Jesse F. Heard & Sons v. Southwest Steel Products

124 So. 2d 211, 1960 La. App. LEXIS 1141
CourtLouisiana Court of Appeal
DecidedOctober 27, 1960
Docket9269
StatusPublished
Cited by28 cases

This text of 124 So. 2d 211 (Jesse F. Heard & Sons v. Southwest Steel Products) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jesse F. Heard & Sons v. Southwest Steel Products, 124 So. 2d 211, 1960 La. App. LEXIS 1141 (La. Ct. App. 1960).

Opinion

124 So.2d 211 (1960)

JESSE F. HEARD & SONS et al., Plaintiff-Appellee,
v.
SOUTHWEST STEEL PRODUCTS et al., Defendant-Appellant.

No. 9269.

Court of Appeal of Louisiana, Second Circuit.

October 27, 1960.
Rehearing Denied December 1, 1960.
Certiorari Denied January 9, 1961.

*212 Diehlmann C. Bernhardt, Monroe, Butler, Binion, Rice & Cook, Houston, Tex., for appellants.

Howell H. Heard, West Monroe, for appellees.

GLADNEY, Judge.

This suit was instituted for the purpose of canceling and erasing from the mortgage records of Lincoln Parish, Louisiana, an affidavit of materialman's lien filed pursuant to the provisions of LSA-R.S. 38:2241 to 38:2247, and to recover damages for the wrongful filing thereof. Jesse F. Heard & Sons (hereinafter sometimes called Heard) and Employer's Liability Assurance Corporation, Ltd., plaintiffs herein, name as defendants Southwest Steel Products, R. *213 Boatner Howell, Jr. as Trustee in Bankruptcy for Industrial Fabricators, Inc., and L. C. Ledbetter, Clerk of Court of Lincoln Parish. Following trial, judgment was rendered favorable to plaintiffs, directing the cancellation of the recorded affidavit but rejecting plaintiffs' demand for damages. An appeal was perfected to this court by Southwest Steel Products.

The following circumstances, concerning which there is no dispute, are pertinent to a proper resolution of the case: On September 9, 1958, Jesse F. Heard & Sons, a partnership engaged in the building and construction business, entered into a written contract with the Louisiana State Board of Education, wherein it was agreed that for the price of $584,446 the contractor would furnish all labor and materials necessary for the construction of a Student Union Building at Grambling College, in Lincoln Parish, Louisiana. In accordance with the statute regulating the claims of materialmen and laborers on public works (LSA-R.S. 38:2241 et seq.), the contractor executed a surety bond with Employer's Assurance Corporation, Ltd. as surety, which bond was duly recorded in the mortgage records of Lincoln Parish. The partnership then entered into a contract with Industrial Fabricators, Inc., whereby the latter agreed to furnish certain structural steel and miscellaneous items requiring special fabrication in order to comply with the detailed architectural plans and specifications. This agreement was executed on a printed form customarily used by Heard for subcontractors. Heard, however, contends such form was used in this instance through error. Industrial Fabricators, Inc., in turn, contracted with Southwest Steel Products for the latter to fabricate in its own shop and deliver to the job site at Grambling College, all of the joists and long spans. After delivery by Southwest Steel Products the materials were incorporated into the structure by O. C. Portman, plaintiff's subcontractor for the erection and assembly of the steel. Neither Industrial Fabricators, Inc., nor Southwest Steel Products engaged in any work on the structure itself.

On June 25, 1959, Industrial Fabricators, Inc., was adjudicated a bankrupt, and at that time was indebted to Southwest Steel Products for $4,591 for the materials fabricated and delivered. On July 3, 1959, Southwest Steel Products filed its affidavit of lien for the balance due it, together with a claim for twenty-five per cent as attorney's fees and $100 as costs for preparation in filing of the lien.

Appellant assigns error based on two propositions: (1) that Industrial Fabricators, Inc., was a subcontractor by virtue of the express written contract with Heard; and (2) that one who specially fabricates steel for a given project is a subcontractor regardless of where the work is performed.

The first contention impresses us as being without merit for two reasons: first, because the petition alleges the form employed was the result of an error, proof of which was established to our satisfaction and that of the trier of facts; and second, whether or not one is a subcontractor within the purview of the lien statute must be resolved from essential factors of legal significance other than simple designation as such by the prime contractor.

The other point advanced in argument by counsel for Southwest Steel Products is the primary issue for this court's disposition. Was the relationship of Industrial Fabricators, Inc., and Heard that of subcontractor and contractor? If so, the proper recordation of its claim by Southwest Products gave rise to a valid and subsisting lien by virtue of the provisions of LSA-R.S. 38:2242. Contrariwise, if the relationship of said parties was simply that of vendor and vendee, the statute does not create a lien in favor of Southwest Products.

