Thurman v. Star Electric Supply, Inc.

307 So. 2d 283
CourtSupreme Court of Louisiana
DecidedJanuary 20, 1975
Docket54972
StatusPublished
Cited by22 cases

This text of 307 So. 2d 283 (Thurman v. Star Electric Supply, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thurman v. Star Electric Supply, Inc., 307 So. 2d 283 (La. 1975).

Opinion

307 So.2d 283 (1975)

T. M. THURMAN, d/b/a Thurman Electric Company
v.
STAR ELECTRIC SUPPLY, INC., et al.

No. 54972.

Supreme Court of Louisiana.

January 20, 1975.

John D. Kopfler and Associates, J. R. Schmidt, Hammond, for applicant Stagecraft Industries, Inc.

Walton J. Barnes, Arthur J. Boudreaux, III, Barnes & Barnes; Baton Rouge, Tom

*284 H. Matheny, Pittman & Matheny, Hammond, for defendants-respondents.

MARCUS, Justice.

This matter originated as a concursus proceeding instituted by T. M. Thurman, doing business as Thurman Electric Company [hereinafter referred to as "Thurman"]. Cited to appear and assert their respective claims to monies deposited by Thurman in the registry of the court were Star Electric Supply, Inc. [hereinafter referred to as "Star"], Stagecraft Industries, Inc. [hereinafter referred to as "Stagecraft"], and Edwin F. Guth Company [hereinafter referred to as "Guth"]. Following trial, the district court rendered judgment in favor of Stagecraft, awarding it the sum deposited in the registry of the court, less court costs. Stagecraft was also given judgment against Star for the amount of the costs. Attorney's fees in the amount of $4,470.02 were also awarded to Thurman and were to be paid from the concursus funds. From this judgment, appeals were taken by Thurman, Stagecraft, and Star. The court of appeal reversed the awards to Thurman and Stagecraft and rendered judgment in favor of Star, awarding it the sum of the deposit, less court costs. Thurman v. Star Electric Supply, Inc., 294 So.2d 255 (La.App. 1st Cir. 1974). We granted the application of Stagecraft for review of the judgment of the court of appeal. 299 So.2d 351 (La. 1974).[1]

FACTS

The evidence discloses that Charles Carter & Company, Inc. [hereinafter referred to as "Carter"], entered into a general contract with the Louisiana State Board of Education, whereby Carter was to furnish all materials and perform all labor according to specifications in the construction of a multi-purpose classroom building to be located on the campus of Southeastern Louisiana College (now University) in Hammond, Louisiana. As required by the public contracts law, Carter obtained a surety bond (from the Aetna Casualty and Surety Company) guaranteeing the contractor's faithful performance of the contract and timely payment by him or any subcontractor for all work done, labor performed, and materials furnished. See La. R.S. 38:2241 (1950).

Shortly thereafter, Carter subcontracted the electrical work under the prime contract to Thurman, who obtained a bond from the Fidelity and Deposit Company of Maryland guaranteeing his faithful performance of the subcontract and his timely payment of all laborers and materialmen as required by law. Incidental to performance of his electrical subcontract, Thurman ordered certain materials from Star, a wholesale electrical supplier. In filling the order, Star purchased the items required from various manufacturers, including Stagecraft and Guth, for resale to Thurman. As is customarily done to save shipping costs, Star designated the job site as the place of delivery in its orders.

The controversy here centers around payment for certain electrical stage lighting equipment manufactured in separate component units and delivered to Thurman at the job site. Three lien affidavits, claiming that amounts were due and owing on the equipment, were filed. First, Star filed a sworn statement of claim on January 22, 1971 in the records of the clerk of court for Tangipahoa Parish, where the materials were delivered and incorporated into the construction project. In its affidavit, Star claimed that it was owed $46,277.75 for the materials supplied to Thurman.[2] A second lien affidavit was *285 filed in the Tangipahoa Parish records by Stagecraft on January 25, 1971, claiming that $44,894.00 was due for materials it furnished pursuant to orders from Star. Finally, Guth filed its affidavit of claim in the same parish records on February 25, 1971; it alleged that it was owed the sum of $12,053.05 for materials supplied to Thurman under orders from Star for use in the construction project.[3]

After the first two lien affidavits were filed, Thurman filed its petition for concursus on January 28, 1971. By various answers, reconventional demands, and third party demands, the cited parties asserted their claims to the depositied funds in the amounts stipulated in their lien affidavits. Whether the funds were properly distributed to Star by the court of appeal is the subject for resolution here.

ISSUES

In order to assess the correctness of the distribution of the funds by the court of appeal to Star and the merit of the competing claim of Stagecraft to the proceeds, two issues must be considered: (1) What parties are entitled to file a sworn statement of claim for amounts due for labor performed or materials furnished in the construction of public works? (2) Which of the parties is of the status described above?

