Premier Steel Co. v. McElwaine-Richards Co.

43 N.E. 876, 144 Ind. 614, 1896 Ind. LEXIS 213
CourtIndiana Supreme Court
DecidedApril 23, 1896
DocketNo. 17,648
StatusPublished
Cited by27 cases

This text of 43 N.E. 876 (Premier Steel Co. v. McElwaine-Richards Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Premier Steel Co. v. McElwaine-Richards Co., 43 N.E. 876, 144 Ind. 614, 1896 Ind. LEXIS 213 (Ind. 1896).

Opinion

Hackney, C. J.

This was an action by the appellee, The McElwaine-Riehards Company, against the appellants, The Premier Steel Company, John E. Mc-Gettigan, receiver for that company, and others, and its object was to enforce a materialman’s lien against the property of said Premier Steel Company. Special findings, with conclusions of law, and a motion to modify the judgment present the questions here assigned on behalf of the appellant. The facts so specially found were that the appellant, The Premier Steel Company, had been engaged in the manufacture of steel blooms, billets, and railroad iron, and had been experimenting in various methods of making steel until May 6,1893, when McGettigan was appointed receiver; that said company’s business was conducted in “one Bessemer mill; one open hearth mill; one machine shop; one foundry; one old iron rail mill; hydraulic pump, etc., and one steel mill,” all upon real estate owned by said company, held within one in[616]*616closure without division with relation to the several buildings; that the buildings thereon were connected by railroad tracks, gas and steam pipes, were lighted by the same electric plant and were all, excepting one, used by said company in its said business; that the building so excepted was leased to the Indiana Steel Company, but was connected to and with another of said buildings by a continuous roof which covered both buildings; that said real estate, including said buildings, was intended for an entire and general plant. In 1892 said company was engaged in making extensive improvements upon said real estate, and notified appellee that it would need therein a large amount of steam, gas and water pipes, materials appellee was then engaged in selling, and that as it should order from time to time, appellee should supply such materials at the best prices, which appellee agreed to do. “In October, 1892, and continuing thereafter until the appointment of said receiver appellee furnished said company, upon its orders from time to time, material, each being a separate order, for construction, erection and repairing of said plant and all the buildings on said real estate, to the amount and value of $7,716.66, upon which there was paid by said company $4,220.63, leaving unpaid at the commencement of this suit $3,496.03, which is still unpaid and was due on May 6, 1893. The material furnished by the appellee was for the use, benefit and betterment of all said property as a whole, and all of said material was used in said construction, erection and repairs aforesaid, except material to the amount and value of $212.00. “That the material which went into each particular mill or building cannot be separated and identified, the larger portion of it being gas pipe, which was placed under ground connecting and ramifying all the [617]*617buildings.” On the 12th day of May, 1893, notice of lien was filed with the proper recorder, which notice included lots owned by said company, but not within said enclosure and not covered by said buildings. It is found that $250.00 was a reasonable attorney’s fee in this cause, and it was further found that the court appointing said receiver “granted appellee the right to join said McGettigan, receiver, as defendant in this cause.” As conclusions of law upon such facts the court stated that there was due appellee $3,562.00 of principal and interest and $250.00 as attorney^ fees, for which two sums, less $212.00, appellee was entitled to a li’en upon said real estate so included within said inclosure; and “4, that plaintiff is entitled to have said lien foreclosed and the real estate sold without relief from valuation or appraisement laws to pay said judgment for $3,600.00, interest and costs.”

Judgment was rendered for appellee extending a lien upon said real estate and upon “all buildings, improvements, mills, shops, engines, boilers, machinery, furnaces, tools, implements, fixtures, rights-of-way, franchises, railroads, railroad tracks, switches, side tracks, appendages and appurtenances, in, upon, or belonging to or connected with said real estate.” The sale of said property was ordered, with directions to apply the proceeds, 1st, to the costs in this case, and of the sale; 2d, appellee’s judgment with interest; 8d, balance returned into court. It was also declared that “The purchaser at said sale shall take, as against the parties to this action, a clear title to said real estate.”

