Blue Cross & Blue Shield of North Carolina v. Odell Associates, Inc.

301 S.E.2d 459, 61 N.C. App. 350, 1983 N.C. App. LEXIS 2685
CourtCourt of Appeals of North Carolina
DecidedApril 5, 1983
Docket8215SC412
StatusPublished
Cited by21 cases

This text of 301 S.E.2d 459 (Blue Cross & Blue Shield of North Carolina v. Odell Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Blue Cross & Blue Shield of North Carolina v. Odell Associates, Inc., 301 S.E.2d 459, 61 N.C. App. 350, 1983 N.C. App. LEXIS 2685 (N.C. Ct. App. 1983).

Opinion

HILL, Judge.

Parties and Relationships

We first identify the parties to this lawsuit:

1. Plaintiff Blue Cross is a nonprofit corporation with its registered and principal office in Orange County, North Carolina, near the City of Chapel Hill.

2. Odell is a North Carolina corporation engaged in architecture and engineering. On or about 5 December 1969, Blue Cross entered into a contract with Odell in which Odell agreed to prepare plans and specifications for the construction of a building to be used as a service center for Blue Cross. Under the contract, Odell was to prepare plans, drawings, and specifications and provide architectural services incident to the general administration of the construction contract. For its services Odell was to be paid $500,000.

3. On or about 16 February 1971, Blue Cross entered into a contract with defendant Teer, engaging Teer as general contractor and providing that Teer was to be fully responsible for construction.

4. On or about 16 February 1971, the defendant USF&G entered into a contract with Teer in which USF&G as surety and Teer as principal became bound to Blue Cross in the sum of $8,000,000 conditioned upon Teer’s prompt and faithful performance of the construction contract.

*353 5. On or about 29 December 1970, the defendant subcontractor General Specialties undertook in conjunction with Odell to design a glass curtainwall that in substance would constitute the outside area of the building, and in conjunction with Teer to build the curtainwall. General Specialties promised as follows: “For two years from the date of acceptance by owner, we guarantee the entire curtainwall against structural failure and water penetration to the building interior.”

6. On or about 6 April 1972, Hartford executed a performance bond under which General Specialties as principal and Hartford as surety became bound to Teer.

7. LOF manufactured and supplied the glass panels used in construction of the curtainwall. It also assisted defendants Odell and General Specialties in the design and preparation of plans for the curtainwall and glazing procedures, by reviewing the drawings and specifications prepared by Odell and General Specialties, by conducting tests, and by meeting with Blue Cross and giving assurances regarding the performance of the glass panels comprising the curtainwall.

By this lawsuit, Blue Cross seeks to recover damages to compensate the cost of replacing glass panels that have failed and the cost of remedial measures that will be necessary to eliminate further failure of the panels.

As to the defendant Odell, Blue Cross has asserted claims for breach of contract and negligence; as to Teer, for breach of contract and breach of warranty; as to General Specialties, for negligence and breach of express warranty; as to LOF, for breach of implied warranty, negligence, breach of express warranty and strict liability; and as to USF&G and Teer, for breach of contract and of the performance bond executed by Teer and USF&G; Blue Cross further alleges that all the defendants are jointly and severally liable for the damages sustained by plaintiff.

Each defendant filed responsive pleadings, asserting, among other things, absence of liability and that in any event Blue Cross’s claims were barred by the statute of limitations. Various cross claims were asserted among the defendants; and, in addition, defendant Teer filed a third party complaint against Hartford, General Specialties’ bonding company, asserting Teer’s right *354 to recover from Hartford should Teer be found liable to plaintiff. An order was entered severing the part of the case dealing with the curtainwall.

The trial judge entered an order and judgment granting LOF’s motion for partial summary judgment and granting the motions for summary judgment of Odell, Teer, General Specialties and USF&G from which Blue Cross appeals. The trial judge entered an order and judgment denying Hartford’s motion for summary judgment against Teer and USF&G, and Hartford appeals.

