N.E. Materials Gp.

CourtVermont Superior Court
DecidedApril 18, 2016
Docket35-3-13 Vtec
StatusPublished

This text of N.E. Materials Gp. (N.E. Materials Gp.) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.E. Materials Gp., (Vt. Ct. App. 2016).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Environmental Division Unit Docket No. 35-3-13 Vtec

N.E. Materials Group Amended A250 DECISION ON THE MERITS Permit (ALTERED)

Twenty-six citizens, collectively known as “Neighbors for Healthy Communities” (Appellants), appeal a District 5 Environmental Commission (District Commission) decision approving the application of North East Materials Group, LLC (NEMG) and Rock of Ages Corporation (ROA) (collectively, Applicants) for a hot-mix asphalt plant at the ROA quarry in the Town of Barre, Vermont. NEMG and ROA cross-appeal.1 On May 4, 5, and 6, 2015, the Court held a three-day merits hearing at the Vermont Superior Court, Civil Division, Washington Unit in Montpelier, Vermont. During the final pre- trial conference in this matter all parties agreed that the Court need not conduct a site visit, as the Court had already performed a site visit in the related matter noted in footnote 1 below. Appearing at the merits hearing were Alan P. Biederman, Esq. and James P.W. Goss, Esq. representing the Applicants; Douglas A. Ruley, Esq.2 and Laura B. Murphy, Esq. representing the Appellants; Gregory J. Boulbol, Esq. representing the Natural Resources Board; and Elizabeth Lord, Esq. and Megan O’Toole, Esq. representing the Agency of Natural Resources (ANR). At the start of trial all parties provided a stipulation limiting the issues for trial to the following: 1 Appellants and NEMG are also parties to separate but related litigation over whether NEMG’s rock crushing operations on ROA’s quarry tract are subject to Act 250 jurisdiction. See In re N.E. Materials Grp. LLC A250 JO #5-21, No. 143-10-12 Vtec. In April 2014, this Court held that NEMG’s rock crusher was part of ROA’s grandfathered preexisting development, and not subject to Act 250 jurisdiction. In re N.E. Materials Grp. LLC A250 JO #5-21, No. 143-10-12 Vtec, slip op. at 14–15 (Vt. Super. Ct. Envtl. Div. Apr. 28, 2014) (Walsh, J.). Appellants appealed that decision, and the Vermont Supreme Court reversed and remanded for further findings. In re N.E. Materials Grp. LLC Act 250 JO #5-21, 2015 VT 79, ¶ 35. On remand we again held that the rock crusher was not a substantial change to NEMG’s preexisting development, and therefore that it was not subject to Act 250 jurisdiction. In re N.E. Materials Grp. LLC A250 JO #5-21, No. 143-10-12 Vtec, slip op. at 20–21 (Vt. Super. Ct. Envtl. Div. Dec. 23, 2015) (Walsh, J.). Appellants have again appealed that determination to the Vermont Supreme Court. 2 In a December 21, 2015 Notice of Withdrawal, attorney Ruley withdrew from this matter. Attorney Murphy continues to represent Appellants.

1 a. Air pollution under Criterion 1. b. Traffic under Criteria 5 and 9(k). c. Aesthetics under Criterion 8, with the understanding that “noise” as listed in Appellants’ Amended Statement of Questions includes only noise from trucks.

The stipulation also provides:

With respect to all other criteria under Act 250 not set forth [above], and all other provisions and requirements of Act 250, the parties agree as a matter of law and as a matter of fact that the decision(s) of the District Commission below may be incorporated into this Court’s decision and final order.

Thus, all other issues presented in Appellants’ Statements of Questions are outside the scope of our review. Based upon the evidence presented at trial, which was put into context by the site visit conducted in the related appeal, No. 143-10-12 Vtec, the Court renders the following findings of fact and conclusions of law.

Findings of Fact

I. The Project 1. NEMG and ROA seek Act 250 approval for construction and operation of a hot-mix asphalt plant and related fixtures and equipment (the Project). 2. The Project is to be located on the ROA quarry tract. 3. ROA is a quarrying operation comprised of several smaller individual quarries active from the late 1800s to current times, now all aggregated as a single parcel under ROA ownership and operation. 4. All total, ROA comprises approximately 930 acres in Barre, Vermont and 230 acres in Williamstown, Vermont. Several roads transect the ROA property, including Graniteville Road. Roads also connect work areas throughout the ROA property. 5. Graniteville Road runs northwest/southeast, and bisects the ROA tract into northern and southern portions. 6. The Project is on 3.46 acres on the south side of Graniteville Road in the Town of Barre, Vermont. The Project site is located in the interior of the ROA quarrying operation.