As heretofore disclosed, Industrial Fabricators, Inc., agreed with Heard, the prime contractor, to furnish specially fabricated steel according to specifications and deliver such finished material to the job site. This *214 it did through its agent or contractor, Southwest Steel Products.

The learned judge a quo has supported his judgment by lengthy, sound, written reasons which are in the record. After a careful study of the testimony and the documentary evidence adduced, we are of the opinion he has clearly defined the issues, made correct factual findings, and sufficiently reviewed pertinent jurisprudence. We find ourselves wholly in accord with the judgment rendered by him, and have decided to adopt, with some omissions, his reasons. They are as follows, viz.:

"So the important issue which is presented to the Court in this case is to determine the relationship between Industrial Fabricators, Inc. and Jesse F. Heard and Sons, for if Industrial Fabricators, Inc. is held to be simply a materialman and not a sub-contractor, the result will be that Southwest Steel Products is not legally entitled to a lien against the public building. On the other hand, if Industrial Fabricators, Inc. is legally a sub-contractor, then the Southwest Steel Products is entitled to a legal and valid lien against the building and the project.

"On the trial of the case, objection was made to the admissibility of any evidence which sought to contradict or vary the terms of the written agreement between Jesse F. Heard and Sons and Industrial Fabricators, Inc. But by virtue of the fact that there was a proper allegation of error, the Court was of the opinion that such testimony was admissible and the testimony was admitted and it was very definitely proven and established that Jesse F. Heard and Sons actually committed error in using the form which it designated as a subcontractor form instead of its usual form for the purchase of materials to be used in such projects.

"Furthermore, the testimony was admissible, in the opinion of the Court, for the reason that the contract itself was rather ambiguous since it contained the following stipulation, `It is agreed that the following is the materials to be furnished and the work to be done by sub-contractor under the sub-contract, to-wit: Structural steel and miscellaneous items including stone anchors, miscellaneous bolts and anchors according to plans and specifications.' So that from the contract itself, it may be observed that apparently there was no intention or understanding on the part of the parties to such agreement that Industrial Fabricators, Inc. were to do any more than simply furnish the structural steel and miscellaneous items, including the stone anchors, bolts and other items according to the plans and specifications. In fact, the testimony shows that both of the parties to the agreement, that is, Jesse F.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ETI, Inc. v. Buck Steel, Inc.
211 So. 3d 439 (Louisiana Court of Appeal, 2017)
Jean Simpson Personnel v. G & G Concrete
803 So. 2d 992 (Louisiana Court of Appeal, 2001)
Wilson Industries, Inc. v. Aviva America Inc.
185 F.3d 492 (Fifth Circuit, 1999)
WILSON INDUSTRIES, INC. v. Aviva America, Inc.
63 F. Supp. 2d 747 (E.D. Louisiana, 1999)
Opinion Number
Louisiana Attorney General Reports, 1998
AFCO Metals, Inc. v. Tudor Construcution Co.
571 So. 2d 698 (Supreme Court of Louisiana, 1990)
Vulcraft v. Midtown Business Park, Ltd.
800 P.2d 195 (New Mexico Supreme Court, 1990)
Wilkin v. Dev Con Builders, Inc.
561 So. 2d 66 (Supreme Court of Louisiana, 1990)
JAVELER CONST. CO., INC. v. Federal Ins. Co.
472 So. 2d 258 (Louisiana Court of Appeal, 1985)
Hauserman, Inc. v. Roussel-Hart General Contractors
395 So. 2d 800 (Supreme Court of Louisiana, 1981)
Slagle-Johnson Lumber, Inc. v. Landis Construction Co.
366 So. 2d 206 (Louisiana Court of Appeal, 1978)
LEONARD B. HERBERT, JR. & CO., INC. v. Kinler
336 So. 2d 922 (Louisiana Court of Appeal, 1976)
Thurman v. Star Electric Supply, Inc.
307 So. 2d 283 (Supreme Court of Louisiana, 1975)
Thurman v. Star Electric Supply, Inc.
294 So. 2d 255 (Louisiana Court of Appeal, 1974)
Gifford Hill & Co. v. Harper
262 So. 2d 842 (Louisiana Court of Appeal, 1972)
In re Wallace Lincoln-Mercury, Inc.
326 F. Supp. 1243 (W.D. Louisiana, 1971)
Continental Casualty Co. v. Associated Pipe & Supply Co.
310 F. Supp. 1207 (E.D. Louisiana, 1969)
Dupree v. Gaubert Industries, Inc.
277 F. Supp. 321 (W.D. Louisiana, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
124 So. 2d 211, 1960 La. App. LEXIS 1141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jesse-f-heard-sons-v-southwest-steel-products-lactapp-1960.