In re SP Land Co., LLC, Act 250 LUP Amendment

2011 VT 104, 35 A.3d 1007, 190 Vt. 418, 2011 Vt. LEXIS 111
CourtSupreme Court of Vermont
DecidedSeptember 22, 2011
Docket2010-332
StatusPublished
Cited by37 cases

This text of 2011 VT 104 (In re SP Land Co., LLC, Act 250 LUP Amendment) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In re SP Land Co., LLC, Act 250 LUP Amendment, 2011 VT 104, 35 A.3d 1007, 190 Vt. 418, 2011 Vt. LEXIS 111 (Vt. 2011).

Opinions

Johnson, J.

¶ 1. This appeal arises out of a dispute over an administrative amendment to the master development plan for Killington Resort Village granted to its co-applicants, the current owners of Killington Resort "Village and SP Land Company. The District One Environmental Commission originally granted this administrative amendment — authorizing the creation of fifteen subdivided lots over approximately 368 acres of Killington Resort Village for transfer to SP Land Company for “future development purposes” — pursuant to Act 250 Rule 34(D). Mountainside Properties, LLC, an adjoining property owner, appeals the Environmental Court’s denial of its motion to alter and amend a grant of summary judgment in favor of co-applicants. Mountainside argues that the Environmental Court erred because: (1) administrative amendments under Rule 34(D) require an underlying Act 250 land use permit, and (2) co-applicants’ fifteen-lot subdivision cannot be approved without demonstrating compliance with all Act 250 criteria under 10 V.S.A. § 6086(a), as required by 10 V.S.A. § 6081(a). We agree and therefore reverse.

¶2. The relevant procedural history is as follows. In 1998, the former owners of Killington Resort Village applied to the District One Environmental Commission (District Commission) for master plan review of the .Killington Resort Village Master Development Plan (“Killington master plan”) pursuant to then-existing Environmental Board Rules 10(c) and 21 and Master Permit Policy and Procedure for Partial Findings of Fact (master permit policy). The master permit policy allowed for review of specific Act 250 criteria [422]*422under § 6086(a) for complex development projects to streamline the review process and reduce costs to applicants.

¶ 3. In 1999, the District Commission issued partial findings of fact and conclusions of law regarding the Killington master plan. It made affirmative findings for five criteria and subcriteria under § 6086(a) and issued a “weather report” for each of the remaining criteria and subcriteria. No Act 250 land use master permit was issued. Pursuant to the master permit policy, the purpose of these partial findings was to assist the applicant and parties by providing notice of factual deficiencies in the application that resulted in a failure to achieve affirmative findings. The five affirmative findings were binding on all parties to the application for a period of five years.

¶ 4. The Vermont Natural Resources Council, a party to the master plan review proceedings, and the former owners of Kllington Resort Village appealed some of the partial findings of fact and conclusions of law made by the District Commission to the Environmental Board. The Board determined that it had appellate jurisdiction to review only those criteria and subcriteria for which the District Commission had made affirmative findings, and therefore entered an order regarding a limited number of the § 6086(a) subcriteria. The Board’s decision and order did not include an Act 250 land use permit.

¶ 5. The partial findings of fact and conclusions of law for the Kllington master plan subsequently received two amendments prior to the administrative amendment at issue here. The first, an administrative amendment issued in March 2004 pursuant to Rule 34(D), authorized the subdivision of approximately 470 acres of Killington Resort Village into nine lots. The second, issued in August 2004, renewed the District Commission’s 1999 partial findings of fact and conclusions of law for another five-year period. Neither amendment included an Act 250 land use permit.

¶ 6. At the end of 2007, co-applicants (successors in title to the original permittee) discussed with the District Commission’s district coordinator options for obtaining a third amendment to the Kllington master plan for another proposed subdivision. The district coordinator recommended applying for an administrative amendment pursuant to Rule 34(D), which allows a district coordinator “to amend a permit . . . when . . . necessary for record-keeping purposes or to provide authorization for minor revisions to permitted projects raising no likelihood of impacts [423]*423under the criteria of [§ 6086(a)].” 6 Code of Vt. Rules 12 004 060-15, available at http://www.michie.com/vermont. The district coordinator suggested Rule 34(D) because at that time over fifty different Act 250 permit series covered Killington Resort Village, the 1999 master plan review decision pertained to the entirety of Killington Resort Village, and no construction element was included in the proposed amendment.

¶ 7. Thus, in April 2008, co-applicants applied under Rule 34(D) for a third administrative amendment, despite not having an Act 250 land use permit. Co-applicants sought permission to realign the nine subdivided lots approved in the first administrative amendment into fifteen subdivided lots for transfer to SP Land for “future development purposes.” The application listed Mountainside as an adjoining property owner. The district coordinator, with approval of the District Commission, granted the administrative amendment in May 2008 pursuant to Rule 34(D). The amendment stated that no development of the parcels was approved by the amendment and referred to itself as a “permit.”

¶ 8. Mountainside then filed a motion with the District Commission to alter the third administrative amendment under Act 250 Rule 31(A).1 Mountainside’s motion questioned, among other things, the propriety of using Rule 34(D) to authorize the subdivision of 368 acres, arguing that the proposed subdivision likely involved more than minor record-keeping or minor revisions to an existing project. The District Commission denied Mountainside’s motion to alter in October 2008.

¶ 9. Mountainside filed an appeal with the Environmental Court in November 2008. It submitted a list of fifteen questions for the court to address on appeal, the majority of which related to the fifteen-lot subdivision. The parties filed cross-motions for summary judgment. The Environmental Court granted summary judgment in favor of co-applicants on all fifteen questions, concluding that, [424]*424under Rule 34(D), the fifteen-lot subdivision authorized by the third administrative amendment would cause no impact to any Act 250 criteria.

¶ 10. Mountainside subsequently filed a motion to alter and amend the Environmental Court’s grant of summary judgment pursuant to Vermont Rule of Civil Procedure 59(e). It presented arguments similar to those presented here: absent an underlying Act 250 land use permit, no administrative amendment can issue under Rule 34(D), and co-applicants’ fifteen-lot subdivision cannot be authorized without full review of all the criteria and subcriteria of § 6086(a).

¶ 11. The Environmental Court sought guidance from the Natural Resources Board Land Use Panel as to whether the absence of an Act 250 land use permit precludes issuing a Rule 34(D) administrative amendment to a master plan. The Land Use Panel’s written response concluded that without an underlying permit there could be no administrative amendment under Rule 34(D) because there was nothing to amend under the process set out in that rule. The memorandum explained that the District Commission could issue Revised Master Plan Findings and Conclusions but these would not be issued under Rule 34, as Rule 34 addresses only permit amendments.

¶ 12. The Environmental Court nonetheless denied Mountainside’s motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heritage Family v. Brown
Vermont Superior Court, 2026
McPartland ZA Appeal - Decision on Motion
Vermont Superior Court, 2025
Capitol Plaza Act 250 - Decision on Motion
Vermont Superior Court, 2020
Citimortgage, Inc. v. Siebold
Vermont Superior Court, 2019
Scott Farm Act 250 - Decision on Motions
Vermont Superior Court, 2018

Cite This Page — Counsel Stack

Bluebook (online)
2011 VT 104, 35 A.3d 1007, 190 Vt. 418, 2011 Vt. LEXIS 111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-sp-land-co-llc-act-250-lup-amendment-vt-2011.