clarifies that he made observations of an area of the roof that had been opened by the contractor, “including saturated fibreboard under a secondary roofing layer of EPDM, which was under the top roof layer of EPDM over one [405]*405inch polyisocyanurate insulation." He goes on, “I was not looking for the source of the water saturating the fibreboard ... I was only describing my observations that day. I do not know when or how the fibreboard became wet ... I was not suggesting that whoever installed the top roof layer did so over wet fibreboard.”

After receiving these reports from Lydon and Follett, Christopher Downey consulted an attorney. On advice of the attorney, he sought an opinion from an engineering firm, Simpson, Gumpertz and Heger (SGH).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sheehan v. Tobin
93 N.E.2d 524 (Massachusetts Supreme Judicial Court, 1950)
Stone v. Essex County Newspapers, Inc.
330 N.E.2d 161 (Massachusetts Supreme Judicial Court, 1975)
McAvoy v. Shufrin
518 N.E.2d 513 (Massachusetts Supreme Judicial Court, 1988)
Fleming v. Benzaquin
454 N.E.2d 95 (Massachusetts Supreme Judicial Court, 1983)
Hendrickson v. Sears
310 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1974)
Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
Fall River Hous. Auth. v. HV COLLINS CAPE COD LATH
604 N.E.2d 1310 (Massachusetts Supreme Judicial Court, 1992)
White v. Peabody Construction Co., Inc.
434 N.E.2d 1015 (Massachusetts Supreme Judicial Court, 1982)
Jones v. Taibbi
512 N.E.2d 260 (Massachusetts Supreme Judicial Court, 1987)
Correllas v. Viveiros
572 N.E.2d 7 (Massachusetts Supreme Judicial Court, 1991)
Community National Bank v. Dawes
340 N.E.2d 877 (Massachusetts Supreme Judicial Court, 1976)
McGuinness v. Cotter
591 N.E.2d 659 (Massachusetts Supreme Judicial Court, 1992)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Hanson Housing Authority v. Dryvit System, Inc.
560 N.E.2d 1290 (Massachusetts Appeals Court, 1990)
New England Tractor-Trailer Training of Connecticut, Inc. v. Globe Newspaper Co.
480 N.E.2d 1005 (Massachusetts Supreme Judicial Court, 1985)
DiMarzo v. American Mutual Insurance
449 N.E.2d 1189 (Massachusetts Supreme Judicial Court, 1983)
Oliveira v. Pereira
605 N.E.2d 287 (Massachusetts Supreme Judicial Court, 1992)
Kohl v. Silver Lake Motors, Inc.
343 N.E.2d 375 (Massachusetts Supreme Judicial Court, 1976)
Thurlow v. Town of Provincetown
149 N.E.2d 901 (Massachusetts Supreme Judicial Court, 1958)
Fahy v. Melrose Free Press Inc.
10 N.E.2d 187 (Massachusetts Supreme Judicial Court, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
30 Mass. L. Rptr. 403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/downey-v-chutehall-construction-co-masssuperct-2012.