Massachusetts Housing Opportunities Corp. v. Whitman & Bingham Associates, P.C.

983 N.E.2d 734, 83 Mass. App. Ct. 325, 2013 WL 617054, 2013 Mass. App. LEXIS 30
CourtMassachusetts Appeals Court
DecidedFebruary 21, 2013
DocketNo. 12-P-53
StatusPublished
Cited by7 cases

This text of 983 N.E.2d 734 (Massachusetts Housing Opportunities Corp. v. Whitman & Bingham Associates, P.C.) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Massachusetts Housing Opportunities Corp. v. Whitman & Bingham Associates, P.C., 983 N.E.2d 734, 83 Mass. App. Ct. 325, 2013 WL 617054, 2013 Mass. App. LEXIS 30 (Mass. Ct. App. 2013).

Opinion

Graham, J.

After a wastewater treatment plant for one of its development projects vastly exceeded projected costs, the plaintiff, Massachusetts Housing Opportunities Corporation (MHOC), [326]*326filed a complaint alleging tort claims (counts I - III), breach of contract (count IV), and violation of G. L. c. 93A (count V) against the defendants, engineering firms Whitman & Bingham Associates, P.C. (Whitman), and Aquapoint, Inc. (Aquapoint).2 A judge of the Superior Court granted the defendants’ motion for summary judgment, and MHOC appeals. It argues that the judge erred in concluding that its tort and contract claims are barred by the applicable statute of limitations, and that its c. 93A claim is without support in the record. We affirm.

Background. The undisputed facts, viewed in the light most favorable to the nonmoving party, MHOC, are as follows. In 2003, MHOC, a property development corporation, was in the process of developing a condominium project in Sterling (development). On October 2, 2003, it entered into an agreement with Whitman to design “a subsurface sewage disposal system” (septic system) for the development. Whitman, in turn, hired Aquapoint to provide information about sewage treatment equipment and permitting advice. Whitman began work on the design, and, in November, 2004, told MHOC that the septic system could be permitted relatively inexpensively under the Department of Environmental Protection’s (DEP) Title 5 alternative system for piloting program (piloting program).3 Thereafter, on December 15, 2004, Whitman submitted an application under the piloting program on behalf of MHOC. MHOC signed the application and paid the $430 filing fee by check. Also in December, 2004, MHOC received a $300,000 bid from a third party, M.P. Crowley, to construct the septic system as designed by Whitman.4

Shortly after the piloting program application was submitted, DEP instructed Whitman that it must instead file an application for a major groundwater discharge permit (MGD permit). Whitman, in turn, told MHOC of DEP’s instructions. On January 7, 2005, Whitman submitted a new MGD permit application on [327]*327behalf of MHOC for the construction of a “wastewater treatment” plant. Again, MHOC signed the application and paid the now $13,445 filing fee. Despite the change in permit sought and the dramatically increased filing fee, Whitman submitted the same design it had already created for the piloting program.

On February 3, 2005, DEP informed MHOC that Whitman’s design was “administratively deficient” in numerous identified respects. Neither MHOC nor Whitman remedied any of the perceived problems and, on April 1, 2005, DEP formally rejected Whitman’s MOD permit application, identifying forty-two deficiencies to be remedied before a permit could issue. Whitman eventually modified the original design to meet the specified requirements, essentially transforming its original septic system design “to a full-blown sewer treatment plant.” Both parties then worked with DEP to expedite its review and approval of the application.

After receiving the modified design, on May 10, 2005, Aqua-point submitted to MHOC a $288,611.65 “final bid” for the materials to construct the wastewater treatment plant. The figure did not include labor costs. At about the same time, M.P. Crowley told MHOC that, because of the design changes, it was withdrawing its prior bid of $300,000. DEP approved Whitman’s new design in June, 2005, and construction commenced. The Whitman-designed wastewater treatment plant eventually cost MHOC more than $700,000.

On May 23, 2008, MHOC filed a complaint in the Superior Court against the defendants alleging professional malpractice, negligent misrepresentation, fraud, breach of contract, and violations of c. 93A. At their core, the claims are largely premised on an alleged promise made by Whitman on at least two separate occasions that the wastewater treatment plant would not cost more than $200,000. According to MHOC, it was not until June, 2005, that it became aware of the full cost to build the wastewater treatment plant.

The defendants thereafter moved for summary judgment, arguing that the tort and breach of contract claims were time barred. The judge agreed, concluding that a three-year statute of limitations applied to those claims, and that MHOC had notice of its alleged injuries more than three years prior to the filing [328]*328date. The judge also concluded that the defendants were entitled to judgment on the c. 93A claim, as “nothing within the summary judgment record . . . indicate[s] [that] the purpose of these misrepresentations/omissions was coercive or extortionate.” This appeal followed.

Discussion. Summary judgment is appropriate where there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law. See Mass.R.Civ.P. 56(c), as amended, 436 Mass. 1404 (2002); Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). “We review a grant of summary judgment de nova, construing all facts in favor of the nonmoving party.” Miller v. Cotter, 448 Mass. 671, 676 (2007).

a. Statute of limitations, i. Tort claims. “Tort claims in Massachusetts are governed by the three-year limitations period set forth in G. L. c. 260, § 2A, amended by St. 1973, c. 777, § 1.” Doherty v. Admiral’s Flagship Condominium Trust, 80 Mass. App. Ct. 104, 107 (2011). Therefore, in this case, MHOC’s negligence and other tort claims must have accrued on or after May 23, 2005, “or fall under the protection of an applicable exception, to be within the statutory limitations period.” Ibid. Although the permitting process had begun well before that date, MHOC maintains that its action was tolled by the discovery rule because it was not until June, 2005, that it became aware of the actual cost of the wastewater treatment plant.

“Under our discovery rule, a cause of action for negligence accrues when ‘a plaintiff knows or reasonably should know that it has sustained appreciable harm as a result of a defendant’s negligence.’ ” Khatchatourian v. Encompass Ins. Co. of Mass., 78 Mass. App. Ct. 53, 57 (2010), quoting from Massachusetts Elec. Co. v. Fletcher, Tilton & Whipple, PC., 394 Mass. 265, 268 (1985). “What a plaintiff knew or should have known is a question of fact that is often unsuited for summary judgment. . . . However, ‘when the facts regarding discovery of harm are undisputed, the question may be decided as matter of law.’ ” Ibid., quoting from Vinci v. Byers, 65 Mass. App. Ct. 135, 139 (2005).

In its complaint, MHOC alleges that Whitman negligently failed to identify the proper waste disposal system for the [329]*329development, and supplied false and misleading information to MHOC about the size and scope of that system, its permitting costs, and the rejection of the December 15, 2004, permit application. These failures and omissions, it contends, caused it to suffer economic harm that it did not discover until June of 2005, when DEP finally approved the modified design and “the system went from $300,000 to $800,000.”

The argument is unconvincing. Assuming MHOC was injured as alleged, it reasonably should have been aware of the escalating cost of the system well before June, 2005.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sawyer-Mackie v. Corcym, Inc.
D. Massachusetts, 2023
Trindade v. Grove Services, Inc.
D. Massachusetts, 2020
Stanley v. Black
D. Massachusetts, 2019
Stanley v. Schmidt
369 F. Supp. 3d 297 (District of Columbia, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
983 N.E.2d 734, 83 Mass. App. Ct. 325, 2013 WL 617054, 2013 Mass. App. LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massachusetts-housing-opportunities-corp-v-whitman-bingham-associates-massappct-2013.