If only Star is entitled to a claim under the public contracts law, the judgment of the court of appeal was correct in awarding it the fund deposited by Thurman. However, if, as contended by Stagecraft, it has a lien right under the public contracts law, it is entitled to the monies on deposit since its claim for payment of the price of the equipment necessarily antecedes that of Star, to whom it first sold the equipment for resale to Thurman, and payment to Stagecraft also satisfies the claim of Star to the extent that Star's claim represents its indebtedness to Stagecraft for the wholesale price of the equipment.

I.

The public contracts law dictates that the representative of any governing authority contracting for the construction of public works.

shall require of the contractor a bond, with good, solvent, and sufficient surety. . . for the faithful performance of the contract with an additional obligation for the payment by the contractor or subcontractor for all work done, labor performed, or material or supplies furnished for the construction . . . of any public works.

La.R.S. 38:2241 (1950). The law further provides that

[a]ny person to whom money is due for doing work, performing labor, or furnishing materials or supplies for the construction. . . of any public works. . .

may file a sworn statement of the amount due him with the governing authority having the work done and record it in the mortgage records of the parish in which the construction is located. Id. 38:2242. The effect of this is twofold: first, it accords to those not enjoying contractual privity with the general contractor a right of action against both the contractor and his surety; second, upon the filing and recordation of the affidavit of claim, any payment made by the governing authority without deducting the amount of the claim renders the authority liable for the claim. Id.

*286 The language quoted from the statutory provisions above has been interpreted in pari materia to embrace only those claimants for whose benefit a surety bond is required, i. e., those creditors seeking payment for labor performed for or materials furnished to the contractor or a subcontractor. See, e. g., American Creosote Works, Inc. v. City of Monroe, 175 La. 905, 144 So. 612 (1932); J. Watts Kearny & Sons v. Perry, 174 La. 411, 141 So. 13 (1932); 21 La.L.Rev. 846 n. 2 (1961).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dr. Joe W. Aguillard v. Louisiana College
Louisiana Court of Appeal, 2021
SIEMENS BLDG. TECHNOLOGIES v. Jefferson Parish
298 F. Supp. 2d 415 (E.D. Louisiana, 2004)
Jean Simpson Personnel v. G & G Concrete
803 So. 2d 992 (Louisiana Court of Appeal, 2001)
Wilson Industries, Inc. v. Aviva America Inc.
185 F.3d 492 (Fifth Circuit, 1999)
WILSON INDUSTRIES, INC. v. Aviva America, Inc.
63 F. Supp. 2d 747 (E.D. Louisiana, 1999)
Western Metal Lath v. Acoustical & Construction Supply, Inc.
851 P.2d 875 (Supreme Court of Colorado, 1993)
Unadilla Silo Co. v. Hess Bros.
586 A.2d 226 (Supreme Court of New Jersey, 1991)
AFCO Metals, Inc. v. Tudor Construcution Co.
571 So. 2d 698 (Supreme Court of Louisiana, 1990)
Wilkin v. Dev Con Builders, Inc.
561 So. 2d 66 (Supreme Court of Louisiana, 1990)
Lyle Signs, Inc. v. Evroks Corporation & Travelers Indemnity Co.
562 A.2d 785 (Supreme Court of New Hampshire, 1989)
Daigle v. Donald M. Clement Contractor, Inc.
533 So. 2d 1064 (Louisiana Court of Appeal, 1988)
Owl Construction Co. v. Ronald Adams Contractor, Inc.
642 F. Supp. 475 (E.D. Louisiana, 1986)
Henican v. Carr
483 So. 2d 1234 (Louisiana Court of Appeal, 1986)
JAVELER CONST. CO., INC. v. Federal Ins. Co.
472 So. 2d 258 (Louisiana Court of Appeal, 1985)
Honeywell, Inc. v. Jimmie B. Guinn, Inc.
440 So. 2d 973 (Louisiana Court of Appeal, 1983)
Slagle-Johnson Lumber Co. v. Landis Const. Co.
379 So. 2d 479 (Supreme Court of Louisiana, 1980)
Carr Oil Co. v. Donald G. Lambert Contractor, Inc.
380 So. 2d 157 (Louisiana Court of Appeal, 1979)
Slagle-Johnson Lumber, Inc. v. Landis Construction Co.
366 So. 2d 206 (Louisiana Court of Appeal, 1978)
LEONARD B. HERBERT, JR. & CO., INC. v. Kinler
336 So. 2d 922 (Louisiana Court of Appeal, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
307 So. 2d 283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thurman-v-star-electric-supply-inc-la-1975.