Daigle v. Donald M. Clement Contractor, Inc.
This text of 533 So. 2d 1064 (Daigle v. Donald M. Clement Contractor, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
W.J. DAIGLE, d/b/a Commercial Renovations
v.
DONALD M. CLEMENT CONTRACTOR, INC., et al.
Court of Appeal of Louisiana, Fourth Circuit.
*1065 Steven M. Lozes, Lozes, Cooper & Cambre, New Orleans, for plaintiffs.
David J. Mitchell, Dan Richard Dorsey, Porteous, Hainkel, Johnson & Sarpy, New Orleans, for defendants.
Before GULOTTA, C.J., and SCHOTT and ARMSTRONG, JJ.
ARMSTRONG, Judge.
Defendants, Donald M. Clement Contractor, Inc., Travelers Insurance Company and Commercial Union Insurance Company appeal the trial court's judgment in favor of plaintiff, W.J. Daigle, d/b/a Commercial Renovations, for the amount of $10,200 plus ten percent attorney fees, together with legal interest and costs.
This lawsuit arises out of two separate construction contracts between defendants Donald M. Clement Contractors, Inc. ("Clement"), and the Parish of St. Bernard involving the construction of certain projects known as "Val Reiss Park, Phase II" and "Val Reiss Park, Phase III" in Chalmette, Louisiana. The Phase II improvements were bonded by a performance and payment bond issued by Travelers Insurance Company ("Travelers"), which also bonded Phase III of the project. Clement subcontracted the construction of certain items including two dugouts and two gates to Peter Aizenman, president of Competent Contractors, Inc. ("Aizenman"). The subcontract was in writing and contained a provision that Aizenman would furnish all labor, material, equipment and supervision to construct these items. The sum agreed upon for the gates was $5,900.00 and for the dugouts was $8,200.00.
Subsequently, Aizenman contacted plaintiff, W. Joseph Daigle, d/b/a Commercial Renovators ("Daigle"), and subcontracted the construction of the dugouts and construction of the two gates for the prices that Clement had agreed to pay him. This contract was oral and no mention was made of the provision requiring Aizenman to purchase materials. Pursuant to this oral contract with Aizenman, Daigle built the dugouts and the two gates. The terms of this agreement were subsequently memorialized in writing.
Daigle claims that Clement contacted him directly at a later date about building a third gate. Daigle initially refused because he had only been paid $5,900.00 by Aizenman for the two gates, but nothing for the two dugouts. Clement then offered to pay $4,000.00 for the gate with a $2,000.00 advance and Daigle agreed. Clement issued a check for $2,000.00 in partial payment of the gate, leaving a balance of $2,000.00.
Upon completing the work in January of 1983, Daigle personally delivered his outstanding invoice to Clement for $10,200 *1066 which included the dugouts for $8,200.00 and the gate for $2,000.00. When payment was not forthcoming Daigle obtained a certificate of substantial completion for the Phase III improvements and filed liens, which were bonded. On January 5, 1984 Daigle filed suit against Clement, Travelers, (issuer of the performace and payment bond) and Commercial Union Insurance Company, (issuer of lien bonds) seeking relief pursuant to the Public Works Act, La.R.S. 38:2241. The Parish of St. Bernard and the individual police jurors were named as parties but were dismissed on an exception of no cause of action. Judgment was entered for Daigle in the amount of $10,200.00, his total claim, plus ten percent attorney fees and interest. No written reasons for judgment were given. Clement filed a motion for new trial which was denied and this appeal was taken.
By his first assignment of error, Clement argues that the trial court erred in failing to dismiss Daigle's suit for noncompliance with the Public Works Act, specifically La.R.S. 38:2247. La.R.S. 38:2247 requires that a claimant notify the contractor of his claim by certified mail within 45 days from the recordation of the notice of acceptance by the owner of the work. Clement claims that Daigle did this prematurely in the case of the gate constructed under the Phase III contract and that notice was received in excess of 45 days in regard to the dugouts constructed under the Phase II contract. By his own testimony, Clement explained that all of the work Daigle performed was under the Phase II contract. Clement relies on Powers Regulator Co. v. Murphy's Plumbing Service, Inc., 311 So. 2d 503 (La.App. 4th Cir.1975) to argue that in failing to meet the notice requirements of the statute Daigle's suit should be dismissed.
Powers involved a case where the notice that the claimant sent by certified mail was not delivered. The Post Office notified the claimant of the non-delivery, and the claimant took no further timely action to accomplish delivery even though sufficient time remained available. Powers is distinguishable from the case before us because Daigle filed a lien with the mortgage office at the time when the statute allowed recordation of the lien to serve as notice.[1]
Daigle also complied with section 2247 by mailing a certified letter containing the lien affidavits and the invoice on March 1, 1983. Furthermore, Daigle proved that he personally delivered a written invoice to Clement on January 27, 1983. The fact that Clement maintains he did not receive the certified letter until August does not circumvent the fact that he had notice of the lien well within the 45 day limit assigned by the statute.
By his second assignment of error Clement maintains that Daigle failed to prove that there was a subcontract between Aizenman and himself. However, it is not necessary for Daigle to be a subcontractor in order to proceed as a claimant against Clement under the Public Works Act. La.R.S. 38:2247 governs the claims of subcontractors as well as materialmen and laborers. Honeywell, Inc. v. Jimmie B. Guinn, Inc., 462 So.2d 145 (La.1985); see also Harvey Canal Towing Co., Inc. v. Gulf South Dredging Co., Inc. 345 So.2d 567 (La.App. 4th Cir.1977).
Clement insists that Daigle is actually Aizenman's partner and thus knowledge of the terms of the contract between Aizenman and Clement should be attributed to Daigle. However, this court is satisfied from our review of the law and the facts that Daigle qualifies as a subcontractor. Thurman v. Star Electric Supply Inc., 307 So.2d 283 (La.1975). The Thurman decision notes that a subcontractor is a person who provides labor in attaching or incorporating materials into the building or on-site improvements. By his own testimony, Clement admitted that he contacted Daigle at a telephone number separate from that of Aizenman, and that *1067 Daigle's telephone was regularly answered under the name of Commercial Renovations, a separate entity from Competent Contractors, Inc. As a subcontractor Daigle can not be held to the terms of the Clement-Aizenmen contract. That agreement is only enforceable as between the parties. A basic rule of contract construction under Louisiana law is that a contract represents the law between the parties. Latter and Blum, Inc. v. Nodier, 442 So. 2d 854 (La.App. 4th Cir 1983). Clement's confusion as to the relationship between Aizenman and Daigle does not serve as a valid defense under the Public Works law. The Thurman decision specifically holds that a subcontractor who provides labor and materials to another subcontractor is protected by the Public Works Act.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
533 So. 2d 1064, 1988 WL 113209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daigle-v-donald-m-clement-contractor-inc-lactapp-1988.