It is first urged that, though the materials supplied may have been used in the repairs and improvements of the company’s buildings, it was essential to the maintenance of a lien that they should have been supplied for the purpose of being so used. That is to say, that the appellee supplied them, at the time contem[618]*618plating the use made of them. This fact is certainly well found by the court. As will be seen the object of the purchase was stated before materials were furnished, and appellee furnished said company, upon its orders from time to time, material, each being a separate order, for construction, erection and repairing said plant, and all the buildings thereon.

It is next claimed that the conclusions of lav/ were “erroneous for the reason that it is not shown for what buildings the materials were furnished, nor in what buildings they were used, while it is shown that several of the buildings were separate and independent, and yet the lien was taken, not only on all the buildings, but also on vacant lots across the street.” While the notice of lien described other lots than those covered by the plant, the lien as adjudged by the court did not include such lots. It is not claimed for appellants that to include in the notice of such lien more land than the lien could be maintained upon would vitiate the lien, and we observe no good reason in such a claim. But that the lien was extended to all of the buildings raises a question of greater moment. The following is quoted, by counsel, from Jones on Liens, sections 1310, 1311, as stating the correct rule: ‘ Where materials are furnished for one or more of several buildings upon a large tract of land, used together in the general business of a manufacturing firm or corporation, a mechanics’ lien must be filed against the particular building or buildings only to which the materials were supplied and the lots and curtilages appurtenant thereto; but not against the entire premises, including the old buildings as well as the new.”

We have no occasion to discuss here the rule with reference to the improvement of one of a number of buildings upon a large tract of land, as the repairs of [619]*619a coal dump situated upon several hundred acres of mining land. Here we have material supplied under one contract, though at various times and upon separate orders, for the improvement of several buildings erected upon a small tract within the city of Indianapolis, the description of which we have omitted for the sake of brevity. The improvement related to all of the buildings; “connecting and ramifying all the buildings.” The buildings were erected as parts of a single plant, and, though one of them was occupied by a tenant company, that building was, in its construction, connected with, or a part of, another of the buildings, and the ground was not divided with reference to the several buildings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cato v. David Excavating Co., Inc.
435 N.E.2d 597 (Indiana Court of Appeals, 1982)
Saint Joseph's College v. Morrison, Inc.
302 N.E.2d 865 (Indiana Court of Appeals, 1973)
State Ex Rel. Elder, Rec. v. Circuit Ct., Madison County
5 N.E.2d 641 (Indiana Supreme Court, 1937)
Gayer v. Roddie
1932 OK 75 (Supreme Court of Oklahoma, 1932)
Rathburn v. Landess
129 So. 738 (Supreme Court of Florida, 1930)
William M. Graham Oil & Gas Co. v. Oil Well Supply Co.
1927 OK 338 (Supreme Court of Oklahoma, 1927)
Lively v. Evans-Howard Fire Brick Co.
1925 OK 894 (Supreme Court of Oklahoma, 1925)
Dix v. Willfred Coal Co.
132 N.E. 595 (Indiana Court of Appeals, 1921)
Sheldon v. Chicago Bonding & Surety Co.
190 Iowa 945 (Supreme Court of Iowa, 1921)
Redman v. Murray W. Sales Co.
266 F. 272 (Sixth Circuit, 1920)
West v. Dreher
126 N.E. 688 (Indiana Court of Appeals, 1920)
Gaston v. Avansino
154 P. 85 (Nevada Supreme Court, 1915)
Van Wart v. Rees
92 A. 328 (Supreme Judicial Court of Maine, 1914)
Judah v. F. H. Cheyne Electric Co.
101 N.E. 1039 (Indiana Court of Appeals, 1913)
Foster Lumber Co. v. Sigma Chi Chapter House of DePauw University
97 N.E. 801 (Indiana Court of Appeals, 1912)
Randall v. Wagner Glass Co.
94 N.E. 739 (Indiana Court of Appeals, 1911)
Crane Co. v. Erie Heating Co.
112 P. 430 (Oregon Supreme Court, 1910)
Stoltze v. Hurd
128 N.W. 115 (North Dakota Supreme Court, 1910)
Pusey & Jones v. Pennsylvania Paper Mills
173 F. 634 (U.S. Circuit Court for the District of Middle Pennsylvania, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
43 N.E. 876, 144 Ind. 614, 1896 Ind. LEXIS 213, Counsel Stack Legal Research, https://law.counselstack.com/opinion/premier-steel-co-v-mcelwaine-richards-co-ind-1896.