Foster Lumber Co. v. Sigma Chi Chapter House of DePauw University

97 N.E. 801, 49 Ind. App. 528, 1912 Ind. App. LEXIS 202
CourtIndiana Court of Appeals
DecidedMarch 5, 1912
DocketNo. 7,478
StatusPublished
Cited by12 cases

This text of 97 N.E. 801 (Foster Lumber Co. v. Sigma Chi Chapter House of DePauw University) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foster Lumber Co. v. Sigma Chi Chapter House of DePauw University, 97 N.E. 801, 49 Ind. App. 528, 1912 Ind. App. LEXIS 202 (Ind. Ct. App. 1912).

Opinion

Adams, J.

Appellee brought this action against appellants and two other defendants to cancel liens of record, which defendants separately claimed to hold against the property of appellee, and to enjoin defendants from instituting1 any proceeding to foreclose their liens until the validity thereof should he determined in the pending action.

The following is a brief summary of the essential facts shown by the evidence and found by the court: Appellee, a college fraternity, on August 27, 1908, entered into a contract with the firm of Caldwell & Mobley to furnish all [530]*530materials and perform all labor necessary in the erection of a chapter house on real estate owned by the fraternity at Greencastle, Indiana. The contractors partially completed their work, but in the latter part of December, 1908, abandoned it. At that time said contractors were indebted to a large number of parties in the sum of $8,000, on account of labor and materials furnished in the construction of said building. Creditors of the contractors filed in the office of the recorder of Putnam county notices of their intention to hold liens on said building for the amount of their several claims. After the work was abandoned, appellee entered into an agreement with all parties claiming to hold liens against said property, except the defendants herein, whereby appellee was granted an extension of time for paying the claims held by such creditors. Appellee denied that the defendants in this suit were entitled to hold liens, and brought this suit to cancel them.

The Foster Lumber Company agreed to furnish, for the sum of $954.30, certain materials to be used in constructing said building, and did furnish and deliver to the contractors at appellee’s building, on or before October 3, 1908, all of the materials so contracted for, which materials were used in constructing said building. The court does not find the fact, but it appears from the evidence that a part of the material furnished by the Foster Lumber Company was used in the building after December 1,-1908. On January 12, 1909, appellant company filed notice of its intention to hold a lien on appellee’s property for the sum of $954.30.

Charles H. Springer undertook to furnish to said contractors, for the sum of $600, all the stone used in the building, as required by the plans and specifications. Subsequently Springer contracted with the IToadley Stone Company to furnish the stone required in said building in consideration of the payment by Springer of a definite sum. All the stone furnished by said Hoadley Stone Company, and which was used in constructing said building was received on or [531]*531prior to November 27, 1908. A stone window sill was received December 9, 1908, but was furnished on account of an error of the contractors in checking up the original shipment, and was not used. The specifications called for two stone ornaments ten inches square, which were found to be improperly carved. On December 17, a keg was received at the building, which remained unopened until after the work was abandoned, and which was then found to contain the two stone ornaments, prdperly carved, but only eight inches square, and unfit for use, although made in conformity with a drawing submitted by the architects. On February 12, 1909, appellant Springer filed notice of his intention to hold a lien for the sum of $583 on the- property of appellee.

By the fourth conclusion of law the court stated that the pretended lien of appellant Foster Lumber Company was invalid, without right, and that said defendant was not entitled to have or to hold a lien against the property of appellee, and that said appellant’s notice of its intention to hold a lien, as filed and recorded, should be canceled, set aside and held for naught.

By the fifth conclusion of law the court stated the law to be the same as to the pretended lien of appellant Charles II. Springer.

Appellants separately excepted to the fourth and fifth conclusions of law, and assign the same as error.

It is obvious that the determination of this cause involves only the determination of one underlying proposition: Did appellants, at the time judgment was rendered below, have valid and enforceable liens against the property of the appellee f If they had, then the court erred as to every specification of error in the assignment. If they had not, the judgment of the court was right, and appellants were not harmed by the refusal of the court to permit them to file cross-complaints, or by any other action of the trial court.

