This text of 10 Cl. Ct. 703 (Hendricks v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hendricks v. United States, 10 Cl. Ct. 703, 1986 U.S. Claims LEXIS 799 (cc 1986).

Opinion

[704]*704ORDER DENYING PARTIES’ MOTIONS FOR SUMMARY JUDGMENT

MOODY R. TIDWELL, III, Judge:

This inverse condemnation case comes before the court on Cross-Motions for Summary Judgment and involves an alleged taking in violation of the Fifth Amendment of the United States Constitution over which this court has jurisdiction under 28 U.S.C. § 1491 (1982).

The plaintiffs are owners of certain property located upstream from the Harry S. Truman (HST) Dam and Reservoir. The United States had obtained flowage easements on the property prior to plaintiffs purchase. Plaintiffs assert that the United States has operated the HST dam in an improper manner and for purposes that were not within those designated by the dam’s plan of operations. This, they allege, has resulted in their property being inundated with water more often and for longer durations than would have occurred had the dam’s plan of operations been followed. The alleged improper operation has destroyed both their crops and their ability to utilize the property for agricultural purposes. Plaintiffs further assert that the flooding has been in excess of the amount and duration of any anticipated flooding represented by defendant at the time the flowage easements were taken. Plaintiffs move for summary judgment as to liability, and seek eventual compensation for the enlarged flowage easements that have allegedly been imposed on their property at such time that the parties agree or the court determines the proper valuation of their property.

The United States contends that the dam was neither used for improper purposes or operated improperly, and that any flooding that has occurred has been within the terms of the existing flowage easements. Defendant also contends that the parol evidence rule prevents the plaintiffs from altering the terms of the easements by any extrinsic evidence, and further asserts that the burden of risk of any flooding which has subsequently occurred shifted from the government to the property owner once the easements were properly taken.

After careful consideration of the parties’ briefs, supporting memoranda, and the relevant law, the court concludes that there are genuine disputed issues of material fact; and that this matter is not ripe for summary judgment. Therefore, the Defendant’s Motion for Summary Judgment, and Plaintiffs’ Cross-Motion for Summary Judgment are denied.

FACTS

In 1954, Congress authorized construction of the Harry S. Truman Dam (HST) as part of the general comprehensive plan for flood control and other purposes in the Missouri River Basin. See River and Harbor Act-Flood Control Act of 1954, Pub. L. No. 83-780, amended by River and Harbor Act of 1962, Pub. L. No. 87-874, 76 Stat. 1173 (1962).

As part of the process of constructing the dam and the resulting formation of the reservoir, certain lands that were situated within the area to be inundated were condemned by the United States through its power of eminent domain. The government took flowage easements on lands that were not to be permanently inundated, but which might occasionally be flooded by the operation of the dam.

The value of the easements, as determined by defendant, was established by developing a plan of operations for the dam that estimated the intended elevation for the reservoir pool, the flood frequency, and the duration of inundation, if and when flooding should occur. This information was used by the defendant to negotiate any flowage easements that were needed for the proper operation of the dam, including the flowage easements on plaintiffs’ property.

Under the dam’s plan of operations, waters from the reservoir were to be released at a rate of flow sufficient to meet certain target flow rates which were measured at various downstream gauges. The amount of water to be released depended on vari[705]*705ous surrounding circumstances, but was to be an amount sufficient to minimize flooding, provide hydroelectric power, provide a safe recreational area for the public, and minimize harmful effects on fish and wildlife. The primary function of the dam was flood control, however, this use was not exclusive.

In November of 1977, the United States, through condemnation proceedings, acquired a flowage easement for $170,000 from Mrs. Katie Schmidt on 404 acres of property designated as Tract 8510E. (The price of the easement represents an out of court settlement between defendant and Mrs. Schmidt.) In April of 1978, the defendant acquired another flowage easement on 38.3 acres of property, designated as Tract 8509E, from Mrs. Sarah M. Ains-worth. This easement was obtained by an Easement Deed for a purchase price of $8,000. Both tracts of land are situated upstream from the HST dam near the confluence of Clear Creek and the Osage River, and contain the property which is the subject matter of this litigation.

The pertinent language of the flowage easement on Tract 8510E reads as follows:

The public uses for which said land is taken are as follows: The said land is necessary to provide for flood control in the Missouri River Basin and for other uses incident thereto. The said land has been selected for acquisition by the United States for use in connection with the Harry S. Truman Dam and Reservoir, Missouri, as part of the general comprehensive plan for flood control and other purposes in the Missouri River Basin, and for such other uses as may be authorized by Congress or by Executive Order. ******
[The United States has the right] occasionally to overflow, flood and submerge the land lying above elevation 706' m.s.l. ... in connection with the operation and maintenance of the project.
Together with all right, title and interest in and to the structures and improvements now situate on the land, except fencing above elevation 706' m.s.l.; reserving, however, to the owner, his heirs and assigns, the right and privilege at the owner’s expense to use and maintain the levee and related water pumping system, if any, now situate on the land; provided, however, that the aforesaid privilege of use and maintenance shall be totally subordinate to the absolute right of the United States, without notice and without incurring liability of any nature whatsoever, to remove, breach, flood or otherwise damage or destroy in any manner whatsoever, the said levee and related water pumping system ... The above estate is taken subject to existing easements ... reserving, however, to the owner, his heirs and assigns, all rights and privileges which may be used and enjoyed without interfering with the use of the project for the purposes authorized by Congress or abridging the rights and easement hereby acquired ...

The pertinent language in the flowage easement on Tract 8509E reads as follows:

[The United States has] the perpetual right, power, privilege and easement occasionally to overflow, flood and submerge Tract No. 8509E ... in connection with the operation and maintenance of the Harry S. Truman Dam and Reservoir Project ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Allenfield Associates v. United States
42 Cont. Cas. Fed. 77,267 (Federal Claims, 1998)
Nematollahi v. United States
38 Fed. Cl. 224 (Federal Claims, 1997)
Sankey v. United States
22 Cl. Ct. 743 (Court of Claims, 1991)
Government Systems Advisors, Inc. v. United States
25 Cl. Ct. 554 (Court of Claims, 1990)
California Sand & Gravel, Inc. v. United States
36 Cont. Cas. Fed. 75,968 (Court of Claims, 1990)
United States Fidelity & Guaranty Co. v. United States
35 Cont. Cas. Fed. 75,637 (Court of Claims, 1989)
Marvel Engineering Co. v. United States
14 Cl. Ct. 614 (Court of Claims, 1988)
Integon Indemnity Corp. v. United States
34 Cont. Cas. Fed. 75,265 (Court of Claims, 1987)
United Nuclear Corp. v. United States
12 Cl. Ct. 45 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
10 Cl. Ct. 703, 1986 U.S. Claims LEXIS 799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hendricks-v-united-states-cc-1986.