The Building

The four walls of the building, called the curtainwall, are composed primarily of approximately 4800 glass panels and rise three stories above a ground level lobby area. The four sides of the building are sloped, the north and east sides facing the sky at a 45° angle, and the south and west sides facing the ground at a 45° angle. The glass panels consist of two glass panes one-fourth inch thick with one-half inch vacuum space between the panes. These panels are supported on metal frames. As designed, the panels have superior insulating qualities if the seals separating the two panes of glass are intact. Seals on a substantial number of units have failed, depriving the panels of their insulating quality; have become clouded because of vapor between the panes which has impaired visibility; and have become a threat to the safety of employees who work in the building. Conceivably, almost all the panels in the north and east sides are defective and will need to be replaced soon.

The following dates will aid in a general understanding of the lawsuit;

1. Blue Cross-Odell Contract — 27 October 1969.

2. Blue Cross-Teer Contract — 16 February 1971.

3. Teer-General Specialties Subcontract — 28 January 1972.

4. Building Occupied — Summer, 1973.

5. First unit observed to have failed because of fogging and condensation — 29 April 1975.

*355 6. Inspection visit by Mr. Coleman of LOF — last week of September, 1975.

7. First letter from Mr. Coleman of LOF to Blue Cross — 2 October 1975.

8. Meeting between representatives of Blue Cross, Odell, Teer and LOF to discuss the problem — 16 March 1976.

9. Second letter from Mr. Coleman of LOF to Blue Cross —12 April 1976.

10. Suit instituted — 16 March 1979.

Although all parties deny responsibility, there is evidence in the record that some of the panels failed because of one or more of the following reasons:

1. The panels were so designed and constructed that the perimeter seals did not prevent moisture and water from penetrating around and through the dividers into the area between the glass panes. This occurred because the sealing material was not uniformly applied, and/or the sealant over the metal was not waterproof, permitting water to reach the metal and cause it to rust. Water then entered between the panes.

2. The “leak and weep” system did not work properly so as to permit the water to run off.

3. The mullion covers — even if properly designed — were not affixed and sealed properly.

Initially, LOF attempted to cancel its twenty-year warranty to furnish the panels for replacement, but in the course of discovery agreed to reinstate the warranty and furnish the panels for a one-time replacement. LOF, therefore, did not move for summary judgment on plaintiffs claims of express warranty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

OH Tacoma 1 Subi, a Series of OH Tacoma 1 Tr. v. Newsome
Court of Appeals of North Carolina, 2025
Crescent Foods, Inc. v. Evason Pharmacies, Inc.
2016 NCBC 73 (North Carolina Business Court, 2016)
Williams v. HOUSES OF DISTINCTION, INC.
714 S.E.2d 438 (Court of Appeals of North Carolina, 2011)
Rowell v. North Carolina Equipment Co.
552 S.E.2d 274 (Court of Appeals of North Carolina, 2001)
Markham v. Nationwide Mutual Fire Insurance
481 S.E.2d 349 (Court of Appeals of North Carolina, 1997)
Dunes South Homeowners Ass'n, Inc. v. First Flight Builders, Inc.
459 S.E.2d 477 (Supreme Court of North Carolina, 1995)
Dunes South Homeowners Ass'n, Inc. v. First Flight Builders, Inc.
451 S.E.2d 636 (Court of Appeals of North Carolina, 1994)
Kingston Housing Authority v. Sandonato & Bogue, Inc.
577 N.E.2d 1 (Massachusetts Appeals Court, 1991)
Bonestell v. North Topsail Shores Condominiums, Inc.
405 S.E.2d 222 (Court of Appeals of North Carolina, 1991)
McAdoo v. City of Greensboro
372 S.E.2d 742 (Court of Appeals of North Carolina, 1988)
Asheville School v. D. v. Ward Construction, Inc.
337 S.E.2d 659 (Court of Appeals of North Carolina, 1985)
Square D Co. v. C. J. Kern Contractors, Inc.
334 S.E.2d 63 (Supreme Court of North Carolina, 1985)
Pembee Mfg. Corp. v. Cape Fear Const. Co., Inc.
329 S.E.2d 350 (Supreme Court of North Carolina, 1985)
Square D Co. v. C. J. Kern Contractors, Inc.
318 S.E.2d 527 (Court of Appeals of North Carolina, 1984)
Pembee Mfg. Corp. v. Cape Fear Construction Co.
317 S.E.2d 41 (Court of Appeals of North Carolina, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
301 S.E.2d 459, 61 N.C. App. 350, 1983 N.C. App. LEXIS 2685, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blue-cross-blue-shield-of-north-carolina-v-odell-associates-inc-ncctapp-1983.