In Re Katzenbach A250 Permit 7R1374-1 (Christian Katzenbach & Clark Katzenbach, Appellants)

2022 VT 42, 287 A.3d 36
CourtSupreme Court of Vermont
DecidedSeptember 9, 2022
Docket21-AP-189
StatusPublished
Cited by4 cases

This text of 2022 VT 42 (In Re Katzenbach A250 Permit 7R1374-1 (Christian Katzenbach & Clark Katzenbach, Appellants)) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Katzenbach A250 Permit 7R1374-1 (Christian Katzenbach & Clark Katzenbach, Appellants), 2022 VT 42, 287 A.3d 36 (Vt. 2022).

Opinion

NOTICE: This opinion is subject to motions for reargument under V.R.A.P. 40 as well as formal revision before publication in the Vermont Reports. Readers are requested to notify the Reporter of Decisions by email at: JUD.Reporter@vermont.gov or by mail at: Vermont Supreme Court, 109 State Street, Montpelier, Vermont 05609-0801, of any errors in order that corrections may be made before this opinion goes to press.

2022 VT 42

No. 21-AP-189

In re Katzenbach A250 Permit #7R1374-1 Supreme Court (Christian Katzenbach & Clark Katzenbach, Appellants) On Appeal from Superior Court, Environmental Division

February Term, 2022

Thomas G. Walsh, J.

David L. Grayck, Montpelier, for Appellants.

James W. Barlow of James W. Barlow PLC, Danville, for Interested Party Town of Albany.

Thomas J. Donovan, Jr., Attorney General, and Melanie Kehne, Assistant Attorney General, Montpelier, for Appellee Vermont Natural Resources Board.

Rebecca Beidler and Jeffrey Ellis, Albany, Appellees.

PRESENT: Reiber, C.J., Eaton, Carroll and Cohen, JJ., and Johnson, J. (Ret.), Specially Assigned

¶ 1. EATON, J. Applicants Christian and Clark Katzenbach appeal the Environmental

Division’s decision granting but imposing certain conditions on an Act 250 permit for operating

their sand- and gravel-extraction project. Applicants challenge the court’s findings and

conclusions under Criterion 5 and Criterion 8 of Act 250. We conclude that the trial court’s

findings under both criteria are not clearly erroneous, and that its conclusions under Criterion 8

are supported by its findings. However, we conclude that one condition imposed under Criterion

5 is unreasonable in light of the trial court’s findings. We therefore strike that one Criterion 5

condition and affirm in all other respects. ¶ 2. Applicants own a three-acre commercial sand and gravel pit located in Albany,

Vermont. The surrounding area is primarily wooded with some open spaces and characterized by

low-density residential and agricultural uses. Other gravel pits and similar operations exist in the

area, including a pit about two miles away owned by the Town of Albany. Applicants’ project

involves extracting, loading, and transporting sand and gravel. Equipment used in the project

includes a loader, screen, excavator, and two dump trucks.

¶ 3. The project site is accessible from Vermont Route 14 by turning onto West Griggs

Road, a Class IV hard-packed dirt road minimally maintained by the Town. The distance from

Route 14’s intersection with West Griggs Road to the project site entrance is about 1300 feet.

Route 14 is a busy thoroughfare with steady traffic including heavy trucks. Existing traffic on

West Griggs Road is minimal and consists mainly of residential traffic from a cluster of homes

situated at the end of the road near the intersection with Route 14. One such home belongs to

neighbors Rebecca Beidler and Jeffrey Ellis, who reside on property adjacent to the project.

¶ 4. Applicants submitted an Act 250 permit application for their sand- and gravel-pit

project on February 21, 2017. The District Commission issued applicants a permit on August 29,

2017, and the project has been in continuous operation since. The project has an operating life of

twenty years with a maximum extraction rate of 30,000 cubic yards (CY) per year and a total

maximum extraction of 121,000 CY. The 2017 permit approved a maximum project truck traffic

of twenty round trips per day. It also restricted hours of operation to between 6:30 a.m. and 6:00

p.m. during the week and 7:00 a.m. and 1:00 p.m. on Saturdays with no operation on Sundays or

national holidays.

¶ 5. Neighbors appealed applicants’ project permit to the Environmental Division in

September 2017, alleging that the project was not in compliance with multiple Act 250 criteria.

After a trial and site visit in December 2018, the Environmental Division held that applicants failed

to meet their burden of proving that their project complied with Act 250. See 10 V.S.A. § 6088(a)

2 (requiring applicants to bear burden to establish compliance with Act 250 criteria). Applicants’

permit was denied, though the court noted in its decision that applicants could apply for

reconsideration within six months.

¶ 6. Instead, applicants reapplied for a permit in February 2019, supplementing their

application with evidence of compliance with the relevant Act 250 criteria. After a hearing and

site visit in May 2019, the District Commission issued applicants’ current project permit on June

13, 2019. The 2017 permit conditions described above carried through to the 2019 permit.

Neighbors again appealed to the Environmental Division. The Natural Resources Board also

participated in the appeal pursuant to 10 V.S.A. § 8504(n)(3).

¶ 7. After trial in January 2021, the Environmental Division issued its decision on

neighbors’ appeal. Of note for the appeal to this Court, it concluded that additional permit

conditions were required to ensure the project’s compliance with Act 250’s Criterion 5, which

addresses traffic impacts, and Criterion 8, which addresses aesthetic impacts including noise. To

mitigate traffic impacts on pedestrians under Criterion 5, the trial court prohibited haul trucks from

travelling on West Griggs Road between 12:00 p.m. and 1:00 p.m. on any day to allow safe

recreational opportunities during business hours. “As additional mitigation of project impacts”

and to ensure compliance with Criterion 8, the trial court limited haul-truck hours to 10:00 a.m. to

12:00 p.m. and 1:00 p.m. to 3:00 p.m. on weekdays and 10:00 a.m. to 12:00 p.m. on Saturdays

with no operation on Sundays and national holidays.

¶ 8. Applicants subsequently filed a motion to amend the Environmental Division’s

decision, seeking to extend the project’s haul-truck operation hours beyond those ordered by the

court. They argued that the court failed to consider a relevant case recently issued by this Court,

In re JSCL, LLC CU Permit, 2021 VT 22, __ Vt. __, 253 A.3d 429, and that restricting haul-truck

travel to four hours per day during the week and two hours on weekends was unreasonable. The

3 court denied the motion. It concluded that JSCL was not applicable and that even if it was, the

condition imposed was reasonable under the standard set forth in that case.

¶ 9. Applicants now appeal the Environmental Division’s decision adding permit

conditions to bring the project into compliance with Act 250 and its subsequent denial of

applicants’ motion to amend, raising two issues. First, applicants challenge the Environmental

Division’s decision regarding Criterion 8, arguing that the trial court failed to make adequate

findings to support its conclusion that the project’s noise impact would be adverse and that it

analyzed noise impacts using private-nuisance analysis as opposed to the appropriate analysis

under Criterion 8. Second, they propose that the trial court’s findings on the project’s traffic

impacts under Criterion 5 were internally inconsistent and otherwise fail to support its decision to

limit haul-truck hours. Applicants ask this Court to reverse the trial court’s decision, void the

added restrictions limiting the project’s haul-truck hours, and remand for further impact analysis

consistent with Act 250.

¶ 10. To obtain an Act 250 permit, an applicant must satisfy ten criteria. 10 V.S.A.

§ 6086(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2022 VT 42, 287 A.3d 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-katzenbach-a250-permit-7r1374-1-christian-katzenbach-clark-vt-2022.