[532]*5321. [531]*531The right of a materialman to enforce a lien for the value of materials furnished by him is limited to cases where the [532]*532following facts appear: The improvement must be made by the authority of the owner of the real estate, the material must be sold, not generally to the contractor, but for the purpose of being used in constructing the particular building, the materials must be actually used in constructing the building, and the notice of the intention of the materialman to hold a li<?n against the property must be filed, as required by law, within sixty days after furnishing such materials. Topp v. Standard Metal Co. (1911), 47 Ind. App. 483; Barnett v. Stevens (1896), 16 Ind. App. 420, 431; Clark v. Huey (1895), 12 Ind. App. 224, 232; Leeper v. Myers (1894), 10 Ind. App. 314, 316; Miller v. Fosdick (1901), 26 Ind. App. 293.

2. The sixty days given by law in which to file the notice of intention to hold a lien must be computed from the date of the last delivery on the premises, or at some point where title to the material- passes from the seller to the purchaser. 27 Cyc. 141; Premier Steel Co. v. McElwaine-Richards Co. (1896), 144 Ind. 614, 621; Thomas v. Kiblinger (1881), 77 Ind. 85, 86 ; Lawton v. Case (1880), 73 Ind. 60, 62; Hamilton v. Naylor (1880), 72 Ind. 171. In order to furnish material for a building, there must be either an actual or constructive delivery of the material at or near the building. Barnett v. Stevens, supra.

3. In the ease of Clark v. Huey, supra, at page 232, it is said: “The materials were actually ‘furnished/ not purchased only, but ‘furnished/ to be used in appellant’s house. ’ ’

“Furnishing the material is complete when it is sold and delivered for the purpose of erection.” Burns v. Sewell (1892), 48 Minn. 425, 51 N. W. 224, 225.

“The materialman is properly said to have ‘furnished’ the materials, when he has delivered, or has them ready for delivery, at the place where he has agreed to deliver them under the contract.” Tibbetts v. Moore (1863), 23 Cal. 208, 214.

[533]*533“When we speak of a bill of goods ‘furnished’ to a person, we mean simply that they have been ordered for and delivered to such person.” The James H. Prentice (1888), 36 Fed. 777, 782.

4. 5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Evansville v. Verplank Concrete & Supply, Inc.
400 N.E.2d 812 (Indiana Court of Appeals, 1980)
Brazos Concrete Products, Inc. v. Bullock
567 S.W.2d 877 (Court of Appeals of Texas, 1978)
Stanray Corporation v. Horizon Construction, Inc.
342 N.E.2d 645 (Indiana Court of Appeals, 1976)
Van Wells v. Stanray Corporation
341 N.E.2d 198 (Indiana Court of Appeals, 1976)
Morris County Industrial Park v. Thomas Nicol Co.
173 A.2d 414 (Supreme Court of New Jersey, 1961)
Jesse F. Heard & Sons v. Southwest Steel Products
124 So. 2d 211 (Louisiana Court of Appeal, 1960)
Huddleston v. Nislar
72 S.W.2d 959 (Court of Appeals of Texas, 1934)
Indiana Limestone Co. v. Cuthbert
267 P. 983 (Supreme Court of Kansas, 1928)
Rudolph Hegener Co. v. Frost
108 N.E. 16 (Indiana Court of Appeals, 1915)
City of Portland v. Indianapolis Mortar & Fuel Co.
106 N.E. 735 (Indiana Court of Appeals, 1914)
Toner v. Whybrew
98 N.E. 450 (Indiana Court of Appeals, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
97 N.E. 801, 49 Ind. App. 528, 1912 Ind. App. LEXIS 202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foster-lumber-co-v-sigma-chi-chapter-house-of-depauw-university-indctapp-1912.