In re Paris Air Crash of March 3, 1947

69 F.R.D. 310, 1975 U.S. Dist. LEXIS 15174
CourtDistrict Court, C.D. California
DecidedNovember 20, 1975
DocketMDL 172
StatusPublished
Cited by9 cases

This text of 69 F.R.D. 310 (In re Paris Air Crash of March 3, 1947) is published on Counsel Stack Legal Research, covering District Court, C.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Paris Air Crash of March 3, 1947, 69 F.R.D. 310, 1975 U.S. Dist. LEXIS 15174 (C.D. Cal. 1975).

Opinion

MEMORANDUM OPINION AND ORDER FOR SEPARATE TRIALS

PEIRSON M. HALL, Senior District Judge.

The general nature of the cases arising from the Paris air crash of March 3, 1974, and the resulting complexities are set out in the Memorandum of this Court on the question of the applicable choice of law on damages, filed August 1, 1975, D.C., 399 F.Supp. 732, and need not be repeated here except as necessary.

The matter immediately before the Court involves the various motions for separate trials, and the oppositions thereto, filed by the several parties in these cases.

It first appeared that the motions had become moot after the announcement in open court on May 27, 1975, by McDonnell Douglas, General Dynamics, and Turkish Airlines that agreement had been reached which would eliminate issues of liability and which would permit prompt proceedings on the question of damages.1 On such representation by defendants, the Court stayed discovery until June 16, then to July 8, [313]*313and then until August 25, 1975, for a report on progress on settlement.

As pointed out in this Court’s previous opinion on “choice of law,” the agreement was shown to the Court in camera; and upon consent of defendants, the Court made a brief, but not full, statement of its contents in open court and returned it to defendants. Upon order, it has since been filed with the Court in camera. The agreement is dated July 8, 1975.

The Court indicated to counsel that unless there was substantial progress on settlement of the 337 death claims by August 25, 1975, the stay of discovery would be lifted and the parties would proceed with discovery so that it would be completed and the plaintiffs’ cases on death claims disposed of by trial as soon as possible.

On August 25, 1975, no cases had been settled, nor had any formula for settling them been reached, but all parties agreed that sufficient progress had been made to warrant the Court in further staying discovery to permit the parties in good faith to continue their efforts at settlement of the damage claims. The matter was continued to October 6, 1975, for further report.

As indicated in the Memorandum on damages, three teams were designated for defendants to negotiate with different sets of plaintiffs’ counsel. The Court was of the distinct impression that by creating the teams, each team would have full authority to make a firm and agreed amount of settlement in each case which would be binding on all defendants who were parties to the agreement. Each of the defendant teams indicated that they were ready to negotiate immediately and that each team had sufficient personnel so that the plaintiffs would not have to deal with just one person or one firm.2 This was necessary because it would take about as long for one person or one firm to negotiate settlement with the more than 1100 claimants for the 337 decedents as it would to try the question of damages as to each decedent.

In this Court’s experience, it takes an average of two days to try death damages, or a total of 674 trial days for the 337 decedents. Allowing five trial days a week and 52 weeks a year, trial on damages alone would take over two and a half years.3 This does not take into consideration the probable necessity for interpreters, which would lengthen the estimate.

At the hearing on October 6, 1975, there were conflicting reports on the numbers and the timing of various demands, offers, counter-demands, and counter-offers. It appeared that there had been a flurry of activity by defendants as the hearing date drew near, much the same as there had been just prior to the preceding hearing on August 25. It was announced that a settlement figure had been reached in only three cases, each involving a single decedent, out of the 205 cases and 337 decedents.4

While some delays were occasioned by the need of some groups to get actuarial information based on this Court’s Memorandum on damages filed August 1, 1975, D.C., 399 F.Supp. 732, it appears from the October 6 hearing that instead of leaving the amount of settlement to the other negotiators, the final word on all settlements must come from one man, viz., one of 10 attorneys who have appeared in court from time to time for McDonnell Douglas. This fact alone suggests the possibility that the good faith anxiety to settle these cases quickly might be more of a gloss on the oft-[314]*314expressed desire of McDonnell Douglas for early disposition than an abiding will to dispose of these cases promptly. This Court cannot in any justice whatsoever permit a procedure which holds up the finality of the rights of over 1100 claimants for years, either by settlement or by delaying trial, to be asserted or allowed by one man.

What emerges is a serious doubt as to the likelihood of early settlements. This is fortified by the history of this litigation to date; and what seems to loom is the necessity for trial, not only of damages but also of liability. Especially is this so in view of the pointblank refusal of all defendants to settle unless punitive damages are entirely waived. Such waiver is extremely improbable in view of the insistence of at least two groups of plaintiffs in pursuing their demands for punitive damages.

Accordingly, the Court concludes that the motions for separate trials on liability must now be decided.5

Where actions are consolidated and transferred for pre-trial proceedings pursuant to 28 U.S.C. § 1407, the decision whether to consolidate or to separate certain actions is addressed to the sound discretion of the district judge. A Rule 42 motion is a pre-trial proceeding, and it is appropriate that it be decided by the transferee judge. In re Cessna, Aircraft Distributorship Antitrust Litigation, 359 F.Supp. 543 at 544 (Jud.Pan.Multi.Lit.1973). Even if this were not so, all but 12 of the plaintiffs’ cases were filed in this district and would be remanded for trial to this district at the conclusion of proceedings under 28 U.S.C. § 1407.

While jurisidiction of these cases exists under 28 U.S.C. § 1331 (federal question), 28 U.S.C. § 1337 (Congressional acts regulating commerce), and 28 U.S.C. § 1332 (diversity) and the Federal Rules of Civil Procedure control procedures in this court, it is noted that the language of the California Code of Civil Procedure, Section 1048, is identical to that in Rule 42 of the Federal Rules of Civil Procedure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carr v. County of San Diego
S.D. California, 2022
J. B. v. G6 Hospitality, LLC
N.D. California, 2021
Pinal Creek Group v. Newmont Mining Corp.
218 F.R.D. 652 (D. Arizona, 2003)
Simon v. Philip Morris Inc.
200 F.R.D. 21 (E.D. New York, 2001)
Stoddard v. Ling-Temco-Vought, Inc.
513 F. Supp. 314 (C.D. California, 1981)
Organic Chemicals, Inc. v. Carroll Products, Inc.
86 F.R.D. 468 (W.D. Michigan, 1980)
In Re Air Crash Disaster Near Chicago, Ill., Etc.
480 F. Supp. 1280 (N.D. Illinois, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
69 F.R.D. 310, 1975 U.S. Dist. LEXIS 15174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-paris-air-crash-of-march-3-1947-cacd-1975.