2 7. Graniteville Road connects the villages of Upper and Lower Graniteville (both part of Barre Town). Lower Graniteville is located northwest of and at a lower elevation than Upper Graniteville. 8. Lower Graniteville has a general store, senior center, playground, post office, church, school bus stop, and residences. 9. Upper Graniteville is mostly residential. 10. The zoning district for the Project location is “Industrial” pursuant to the Town of Barre Zoning Regulations. 11. The approved maximum operating capacity of the Project is 180 tons of asphalt per hour, while the maximum design operating capacity is 250 tons per hour. The land use permit approved by the District Commission included a rolling average production limit of 4,500 tons per week during any given 45-day period.3 12. The Project will operate from May 1 through mid-November, Monday through Saturday, from 6:00 a.m. to 4:00 p.m. 13. The Project is a batch-type plant, meaning that hot-mix asphalt is manufactured on an as-needed, per-truck-load basis. Prepared hot-mix is not stored for extended periods. 14. The District Commission originally approved the Project on January 24, 2013 and then issued an Altered Land Use Permit on February 26, 2013. 15. The Project was constructed in the summer of 2013 and has been operating since that time (two operating seasons).

II. Air Impacts 16. The Project has several points of potential air emissions. A smokestack emits steam and exhaust gases; temporary storage tanks are equipped with filtered vents; and loading and unloading asphalt trucks may cause fugitive emissions. 17. Trucks carrying asphalt may also emit diesel and asphalt fumes.

3 The permit authorized NEMG to seek permission from the District Coordinator to exceed this rolling average limit “as appropriate . . . to address particular projects or circumstances.”

3 18. The Project has an air pollution control permit issued by ANR on June 15, 2012 (Air Permit). 19. The Air Permit allows NEMG to emit the following quantities of pollutants: a. Particulate matter larger than 10 micrometers in size: 3.2 tons per year (tpy) b. Particulate matter of 10 micrometers or smaller: 2.1 tpy c. Sulphur dioxide: 0.4 tpy d. Oxides of nitrogen: 1.9 tpy e. Carbon monoxide: 9.8 tpy f. Volatile organic compounds: 1.0 tpy g. Criteria Pollutants: 10 tpy h. Hazardous air pollutants: 10 tpy each and 25 tpy total 20. Because each of these emission levels is below 50 tons per year, the Project is not a Major Air Pollution Source under Vermont’s Air Pollution Control Regulations (Regulations), and is not subject to review under Subchapter V of the Regulations. It is still subject to review under Subchapter II. 21. The Air Permit includes the following design requirements and emission limits to reduce air pollution: a. A bag house to control particulate emissions from the Project, b. Mandatory production limits and combustion efficiency of the rotary dryer, c. A clean fuel source—liquid petroleum gas—to fire the Project. 22. The Air Permit also imposes the following operational controls to protect against air pollution: a. The first 500 feet of the access road must be paved and regular water application and sweeping is required to reduce dust, b. All trucks exiting the Project must be covered, c. Active aggregate storage piles must be kept moist to reduce dust, d.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rice v. Santa Fe Elevator Corp.
331 U.S. 218 (Supreme Court, 1947)
City of Burbank v. Lockheed Air Terminal, Inc.
411 U.S. 624 (Supreme Court, 1973)
Altria Group, Inc. v. Good
555 U.S. 70 (Supreme Court, 2008)
Dan's City Used Cars, Inc. v. Pelkey
133 S. Ct. 1769 (Supreme Court, 2013)
Keck v. Commonwealth Ex Rel. Golden
998 S.W.2d 13 (Court of Appeals of Kentucky, 1999)
In Re Eastview at Middlebury, Inc.
2009 VT 98 (Supreme Court of Vermont, 2010)
In Re Hawk Mountain Corp.
542 A.2d 261 (Supreme Court of Vermont, 1988)
In Re Pilgrim Partnership
572 A.2d 909 (Supreme Court of Vermont, 1990)
In Re Rinkers, Inc.
2011 VT 78 (Supreme Court of Vermont, 2011)
In Re Appeals of ANR Permits in Lowell Mountain Wind Project
2014 VT 50 (Supreme Court of Vermont, 2014)
In re Chaves A250 Permit Reconsider
2014 VT 5 (Supreme Court of Vermont, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
N.E. Materials Gp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ne-materials-gp-vtsuperct-2016.