590 So.2d 664 (1991)

BOB McGAUGHEY LUMBER SALES, INC. and McGaughey Building Products, Inc., Plaintiffs-Appellants,
v.
The LEMOINE COMPANY, INCORPORATED, Meritplan Insurance Company and Federal Insurance Co., Defendants-Appellees.

No. 90-514.

Court of Appeal of Louisiana, Third Circuit.

November 13, 1991.

Weems, Abney, Wright & Feldman, Robert B. Dunlap, Shreveport, for plaintiffs/appellants.

Perret, Doise, Daigle, Longman, Russo & Zaunbrecher, Robert W. Daigle, Lafayette, for defendants/appellees.

Before GUIDRY, DOUCET and KNOLL, JJ.

GUIDRY, Judge.

Plaintiffs, Bob McGaughey Lumber Sales, Inc. and McGaughey Building Products, Inc. (hereafter collectively referred to as McGaughey), filed suit against The Lemoine Company, Inc., Meritplan Insurance Company and Federal Insurance Company (collectively referred to as defendants) seeking recovery of $25,385.82, plus interest and attorney's fees, allegedly due for materials supplied to Lemoine which were used and incorporated in State Project No. 08-20-00-85B-4, Medium Security Prison, Avoyelles Parish, Louisiana (hereafter Project).

Defendants filed a peremptory exception of no cause of action and/or no right of action which was sustained. Judgment reflecting the trial court's ruling and dismissing plaintiffs' suit was signed April 6, 1990. From that judgment McGaughey appeals.

*665 FACTS

Lemoine was the general contractor on the Project. On March 9, 1987, in conjunction with its construction of the Project, Lemoine entered into a subcontract with Knost Roofing and Construction Company, Inc. (hereafter Knost) for the construction of all built-up roofing and sheet metal work. Knost, in turn, executed a performance and payment bond with Meritplan. McGaughey furnished materials to Knost at the site of the Project. Those materials were then incorporated into the construction. Lemoine terminated Knost's contract before it was substantially complete allegedly due to Knost's failure to comply with the terms of the subcontract. Knost failed to make payments to McGaughey for materials in the amount of $25,385.82. Subsequently, Knost filed for protection under Chapter 11 of the Bankruptcy Code, In Re: Knost Roofing Company, Inc., Bankruptcy Case No. 88BK01628, United States Bankruptcy Court, Western District of Louisiana.

On May 12, 1988, McGaughey timely filed a Sworn Statement of Amount Due (statement of claim) pursuant to La.R.S. 38:2241 et seq. in the mortgage records of Avoyelles Parish. Notice of the statement of claim was mailed to the State of Louisiana, Division of Administration, with a copy to Lemoine, by regular mail on May 16, 1988. It is undisputed that Lemoine received the notice through regular mail on May 18, 1988. It is further undisputed that the notice was not delivered by either registered or certified mail. Additionally, it is undisputed that, on June 15, 1988, Lemoine received additional notification of the statement of claim pursuant to a letter dated June 14, 1988 from the State of Louisiana, Division of Administration.

On June 20, 1988, Lemoine filed a release of claim bond issued by Federal in the amount of $31,732.28 for the purpose of releasing the claim filed by plaintiffs.

Plaintiffs filed suit seeking to enforce their Public Works Act claim on March 20, 1989 which was dismissed on an exception filed by defendants.

OPINION

The trial court did not file oral or written reasons for its judgment. Defendants' only argument at the trial level and on appeal in support of its exception is the failure of McGaughey to serve Lemoine with notice of its claim by registered or certified mail. Presumably, the trial court sustained defendants' exception because of this omission and the settled principle that statutes relating to liens are strictly construed and are not subject to extension or enlargement by implication. We reverse.

La.R.S. 38:2247 states:

"Nothing in this Part shall be construed to deprive any claimant, as defined in this Part and who has complied with the notice and recordation requirements of R.S. 38:2242(B), of his right of action on the bond furnished pursuant to this Part, provided that said action must be brought against the surety or the contractor or both within one year from the registry of acceptance of the work or of notice of default of the contractor; except that before any claimant having a direct contractual relationship with a subcontractor but no contractual relationship with the contractor shall have a right of action against the contractor or the surety on the bond furnished by the contractor, he shall in addition to the notice and recordation required in R.S. 38:2242(B) give written notice to said contractor within forty-five days from the recordation of the notice of acceptance by the owner of the work or notice by the owner of default, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor or service was done or performed. Such notice shall be served by mailing the same by registered or certified mail, postage prepaid, in an envelope addressed to the contractor at any place he maintains an office in the state of Louisiana."

Defendants argue that the claim of petitioner must fail because notice was not mailed by McGaughey to Lemoine via registered or certified mail. On the other *666 hand, McGaughey argues that the notice requirement of R.S. 38:2247 is satisfied if it be established that the contractor timely receives from the subcontractor written notice of the subcontractor's claim within 45 days of the recordation of the notice of acceptance by the owner of the work or notice by the owner of default. McGaughey urges that the notice requirements are satisfied upon timely receipt of written notice from the subcontractor whether by certified, registered or regular mail or by hand delivery. We agree.

The obvious purpose of the registered or certified notice requirement of R.S. 38:2247 is to assure actual receipt of written notice of the claim and to facilitate proof thereof. In Daigle v. Donald M. Clement Contractor, 533 So.2d 1064 (La. App. 4th Cir.1988), writ denied, 536 So.2d 1216 (La.1989), the court observed that what is required is actual notice. In Daigle, supra, the subcontractor hand delivered notice to the contractor within the 45 day period. Subsequently, he mailed a certified letter to the contractor. Although the letter was mailed within the 45 day time limit, it was not received until six months later. The contractor argued that notice was not proper since it was not received within the prescribed time limit. The court rejected the contractor's contention, stating that the hand delivery was sufficient.

In Powers Regulator Co. v. Murphy's Plumbing Service, Inc., 311 So.2d 503 (La. App. 4th Cir.1975), the court, obviously concerned with actual notice rather than strict compliance with the statute, rejected the claim of a subcontractor who sent notice by certified mail which was never delivered to the contractor. In that case the certified letter was returned to the claimant within the 45 days and the claimant took no further steps to accomplish delivery. The basis of the court's ruling was lack of actual notice of the claim to the contractor.

As previously mentioned, one of the purposes of the certified mailing requirement is proof. The certification does not provide any additional notice to the contractor. If Lemoine denied receiving the notice, then the burden would be upon McGaughey to show that it was actually timely received.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

84 Lumber Company v. F.H. Paschen, S.N. Nielsen, e
914 F.3d 329 (Fifth Circuit, 2019)
Nu-Lite Elec. Wholesalers, LLC v. Axis Constr. Grp., LLC
249 So. 3d 10 (Louisiana Court of Appeal, 2018)
MARTIN MARIETTA MATERIALS v. US Fidelity
940 So. 2d 152 (Louisiana Court of Appeal, 2006)
Gilchrist Construction Co., Inc. v. Terral Riverservice, Inc.
819 So. 2d 362 (Louisiana Court of Appeal, 2002)
K CONST., INC. v. Burko Const., Inc.
629 So. 2d 1370 (Louisiana Court of Appeal, 1993)
Cole's Const. Co., Inc. v. Knotts
619 So. 2d 876 (Louisiana Court of Appeal, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
590 So. 2d 664, 1991 WL 236321, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bob-mcgaughey-lumber-v-lemoine-co-lactapp-1991.