In re Treetop Development Company Act 250 Development (Treetop at Stratton Condominium Assn., Inc., Appellant)

2016 VT 20, 143 A.3d 1086, 201 Vt. 532, 2016 Vt. LEXIS 20, 2016 WL 556155
CourtSupreme Court of Vermont
DecidedFebruary 12, 2016
Docket2015-168
StatusPublished
Cited by15 cases

This text of 2016 VT 20 (In re Treetop Development Company Act 250 Development (Treetop at Stratton Condominium Assn., Inc., Appellant)) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re Treetop Development Company Act 250 Development (Treetop at Stratton Condominium Assn., Inc., Appellant), 2016 VT 20, 143 A.3d 1086, 201 Vt. 532, 2016 Vt. LEXIS 20, 2016 WL 556155 (Vt. 2016).

Opinion

*534 Eaton, J.

¶ 1. This appeal is the latest chapter in an ongoing dispute between the Treetop at Stratton Condominium Association, Inc. (Association) and the Stratton Corporation, Treetop Development Company, LLC, Treetop Three Development Company, LLC, and Intrawest Stratton Development Corporation (collectively, Stratton) over an improperly constructed stormwater management system. The pending matter follows the Association’s appeal of the District 2 Environmental Commission’s (Commission) refusal to impose additional conditions on Stratton’s Act 250 permit, which the Environmental Division of the Superior Court determined to be invalid and unenforceable. For the reasons stated herein, we affirm.

¶ 2. On November 18, 2002, the District 2 Environmental Commission issued Act 250 Permit #2W1142 to Stratton for the construction of twenty-five three-unit townhouses (the Treetop Project) in the Town of Stratton, Vermont. Included in the Act 250 permit was approval for the development and construction of the infrastructure required for the occupancy, use, and management of the Treetop Project and associated infrastructure, including a stormwater management system.

¶ 3. A Stratton Corporation affiliate, the Treetop Development Company, LLC, completed construction of the Treetop Project in 2006, at which point all seventy-five townhouses were sold and conveyed to third-party owners. Each individual owner acquired an undivided percentage interest in the Treetop Project’s common areas and facilities, including the stormwater management systems, which were managed and administered by the Association.

¶ 4. In response to problems with the stormwater management system, the Association filed suit against Stratton in 2009 seeking damages and remediation for various construction defects in the Treetop Project, including those involving the stormwater management system. The parties ultimately reached a settlement agreement, which, relevant to this appeal, required Stratton to apply for and obtain corrective permit amendments and pay for any work necessary to bring the stormwater management aspects of the Treetop Project into compliance with its Act 250 permit. On August 13, 2012, Stratton filed an application with the Commission to amend its Act 250 permit to reflect deviations from the original permit, specifically “to authorize changes in the original as-built plans to the permit plans submitted.” These changes included repairs and modifications to the stormwater management system *535 necessary to fix leaks and seepage and to bring the system into compliance with the terms of General Permit 3-9010. 1

¶ 5. In its Findings of Fact and Conclusions of Law, the Commission expressed its concern over Stratton’s “failure to build its stormwater system in compliance with its prior permits.” The Commission conceded that “[w]hile Stratton’s plan is not the only way to [correct significant stormwater problems], it is the plan on the tablet,] . . . [and it] has been approved by the Agency of Natural Resources and is implementable immediately.” Emphasizing the importance that “the water quality and safety issues be resolved satisfactorily as soon as possible,” the Commission concluded that “issuing a permit with conditions is the most effective way to achieve this outcome.” The Commission provided that it would add “protections in the permit to ensure that solutions proposed by Stratton are effective in addressing the problems,” and that it would “retain jurisdiction over these matters.” In its conclusion, the Commission found that the Treetop Project would be in compliance with Act 250 criteria if it was “completed and maintained as represented in the application and other representations of the Applicants, and in accordance with the findings and conclusions of this decision and the conditions [herein].”

¶ 6. Following a decision by the Commission on October 21, 2013 to approve Act 250 Permit #2W1142-D (amended permit) with conditions, both Stratton and the Association moved to alter and amend the amended permit. After making minor changes, the Commission issued a Memorandum of Decision on November 15, 2013, granting the amended permit. The amended permit included several conditions, including conditions that required Stratton to repair the stormwater retention pond pursuant to approved plans on or before September 1, 2014, and to provide weekly reports on the progress of the repairs until completion. By that time of year, however, the weather made further site work impossible. Relevant to this appeal, permit Condition 14 provided:

*536 The Commission reserves the right to review erosion, the ability of the land to hold water, stormwater management and revegetation issues outlined in these proceedings and to evaluate and impose additional conditions as needed.

(Emphasis added.) Importantly, neither party appealed the amended permit, which became final and binding on December 15, 2013.

¶ 7. In January 2014, the Association provided the Commission with information about the status of the stormwater management system, including a letter from Stratton’s engineer, plans for remediation dated December 18, 2018, and the Association’s response to those filings. Shortly thereafter, on February 7, 2014, the Commission issued a Notice of Reconvened Hearing on the amended permit. The notice was issued pursuant to the authority the Commission reserved unto itself under Condition 14 and indicated the Commission’s intent to discuss whether additional conditions were necessary to address problems with the stormwater management system. Following hearings, the Commission issued a Memorandum of Decision on May 16, 2014 “declin[ing] to impose additional permit conditions with respect to [the amended permit],” and affirming the “adequacy of the conditions of the permit, which was not appealed.” The Commission also noted that, “given there is an active enforcement action [underway] by both [the Agency of Natural Resources] and the [Natural Resources Board], we are assured that there will be oversight regarding compliance with the relevant state requirements, including conditions of [the amended permit], which were not appealed.” 2

¶ 8. The Association timely appealed the Commission’s May 16, 2014 Memorandum of Decision declining to impose further conditions on Stratton to the Environmental Division of the Superior Court. Stratton then moved to dismiss the appeal, alleging that the questions raised on appeal were either collateral attacks on the unappealed amended permit or outside the scope of the *537 Environmental Division’s de novo review. On November 14, 2014 the Environmental Division dismissed the appeal, finding, relevant to the matter now before this Court, that:

The sole purpose of Condition 14 is to ensure compliance with the initial Permit and Permit Amendment. This authority does not belong to the Commission. Rather, it rests with the Natural Resources Board’s authority to ensure compliance with an Act 250 Permit and its conditions through its enforcement powers. . . . the Association cannot use Condition 14 to privately enforce the Permit or Permit Amendment.

Treetop Dev. Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re ACTD LLC, d/b/a The Green Mountain Surgery Center
2020 VT 89 (Supreme Court of Vermont, 2020)
Bourdeau Bros., Inc. v. Boissonneault Family Farm, Inc.
2020 VT 35 (Supreme Court of Vermont, 2020)
In re Mathez Act 250 LU Permit (Sung-Hee Chung, Appellant)
2018 VT 55 (Supreme Court of Vermont, 2018)
In re Hinesburg Hannaford Act 250 Permit
179 A.3d 727 (Supreme Court of Vermont, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2016 VT 20, 143 A.3d 1086, 201 Vt. 532, 2016 Vt. LEXIS 20, 2016 WL 556155, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-treetop-development-company-act-250-development-treetop-at-stratton-vt-2016.