In re Chaves A250 Permit Reconsider

2014 VT 5, 93 A.3d 69, 195 Vt. 467, 2014 Vt. 5, 2014 WL 185031, 2014 Vt. LEXIS 6
CourtSupreme Court of Vermont
DecidedJanuary 17, 2014
DocketNo. 13-069
StatusPublished
Cited by30 cases

This text of 2014 VT 5 (In re Chaves A250 Permit Reconsider) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Chaves A250 Permit Reconsider, 2014 VT 5, 93 A.3d 69, 195 Vt. 467, 2014 Vt. 5, 2014 WL 185031, 2014 Vt. LEXIS 6 (Vt. 2014).

Opinion

Reiber, C.J.

¶ 1. Neighbors Kraig and Doreena Hart appeal an Environmental Division order granting an Act 250 permit to applicants Chaves Londonderry Gravel Pit, LLC and its principal David Chaves for operation of a sand and gravel quarry. Neighbors argue that: (1) modifications made to the project prior to trial were substantial enough to require a remand to the district commission or a continuance of the trial; (2) the court erred in con.1uding that the noise from the project would not have an undue adverse aesthetic impact; (3) the court erred in finding that the project did not impact any historic sites and that the project complied with the region.1 and town plans; and (4) the court imposed an unenforceable restriction in condition 16 related to noise levels. We affirm, but remand for clarification of condition 16.

¶ 2. Applicants’ sand and gravel pit is located along the eastern border of Route 100 in the town of Londonderry. Neighbors own a country inn on property that lies across Route 100 from the operation. The project site has been historically used for sand and gravel extraction for at least fifty years. Applicants purchased the property and began extracting sand, rock and gravel from the site [471]*471in 1997. At the time, no land-use permits covered the extraction operations. Applicants operated under the assumption that their activities on a preexisting quarry were grandfathered and required no state land use approval. The local environmental commission issued a jurisdiction.1 opinion, finding that the scope of applicants’ operation amounted to a substantial change from the preexisting operation and therefore a permit was required. Applicants appealed this determination to the Environmental Division.

¶ 3. Meanwhile, applicants also applied for an Act 250 permit. The district environmental commission ultimately approved the application subject to several conditions. Applicants disputed some of the conditions, and appealed to the Environmental Division. Several parties entered appearances and filed cross-appeals. Neighbors entered an appearance in the Environmental Division as interested parties, but did not file a cross-appeal.

¶ 4. The jurisdiction.1 and permit appeals were coordinated for purposes of pretrial discovery, motion practice and trial. Trial was set for March 5, 2012. On February 21, 2012, applicants filed a motion to adopt a settlement agreement, which was reached with several of the parties. The terms of the settlement agreement contained proposed changes to the project, in.1uding: changing the access point to the quarry from a proposed new entrance at the south of the quarry to an existing access road at the north end of the quarry; changing the loading area and a related berm for noise mitigation; adding noise mitigation berms; limiting the maximum number of truck trips per day; restricting the days and weeks when drilling, blasting and crushing may occur; and establishing a blasting plan.

¶ 5. On February 28, 2012, neighbors filed an objection to applicants’ motion to adopt the settlement agreement, and filed a motion to continue the trial. Neighbors argued that they lacked sufficient time to adequately prepare for trial and that the proposed settlement agreement made material changes to the project that required a remand to the district commission for consideration in the first instance. In particular, neighbors argued that the change in location of the access point to the quarry was a material change that would negatively impact their property. The trial was reset for March 13, 2012.1

[472]*472¶ 6. On March 9, 2012, the trial court denied neighbors’ motion for a remand. The court acknowledged neighbors’ contention that they were unfairly disadvantaged in particular by applicants’ decision to change the access point. The court ruled, however, that the changes were not substantial enough to change the character of the project, and that a remand was not necessary. The court noted that in reviewing a proposed Act 250 project, it was required to consider “all reasonable alternatives to the proposed project, with the limits of not changing the very essence of the project.” Because the parties were obligated to be prepared to address differing proposals, the court found no basis to delay the trial and denied the motion for a further continuance.

¶ 7. Prior to trial, the court informed the parties that it would reserve judgment on the motion to accept the settlement agreement until trial. The court explained that it would make “its own independent determinations as to the appropriate weight and credibility to be assigned to all trial evidence.”

¶ 8. At trial, applicants presented testimony from several different experts related to the project’s blasting plan, impact on traffic and noise creation. At the beginning of the hearing, neighbors objected generally to the admission of any expert evidence relating to changes made as a result of the settlement agreement, arguing that they were provided with an insufficient opportunity to investigate or evaluate the experts’ opinions on how the changed entry point would impact the project. Consistent with its pretrial ruling, the court overruled the objection and allowed the experts to testify.

¶ 9. Neighbors were the only parties to appear and oppose the project at trial. Neighbors cross-examined applicants’ experts and neighbor Doreena Hart testified, but neighbors did not present experts of their own.

¶ 10. The court issued a lengthy written order. As to the jurisdiction.1 appeal, the court affirmed the district commission, holding that applicants’ operations increased the manner and intensity of the preexisting operation and therefore required an Act 250 permit. As to the merits appeal, the court noted that its review was limited to addressing the questions raised by appli[473]*473cants, which related to four criteria and subcriteria: criterion 5 relating to traffic impacts, criterion 8 concerning aesthetic impacts, criterion 9(E) about extraction of earth resources, environmental impacts and site rehabilitation, and criterion 10 about conformity with the town and region.1 plans. The court found that with appropriate conditions the project conformed to all of the criteria, and a permit should be issued. Neighbors filed a timely notice of appeal.

I.

¶ 11. We first address neighbors’ procedural arguments. On appeal, neighbors argue that the modifications to the project made as part of the settlement were substantial and required a remand to the district commission or, at the very least, a continuance. The Environmental Division has authority to “affirm, reverse, or modify the decision of the tribunal appealed from, may remand the case for further proceedings consistent with the order of the court, and may expressly set forth conditions and restrictions with which the parties must comply.” V.R.E.C.P. 5(j). Thus, the Environmental Division may change a proposal without remand as long as the revisions do not amount to “truly substantial changes to the form or type of an application.” In re Sisters & Bros. Inv. Grp., LLP, 2009 VT 58, ¶ 21, 186 Vt. 103, 978 A.2d 448.

¶ 12. Neighbors argue that the changes were so significant that a remand to the district commission was required. Neighbors liken the situation to that in In re Torres, 154 Vt. 233, 236-37, 575 A.2d 193

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Petition of Apple Hill Solar LLC
2021 VT 69 (Supreme Court of Vermont, 2021)
In re B&M Realty, LLC
2016 VT 114 (Supreme Court of Vermont, 2016)
In re LaBerge NOV
2016 VT 99 (Supreme Court of Vermont, 2016)
Margaret Pratt Assisted Living
Vermont Superior Court, 2016
Killington Village Master Plan Act 250
Vermont Superior Court, 2016
N.E. Materials Gp.
Vermont Superior Court, 2016
N.E. Materials Grp Act 250
Vermont Superior Court, 2016
Killington Resort Parking Project Act 250
Vermont Superior Court, 2016
Creative Spirit CU & SP
Vermont Superior Court, 2015
Costco SW Discharge Permit
Vermont Superior Court, 2015

Cite This Page — Counsel Stack

Bluebook (online)
2014 VT 5, 93 A.3d 69, 195 Vt. 467, 2014 Vt. 5, 2014 WL 185031, 2014 Vt. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-chaves-a250-permit-reconsider-vt-2014.