Creative Spirit CU & SP

CourtVermont Superior Court
DecidedNovember 17, 2015
Docket99-7-153Vtec
StatusPublished

This text of Creative Spirit CU & SP (Creative Spirit CU & SP) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Creative Spirit CU & SP, (Vt. Ct. App. 2015).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Vermont Unit Docket No. 99-7-13 Vtec

Creative Spirit Conditional Use & Site Plan Approval (After Remand)

Decision on the Merits

Applicant Sheila Bedi seeks conditional use and site plan approval to convert an existing single-family home, located at 154 West Fairlee Road in the Town of Thetford, Vermont, into a child daycare facility (“the Project”). The pending application has a somewhat long and tortured history that warrants some explanation. We do so at the introduction of this Decision on the Merits because, while the procedural history has several chapters, the substantive part of our Merits Decision only addresses the pending application based upon the evidence introduced and admitted at trial.

Procedural History Ms. Bedi first submitted a conditional use and site plan approval application on August 23, 2012. The Town of Thetford Development Review Board (“the DRB”) held an initial hearing on the application on September 25, 2012. The hearing was continued to October 9, 2012 and then again to October 23, 2012. The DRB then issued a written decision granting Ms. Bedi’s application with conditions on November 27, 2012. A number of concerned neighbors timely appealed that decision to this Court. This Court assigned Docket No. 168-12-12 Vtec to that appeal. At the request of the Town of Thetford (“Town”) and with the consent of Ms. Bedi and the appealing neighbors, the Court remanded that application to the DRB to make further findings of fact and conclusions of law that were not present in the November 27, 2012 decision. In granting the motion to remand, the Court dismissed, without prejudice, that first appeal. 1 The DRB approved her second application, with conditions, in a decision dated July 2, 2013. Neighbors Ridge Satterthwaite, Sally Gage, Cathy Estes, Peter Estes, Deborah McKee, Glenn McKee, Christine Kogel, Cleopatra Mathis, Philip Banios, Helen Drew, Jon Kryander, Cathy Roberts, and Joe Roberts (“Appellants”) timely appealed that second DRB approval to this Court. Marjorie Powers (a neighbor) and Fred and Bethany Budzyn (the current owners of the land on which Applicant plans to develop her daycare facility) appeared as Interested Persons. Ms. Bedi and the Town are represented by Brian P. Monaghan, Esq. Appellants are represented by Nathan H. Stearns, Esq., who was assisted at trial by attorney Daniel C. Hershenson, Esq. The Interested Persons are self-represented. Appellants filed a twenty-three-question Statement of Questions, presenting issues generally related to conditional use and site plan approval under the Town of Thetford, Vermont Zoning Bylaw (“Bylaws”), including issues of parking, traffic and circulation, lighting, landscaping, grading and drainage, impacts on the character of the area, noise, visual impacts, and state-issued wastewater and water-supply permits. Ms. Bedi and the Town moved for summary judgment in their favor on all of Appellants’ questions. In response, Appellants agreed to withdraw three of their twenty-three questions, but opposed the pending summary judgment motion on the remaining questions. The Court thereafter dismissed Questions 2, 21, and 22 (the questions Appellants agreed to withdraw), determined that summary judgment should be entered in Applicant’s favor as to Question 1, and that the applicable law required that Question 23 be dismissed. In re Creative Spirit Conditional Use & Site Plan Application, No. 99-7-13 Vtec, slip op. at 4–6 (Vt. Super. Ct. Envtl. Div. Sept. 26, 2014) (Durkin, J.). None of the testimony or arguments at trial caused the Court to reconsider these pre-trial determinations. We therefore incorporate by this reference those determinations into our Merits Decision, thereby rendering them final. The Court determined that the remaining legal issues (addressed in Appellants’ Questions 3 through 20, inclusive) could not be resolved on summary judgment, since Appellants had presented a basis for disputing the facts material to each of those legal issues. Id. at 6–7. The Court determined that a trial was necessary in order to resolve these disputes over material facts. Id.

2 The matter was initially set for a one-day trial on October 9, 2014. When it became apparent that the trial could not be completed that day, the trial was continued on the following day (Friday, October 10, 2014). When it then became apparent that a third day was needed to complete the trial, the Court searched for the next available day, which was November 5, 2014. The trial was completed that day. Prior to the first day of trial (October 9, 2014), the Court conducted a site visit with the parties and their respective attorneys and experts. The site visit provided helpful context for the evidence that was presented at trial. Once the trial was completed, the parties requested and the Court allowed additional time for the filing of proposed findings of fact and conclusions of law and responses thereto. Those filings were completed and this matter came under advisement on December 31, 2014. Due to other commitments and administrative matters, the Court delayed the research, deliberation, and drafting required to complete this Merits Decision, for which the Court offers its apologies to the parties and their counsel. Based upon the evidence admitted at trial, including that which was put into context by the site visit that the Court conducted with the parties, the Court renders the following Findings of Fact, Conclusions or Law, and Judgment Order that accompanies this Merits Decision.

Findings of Fact

I. General Background 1. Sheila Bedi (“Applicant”) currently operates a daycare facility that she began about fourteen years ago. She operates her current facility out of an old school building in the Town of Fairlee in an area known as the West Fairlee Village. The Town of Fairlee adjoins the Town of Thetford. 2. Applicant’s current facility has twenty-five children enrolled in her daycare program. She employs seven people not including herself, although she does work regularly at the facility. 3. Parents generally drop off their children at Ms. Bedi’s current daycare between 7:00 a.m. and 9:00 a.m.; most daycare enrollees are picked up beginning at 3:00 p.m.

3 4. Applicant also offers after-school care for enrolled children between the hours of 3:30 p.m. to 6:00 p.m. Although a specific percentage was not provided, not all enrolled children continue at Applicant’s center for after-school hours. 5. During her fourteen years of operation, Applicant has not received a single complaint about noise or other activities that bothered the neighbors at her current daycare center. 6. The Court found Ms. Bedi’s testimony credible, particularly since her current daycare center has received a “Five-Star Certification” from the State of Vermont. This certification includes a review of the quality of care at a daycare center, including evaluations of both the inside and outside portions of the facility. Five stars is the highest rating given for this type of certification.

II. Subject Property and Proposed Improvements 7. Applicant submitted an application for conditional use and site plan approvals to renovate an existing single-family residence and attached garage and establish a child daycare facility at 154 West Fairlee Road in the Town of Thetford, Vermont (“the Subject Property”). 8. While her current daycare center has been successful, Applicant concluded that she would prefer to develop a slightly larger facility, closer to area schools; she intends to operate her proposed facility in a fashion similar to her current facility. After a search for alternate sites, she concluded that the already-existing building on the Subject Property would be ideal, since it is located between two school districts along existing bus routes and is of a suitable size. 9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Sisters & Bros. Investment Group, LLP
2009 VT 58 (Supreme Court of Vermont, 2009)
In re Chaves A250 Permit Reconsider
2014 VT 5 (Supreme Court of Vermont, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Creative Spirit CU & SP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/creative-spirit-cu-sp-vtsuperct-2015.