Thurman v. Star Electric Supply, Inc.
This text of 294 So. 2d 255 (Thurman v. Star Electric Supply, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
T. M. THURMAN, d/b/a Thurman Electric Co.
v.
STAR ELECTRIC SUPPLY, INC., Defendant-Appellant-Appellee, and
Stagecraft Industries, Inc., Defendant-Appellant-Appellee, and
Edwin F. Guth Co., Defendant-Appellee.
Court of Appeal of Louisiana, First Circuit.
*256 Tom H. Matheny, Hammond, for plaintiff-appellant-appellee Thurman.
Walton J. Barnes, Baton Rouge, for defendant-appellant-appellee Star Elec.
John D. Kopfler, Hammond, for defendant-appellant-appellee Stagecraft Industries, Inc.
Duncan S. Kemp, III, Hammond, for appellee.
Before LOTTINGER, BLANCHE and de la HOUSSAYE, JJ.
LOTTINGER Judge.
This is a concursus proceeding instigated by T. M. Thurman d/b/a Thurman Electric Company. Other parties are Star Electric Supply, Inc., Stagecraft Industries, Inc. and Edwin F. Guth Company.
The facts disclose that Charles Carter & Company, Inc. entered into a contract with the Louisiana State Board of Education for the construction of a multi-purpose classroom building on the campus of Southeastern Louisiana College at Hammond, Louisiana. As part of its performance, Carter entered into a sub-contract with T. M. Thurman, d/b/a Thurman Electric Company, by which sub-contract Thurman obligated himself to complete the electrical portion of the contract. Thurman ordered certain electrical materials needed for the construction of the building from Star Electric Supply, Inc. Star accepted this order and purchased the items required from various manufacturers including Stagecraft Industries, Inc. and the Edwin F. Guth Company.
Subsequently, Star filed a lien in the sum of $46,277.75 asserting that this amount remained due and unpaid on the materials which it furnished Thurman. Stagecraft filed a lien in the sum of $44,894.00 asserting that this amount remained due and unpaid on materials sold by it to Star, and Guth filed a lien in the sum of $12,053.05 asserting that this amount remained due and unpaid on its order.
Thurman then filed a petition for concursus citing Star, Stagecraft and Guth to appear therein and assert whatever claims they may have and deposited into the registry of the Court the sum of $44,702.28 which was the amount Thurman acknowledged as yet unpaid on its original purchase order to Star. Stagecraft filed an answer to the concursus proceeding in a third party demand. The essence of the answer to the concursus was that Stagecraft sold equipment and fixtures to Star which were used in the construction and for which the balance of $44,894.00 was still due. The essence of the third party demand was that it should have judgment against Carter and his surety, Thurman and his surety, Star, and the State, for the amount of its claim because it supplied materials used in the construction. Star answered the concursus proceeding, reconvening against Thurman and third partied Thurman's surety, as well as Carter and his surety, as well as the State. The essence of the answer to the concursus was that it was entitled to the proceeds in the registry of the Court. The reconvention was to the effect that it was *257 not paid in full for materials sold to Thurman and should have judgment against Thurman for the unpaid balance. The third party demand was to the effect that Star was entitled to the proceeds in payment for the balance due on its claim by virtue of its lien.
Guth filed an answer and third party demand. The answer, in essence, prayed for the satisfaction of its claim from the proceeds in the registry of the Court because it sold materials to Star used in the construction and the third party demand was to the effect that Carter, his surety, Thurman, his surety, Star and the State were liable for the amount of the claim because the materials were used in the construction of the building.
Thurman, his surety, Carter, his surety and the State answered the third party demand of Guth denying same and also Thurman and his surety, Carter and his surety and the State answered the third party demands of Star denying same. Subsequently, Thurman and his surety, Carter and his surety, and the State answered the third party demand of Stagecraft denying same.
Following trial, judgment was rendered in favor of Stagecraft awarding it the sum of $44,702.28, deposited in the registry of the Court. All costs of the Court were to be deducted from the deposit, and Stagecraft was given judgment against Star for the amount of the costs. The claim of Thurman for attorney fees in the sum of $4,470.02 to be paid from the funds on deposit in the registry of the Court was granted. From this judgment appeals were taken by Thurman, Stagecraft and Star. Guth did not appeal nor did they answer the appeal, and, therefore, this Court will not even consider its claim.
We feel that the Lower Court erred both in awarding a judgment in favor of Stagecraft, as well as awarding Thurman attorney fees.
With regard to the judgment in favor of Stagecraft, we feel that the decision of our learned brethren from the Second Circuit in the case entitled Heard & Sons v. Southwest Steel Products, 124 So.2d 211, is controlling. In that case the petitioner entered into a building contract with the Louisiana State Board of Education. The contractor was to furnish all labor and materials necessary for the construction of a student union building at Grambling College. The contractor entered into a subcontract with Industrial Fabricators for the furnishing of certain structural steel and miscellaneous items which required special fabrication. Industrial Fabricators in turn contracted Southwest Steel Products for the fabrication of the steel. Subsequently, Industrial Fabricators were adjudged bankrupt and Southwest Steel Products filed its affidavit of lien.
In that case the Court held that one who supplies materials to either a contractor or sub-contractor in connection with construction of a public building is entitled to a lien under the Public Works Act, but one who furnishes material to materialmen has no right to a lien. In that regard the Court there said as follows:
"It is the view of this Court that where one simply contracts to furnish a completed article to be used in a building, and where such person does not have the responsibility and is under no obligation in any manner to join in the installation of such materials in the building itself and to take no part in the actual erection or construction of the building at the site where the same is being constructed, that he and his employees are simply suppliers of materials, that they have no lien for such materials upon the proceeds of the building contract, especially where labor performed in preparation of the materials was done away from the building site and in the place of business of the supplier of such materials."
"In other words, the test ought to be not whether or not there has been time and labor expended in producing the material, for that would be true in the preparation *258 of all materials, but the test should be whether or not the person furnishing the material thereafter performed any labor in attaching to or incorporating the materials into the building or improvements involved in that case.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
294 So. 2d 255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thurman-v-star-electric-supply-inc-lactapp-1974.