Integon Indemnity Corp. v. United States

34 Cont. Cas. Fed. 75,265, 12 Cl. Ct. 115, 1987 U.S. Claims LEXIS 56
CourtUnited States Court of Claims
DecidedApril 2, 1987
DocketNo. 108-84C
StatusPublished
Cited by1 cases

This text of 34 Cont. Cas. Fed. 75,265 (Integon Indemnity Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Integon Indemnity Corp. v. United States, 34 Cont. Cas. Fed. 75,265, 12 Cl. Ct. 115, 1987 U.S. Claims LEXIS 56 (cc 1987).

Opinion

ORDER DENYING DEFENDANT’S MOTION FOR SUMMARY JUDGMENT

NAPIER, Judge:

This suit arises from a contract between Gulf South Contractors, Inc., as the principal and contractor, and the Army Corps of Engineers. In this suit, the plaintiff, In-tegon Indemnity Corporation (Integon), a Miller Act payment bond surety, claims entitlement to a progress payment which it alleges was improperly paid by the defendant, United States Government, to the contractor. Defendant admits that the payment was made to the contractor, but denies that such payment was improper.

The Government has moved, over plaintiff’s objection, for summary judgment on plaintiff’s claim. It contends that there is no dispute as to any material fact and that the payment by the Government to the contractor was reasonable.

Statement of the Case

The parties’ agreed statements of uncon-troverted facts, insofar as pertinent, follow. On September 27, 1979, the Army Corps of Engineers entered into Contract No. DACA01-79-C-0117 with Gulf South Contractors, Inc. (GSC). As required by contract and the Miller Act, 40 U.S.C. § 270a (1976), performance and payment bonds were obtained by GSC from Integon on October 12, 1979. On January 27, 1981, GSC notified the Government that further payments under the contract should be forwarded to:

Gulf South Contractor’s Inc.
c/o Palmer Howard and Nowak
302 3rd Street, Suite 4
Neptune Beach, Florida 32233

On March 12, 1981, a Government inspector determined during a routine inspection that GSC was “less than diligent” in completing the contract. He also noted that a subcontractor had quit work due to nonpayment and concluded that GSC appeared to lack the ability to complete the remainder of the work on the project in a timely manner. As a result of the lack of work being accomplished, the Government speculated that GSC was experiencing financial problems. By a letter dated March 16, 1981, the Government advised GSC that it was not making a diligent effort to complete the contract. On or about March 24, 1981, the Government made a telephone inquiry to Integon regarding GSC’s financial problems. Integon’s counsel and rep[117]*117resentative, Edward Nowak, responded to the inquiry and informed the Government that he would investigate the problem. On April 22, 1981, GSC notified the Government that GSC was no longer in a position to complete the contract. On April 27, 1981, Integon notified the Government by mailgram that it had declared GSC in default and that no further distributions of contract funds should be made to GSC without the written consent of Integon.

By a letter dated June 8, 1981, the Government requested Integon to provide information regarding the “means and time proposed by yourself and/or our prime contractor for completion of the project.” Plaintiffs representative and the Government contracting officer corresponded and met at various times throughout the summer. The Government organized a meeting for September 17, 1981, between GSC, Integon and the Government to resolve the issues of completion of the contract and future payments. Plaintiffs representative requested that the meeting be rescheduled because he could not attend due to a conflict. The meeting was held as scheduled on September 17, 1981, without plaintiffs representative. After the meeting with GSC, the Government determined that it should make payments under the contract to the contractor directly. Plaintiffs representative was not informed of this decision. On October 8, 1981, the Government paid the contractor $44,413 directly, pursuant to payment number 14.

On December 14, 1981, Integon made a demand for payment number 14. The Government denied plaintiffs demand. A final payment of $6,410 was paid directly to plaintiff reflecting a deduction of $1,090 from the contract price for the cost of completion work incurred by the Government. Integon filed this suit for reimbursement of the alleged improper payment to the contractor.

Discussion

In moving for summary judgment the Government asserts that the contracting officer exercised reasonable discretion in directing that payment number 14 of $44,-413 be paid directly to the contractor, GSC, rather than to the contractor’s surety, In-tegon. Integon contends that performance of the contract was complete and therefore the Government was a stakeholder and that as stakeholder, the Government may not make payments under the contract absent a judicial determination or an agreement between the parties as to disbursement.

In Balboa Insurance Co. v. United States, 775 F.2d 1158, 1162 (Fed.Cir.1985), the Federal Circuit ruled that “ * * * the United States becomes a stakeholder with a duty of acting with reasoned discretion when a Miller Act surety alleges that the contractor has breached the contract by defaulting under one of the bonds.”

The Federal Circuit has reiterated1 the following factors as important in determining whether the Government has exercised reasonable discretion in distributing funds:

(1) Attempts by the Government after notification by the surety, to determine that the contractor had the capacity and intent to complete the job. (2) Percentage of contract performance completed at the time of notification by the surety. (3) Efforts of the Government to determine the progress made on the contract after notice by the surety. (4) Whether the contract was subsequently completed by the contractor (not conclusive, but relevant to show the reasonableness of the contracting officer’s determination of the progress on the project). (5) Whether the payments to the contractor subsequently reached the subcontractors and materialmen (this goes to the equitable obligation of the Government to subcontractors and others to see that they will be paid; also, because the surety is liable to the subcontractors, any money that [118]*118reachés them furthers the objectives of the surety as well as those of the Government). (6) Whether the Government contracting agency had notice of problems with the contractor’s performance previous to the surety’s notification of default to the Government. (7) Whether the Government’s action violates one of its own statutes or regulations. (8) Evidence that the contract could or could not be completed as quickly or cheaply by a successor contractor. [Citations omitted.]

Balboa Insurance Co., 775 F.2d at 1164, 1165.

While there is a significant difference between the Government’s role before and after completion of performance on a contract, Argonaut Insurance Co. v. United States, 193 Ct.Cl. 483, 493, 434 F.2d 1362, 1367-68 (1970), the issue of whether the Government exercised its discretion reasonably and considered the surety’s interest is material whenever the Government is in the position of stakeholder. Balboa Insurance Co., 775 F.2d at 1164.

A motion for summary judgment under Rule 56 shall be granted where it appears from the pleadings that there is no genuine issue as to any material fact and that such facts entitle the moving party to a judgment as a matter of law. RUSCC Rule 56(c);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Fidelity & Guaranty Co. v. United States
35 Cont. Cas. Fed. 75,637 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,265, 12 Cl. Ct. 115, 1987 U.S. Claims LEXIS 56, Counsel Stack Legal Research, https://law.counselstack.com/opinion/integon-indemnity-corp-v-united-states-cc-1987.