Mosesian v. Franki Foundation Corp.

8 Mass. L. Rptr. 629
CourtMassachusetts Superior Court
DecidedJune 24, 1998
DocketNo. 946682
StatusPublished

This text of 8 Mass. L. Rptr. 629 (Mosesian v. Franki Foundation Corp.) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mosesian v. Franki Foundation Corp., 8 Mass. L. Rptr. 629 (Mass. Ct. App. 1998).

Opinion

Butler, J.

Plaintiffs Charles Mosesian (“Mosesian”) and Coolidge Avenue 125 Corporation (“125 Corp.”) bring this action against defendant Franki Foundation Corporation (“Franki”) alleging breach of warranty and negligence. Franki moves for summary judgment on the grounds that plaintiffs have failed to bring this action within the six-year period allowed under the [630]*630applicable statute of repose, G.L.c. 260, §2B and have failed to state a claim as to Counts I and II (breach of contract counts). For the following reasons, Franki’s motion for summary judgment is DENIED in part, and ALLOWED in part.

BACKGROUND

The following undisputed facts are taken from the pleadings and affidavits.

In the beginning of 1986, Mosesian was the developer, and 125 Corp. was the developer and general contractor, of Horizon East Condominiums, an eighty-four residential unit project in Watertown, Massachusetts. On July 2, 1986, Mosesian accepted Franki’s written proposal to provide the labor, materials and equipment for the installation of pressure injected footings (“PIFs") that would provide the support for the condominiums. Franki provided the specifications of the PIFs, including that each would have a weight capacity of up to 120 tons. In addition, the contract provided certain guarantees regarding the performance of the PIFs.2 Franki began work on June 19, 1986, and by August 11, 1986, the installation was complete.

After Franki completed its work, Mosesian requested a letter describing the contractual guarantee. In response, on November 24, 1986, Franki sent a letter that described the guarantee as follows:

We guarantee that our foundation units will satisfactorily support the loads shown in the contract plans and specifications. Where cohesive soil subject to consolidation occurs below the agreed bearing stratum for our units, we assume responsibility for satisfactoiy transfer of structural loads to the bearing stratum, but the purchaser shall predict and design for possible long term settlement of the bearing stratum itself.
If our foundation units do not perform in accordance with our guarantee, we will at our cost, repair or replace all resultant structural damages.3
We shall not be held to this guarantee in the event of (i) loading in excess of or of a type differing from that shown in the plans and specifications or (ii) interference, whether of natural or human origin, with the vertical or lateral support provided to our foundation units by the sub-soil. This guarantee on workmanship and materials of a period of one (1) year past acceptance by the owner.

(Emphasis added.)4

During Franki’s work, Mosesian questioned whether the piles were being driven deeply enough and whether the machine being used by Franki was adequate for the job. In response to his questions, Robert Barry, vice president of Franki, assured Mosesian that the piles were being driven to the proper depths and that the pile driving machine was adequate. In 1987, Mosesian completed payment on Franki’s invoices.

Two years after Franki had completed its work, an occupancy permit was issued by the Town of Water-town on August 12, 1988, for six of the eighty-four units, including unit 101. The occupancy permit was issued on a hardship basis to accommodate six prospective purchasers who had entered into purchase agreements for condominium units and who had either sold their prior residences or given notice to their landlords in reliance on the purchase agreements. These occupants were allowed to occupy the six emits after the partial occupancy permit was issued: however, they did not pay rent for the use of the emits and did not own the units at that time.5

As of August 12, 1988, the date of issuance of the partial occupancy permit, the following work still needed to be completed: engineering and welding work, unrelated to the subsequently discovered foundation problems, to ensure that the condominiums satisfied the applicable wind and earthquake resistance standards: installing hand railings throughout the condominiums: and carpeting the common areas. The full occupancy permit was issued on November 21, 1988.6

In late 1993, Mosesian noticed various cracks on the northeastern corner of the building and what appeared to be unusual settlement of unit 101, which was on the first floor of the building. In early 1994, Mosesian hired a consultant to investigate the cause and extent of the problems. The consultant determined that one section of the foundation had settled between two and two and one-half inches.7

Franki was informed about the settlement and it subsequently inspected the building. After discussions with Mosesian, Franki refused to correct the settlement problem. The work needed to repair the settlement and the resultant damage has not been completed.

On November 18, 1994, this complaint was filed, alleging the following causes of action:

Count 1: Mosesian v. Franki:
Breach of Contract
Count 11: 125 Corp. v. Franki:
Breach of Contract (125 Corp. as intended third-party beneficiaiy)
Count III: Mosesian and 125 Corp. v. Franki: Negligence
Count IV: Mosesian and 125 Corp. v. Franki: Indemnification
Count V: Mosesian and 125 Corp. v. Franki: Contribution

DISCUSSION

Summary judgment must be granted where there are no material facts in dispute and the moving party is entitled to judgment as a matter of law. Cassesso v. Commissioner of Correction, 390 Mass. 419, 422 (1983); Mass.R.Civ.P. 56(c). The moving party bears [631]*631the burden of affirmatively demonstrating the absence of a triable issue and that the moving party is entitled to judgment as a matter of law. Pederson v. Time, Inc., 404 Mass. 14, 16-17 (1989). “If the moving party establishes the absence of a triable issue, the party opposing the motion must respond and allege specific facts which would establish the existence of a genuine issue of material fact in order to defeat a motion for summary judgment.” Id. at 17. The opposing party cannot rest on its pleadings and mere assertions of disputed facts to defeat the motion for summary judgment. LaLonde v. Eissner, 405 Mass. 207, 209 (1989).

Defendant seeks summary judgment, arguing that G.L.c. 260, §2B bars all counts because all claims sound in tort, and alternatively, that Counts I and II, alleging breach of warranty, do not state a claim because the warranty provided to the plaintiffs was for one year only.8 Plaintiffs counter that Section 2B is inapplicable to Counts I, II, IV and V because they are contract claims, and that alternatively, if Section 2B is applicable, the claims are still timely because the statute did not begin to run until the full occupancy permit was issued on November 21, 1988.

Statute of Repose — G.L.c. 260, §2B

General Laws c. 260, Section 2B provides in pertinent part that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
LaLonde v. Eissner
539 N.E.2d 538 (Massachusetts Supreme Judicial Court, 1989)
Hoffman v. Howmedica, Inc.
364 N.E.2d 1215 (Massachusetts Supreme Judicial Court, 1977)
Anthony's Pier Four, Inc. v. Crandall Dry Dock Engineers, Inc.
489 N.E.2d 172 (Massachusetts Supreme Judicial Court, 1986)
Cassesso v. Commissioner of Correction
456 N.E.2d 1123 (Massachusetts Supreme Judicial Court, 1983)
Kingston Housing Authority v. Sandonato & Bogue, Inc.
577 N.E.2d 1 (Massachusetts Appeals Court, 1991)
Condon v. Haitsma
90 N.E.2d 549 (Massachusetts Supreme Judicial Court, 1950)
Klein v. Catalano
437 N.E.2d 514 (Massachusetts Supreme Judicial Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
8 Mass. L. Rptr. 629, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mosesian-v-franki-foundation-corp-masssuperct-1998.