ETI, Inc. v. Buck Steel, Inc.

211 So. 3d 439, 2016 La.App. 4 Cir. 0602, 2017 WL 431785, 2017 La. App. LEXIS 128
CourtLouisiana Court of Appeal
DecidedFebruary 1, 2017
DocketNO. 2016-CA-0602
StatusPublished
Cited by6 cases

This text of 211 So. 3d 439 (ETI, Inc. v. Buck Steel, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ETI, Inc. v. Buck Steel, Inc., 211 So. 3d 439, 2016 La.App. 4 Cir. 0602, 2017 WL 431785, 2017 La. App. LEXIS 128 (La. Ct. App. 2017).

Opinion

Judge Daniel L. Dysart

|! This matter arises from a contractual dispute between ETI, Inc. (“ETI”) and Buck Steel, Inc. (“Buck Steel”). For the reasons that follow, we affirm.

FACTUAL AND PROCEDURAL BACKGROUND

In November, 2011, the State of Louisiana entered into a contract with ETI for the latter to serve as the general contractor for the construction of an addition to the central plant at the University of New Orleans North Campus (“the Project”). ETI then subcontracted with Buck Steel for certain tasks related to the construction of a metal building system required for the Project. Included among these tasks was the preparation of engineered stamped drawings.

After issues arose over the drawings prepared by Buck Steel, ETI terminated its contract with Buck Steel and filed a Petition against it on November 23, 2012, alleging the following facts. According to ETI, it provided Buck Steel with a copy of the plans, specifications and addenda for the Project on February 1, 2012. Buck Steel then submitted a quote for the metal building system on February 2, 2012, which ETI accepted on February 3, 2012. Thereafter, ETI instructed Buck Steel to 12prepare the “submittals necessary to obtain the approval of ... [the] Metal Budding System by the Engineer and Architect of record for the project.” ETI issued a payment to Buck Steel in the amount of $17,500.00 on February 22, 2012.

On March 9, 2012, Buck Steel issued a submittal to the Project’s architect, who rejected it for the reason that “the submit-tal and shop drawings failed to comply with the plans and specifications for the Project.” The architect provided “extensive notes” for Buck Steel to use in order to revise its submittal.

On June 4, 2012, ETI issued another payment to Buck Steel in the amount of $28,129.00 and, on June 18, 2012, Buck Steel issued its second submittal to ’ the Project’s architect. This submittal was again rejected “for the same reason that the first submittal was rejected.”

In this lawsuit, ETI alleged that, because of Buck Steel’s failure to properly and timely prepare the necessary submit-tals, there was a delay in the Project and ETI incurred delay damages. ETI further alleged that it had to obtain the metal building system from another vendor. ETI sought the return of the funds paid to Buck Steel, in addition to damages, including delay damages, costs and other equitable relief.

By way of a First Amended and Supplemental Petition, filed on May 2, 2014, ETI amended its original petition so as to specify the damages it sought, as follows:

- Return of the two payments ($17,500.00 and $28,129.00)
Is- Increased contract amount of $21,155.32 which ETI incurred in “hir[ing] an alternate contractor to prepare the necessary submittals and provide the metal building that Buck Steel failed to provide”
- Unusable Boes Iron Works mezzanine steel valued at $25,039.00
- Delay damages of $70,800.00
- ETI’s additional overhead of $141,012.00
- Payments to “Bonding Company Administrator” of $27,000.00
[442]*442- Payments to “the paymaster for the bonding company” of $6,000.00
- Olympic Group price increase of $7,060.00

On September 12, 2014, Buck Steel filed a Reconventional Demand against ETI in which it alleged that ETI breached the contract with it when it “unilaterally rescinded. .. and canceled the Sales Contract on or before August 16, 2012.” Buck Steel sought liquidated damages pursuant to the sales contract in the amount of 33% “of the entire contract,” collection costs, attorney’s fees and other costs and fees.

The matter proceeded to trial from May 4-6, 2015, and by judgment dated November 3, 2015, the trial court awarded ETI damages of $46,194.32 (on the basis that ETI “carried its burden of proving a breach of contract).1 The judgment also found that Buck Steel, “a vendor under Louisiana law, is allowed to bring its breach of contract claim, BUT that the Court finds no breach of the Sales Contract in question.” The Court also concluded that Buck Steel “is entitled to retain the $45,629 in deposits paid by ETI, Inc.” The judgment then stated that ETI was .[^entitled to the difference of the two amounts or a total of $565.32 in damages.”

On November 12, 2015, ETI filed a Motion for New Trial on the basis that the trial court’s November 3, 2015 judgment was inconsistent with the Reasons for Judgment and because the judgment contained a mathematical error with respect to awarding ETI the difference between the sums awarded to ETI and Buck Steel.2 After a hearing on the motion held on January 8, 2016, the trial court issued a judgment on March 7, 2016. The judgment denied ETI’s motion for new trial but corrected its prior judgment so as to read as follows:

IT IS FURTHER ORDERED, ADJUDGED AND DECREED that ETI, Inc. carried its burden of proving a breach of contract action on the part of Buck Steel AND is entitled to damages in the amount of $46,194.32. Under the evidence presented, Buck Steel is entitled to retain the $45,629 in deposits paid by ETI.3

ETI timely appealed the judgment.

DISCUSSION

At the outset, ETI urges this Court to adopt a de novo standard of review, arguing that, while a “trial judge has broad discretion in granting or denying a motion for new trial,” “when one or more legal errors interdict the court’s fact finding process, the manifest error standard becomes inapplicable.” While we agree with ETI that issues concerning the interpretation of contracts are questions of law subject to a de novo standard of review,4 factual determinations by the trial | Bcourt [443]*443are subject to a manifest error standard of review. See, Harold A. Asher, CPA, LLC v. Haik, 12-0771, p. 4 (La.App. 4 Cir. 4/10/13), 116 So.3d 720, 723.

In this appeal, ETI does not challenge the trial court’s failure to award it certain items of damages it sought by way of its original and supplemental petitions (e.g., delay damages, additional overhead, payments related to the bond or the price increase of Olympic Group). Rather, ETI raises three issues in this appeal: (1) the trial court’s finding that Buck Steel is not a contractor under Louisiana law, (2) the trial court’s finding that Buck Steel is allowed to retain the payments made to it by ETI; and (3) the trial court’s failure to award costs to ETI. We address each assignment of error in turn.

Whether the tidal court erred in finding that Buck Steel is not a contractor under Louisiana law

In its first assignment of error, ETI maintains that the trial court erred in failing to find that, under the circumstances of this ease, Buck Steel was a contractor rather than a vendor because it agreed to supply the material to construct the metal budding and to erect the building in question. ETI then argues that, because Buck Steel was a contractor as contemplated by La. R.S. 37:2150.1(4)(a),5 and was not licensed as a contractor in Louisiana, “Buck Steel’s Contract for over $50,000, which included erecting the steel building, was absolutely null.” In | (¡support of its arguments, ETI relies on the case of Alonzo v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
211 So. 3d 439, 2016 La.App. 4 Cir. 0602, 2017 WL 431785, 2017 La. App. LEXIS 128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eti-inc-v-buck-steel-inc-lactapp-2017.