In Re Killington, Ltd.

616 A.2d 241, 159 Vt. 206, 1992 Vt. LEXIS 123
CourtSupreme Court of Vermont
DecidedSeptember 11, 1992
Docket90-535
StatusPublished
Cited by31 cases

This text of 616 A.2d 241 (In Re Killington, Ltd.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Killington, Ltd., 616 A.2d 241, 159 Vt. 206, 1992 Vt. LEXIS 123 (Vt. 1992).

Opinion

*208 Dooley, J.

The Vermont Environmental Board denied an Act 250 permit to Killington, Ltd., for construction of a pond intended to enhance Killington’s snowmaking capacity at its ski area. Killington appeals that ruling, which was based on the Board’s conclusion that the proposed construction would not satisfy 10 V.S.A. § 6086(a)(8)(A) because it would imperil a habitat necessary to the survival of a population of black bears. We affirm.

Application for the permit was filed on February 18, 1986, with District Environmental Commission No. 1. The application sought approval to divert the waters of Madden Brook to build a snowmaking pond in an area known as Parker’s Gore East in the Town of Mendon. After extensive hearings and procedural maneuvering, the District Commission denied the application on July 14, 1987. The Commission found that construction of the pond would threaten a population of black bears by making inaccessible a stand of beech trees used by the bears for food. The Commission also found that the construction would prevent the bears from using a tract of spruce and fir to travel into Parker’s Gore East, where they build up body fat in the fall in preparation for winter hibernation.

Pursuant to 10 V.S.A. § 6089(a), Killington appealed the Commission’s denial to the Environmental Board on August 13, 1987. The appeal challenged the Commission’s decisions to grant party status to certain organizations and municipalities and to impose conditions on any permit that might be issued. Its fundamental challenge, however, was to the conclusion, under 10 V.S.A. § 6086(a)(8)(A) (hereinafter criterion 8(A)), that the project would significantly impair necessary wildlife habitat, would not utilize all feasible and reasonable means of lessening the alleged impairment, and would be a detriment to the general welfare of the public. Killington asserted that the Commission’s findings did not support its conclusions and that the conclusions were based on a fundamental misconstruction of the term “necessary wildlife habitat” as used in the statute.

Pursuant to Environmental Board Rule 14(A), and over Killington’s objection, the Board granted party status to Two Rivers-Ottauquechee Regional Planning Commission and the towns and planning commissions of Shrewsbury and Bridge-water because they adjoined land “contiguous to the site of the *209 proposed project that is owned or controlled by Killington.” During the evidentiary stage of the Board’s review, the Town of Shrewsbury sought to present evidence that, in addition to the harm likely to be done to the bears’ use of the beech, spruce and fir trees, the proposed pond construction would also destroy wetlands in Parker’s Gore East critical to the animals’ survival. The subject of the wetlands had not been raised by any party before the Commission and was not addressed in the Commission’s findings, conclusions or order. Over Killington’s objection, the Board allowed the evidence to be presented because it was probative of “the existence of necessary bear habitat in Parker’s Gore East” and the likely effect of pond construction and operation on that habitat, the issues raised by Killington’s appeal.

On May 11, 1989, the Board ruled that the term “necessary wildlife habitat” in criterion 8(A) covered habitat critical to the survival of the particular wildlife population dependent on it, and that Parker’s Gore East constituted necessary wildlife habitat. It also concluded that construction and operation of the pond would destroy or significantly impair that habitat in a number of respects. On September 21, 1990, the Board issued its final findings. It concluded that Killington met none of the subcriteria of criterion 8(A), 1 which, if satisfied, allow the issuance of a permit regardless of the imperilment of necessary wildlife habitat. Therefore, the Board also denied the permit.

On appeal, Killington contends that (1) the Board erred in granting party status to the municipalities and planning com *210 missions; (2) the Board erred in considering the issue of wetlands in Parker’s Gore East; (3) the Board erred in defining “necessary wildlife habitat” for the purpose of criterion 8(A) to mean habitat critical to the survival of a particular population of wildlife, rather than to that of an entire species in Vermont; and (4) the Board’s findings did not support its conclusions that necessary black bear habitat existed in Parker’s Gore East and that such habitat would be destroyed or imperiled by the proposed project.

It is important at the outset to emphasize the deference with which we treat decisions by the Environmental Board as to matters properly within its jurisdiction. See In re Denio, 158 Vt. 230, 239, 608 A.2d 1166, 1171 (1992) (Board’s decisions presumed to be “‘correct, valid and reasonable . . . and we will normally defer to its determinations’ ”) (quoting Vermont State Colleges Faculty Federation v. Vermont State Colleges, 151 Vt. 457, 460, 561 A.2d 417, 419-20 (1989)). The Board, of course, is required to follow both the standards established by the Legislature and the procedures which it has itself adopted in order to carry out its statutory mandate. However, “ ‘absent compelling indication of error,’ we will sustain the interpretation of a statute by the administrative body responsible for its execution.” In re Duncan, 155 Vt. 402, 408, 584 A.2d 1140, 1144 (1990). The same is true for an agency’s interpretation of its own rules. See Rogers v. Watson, 156 Vt. 483, 489, 594 A.2d 409, 412 (1991). As to findings of fact, we must affirm the Board if its findings are based on substantial evidence. 10 V.S.A. § 6089(c); see Denio, 158 Vt. at 238, 608 A.2d at 1170-71. Conclusions, in turn, are affirmed when “rationally derived from [the] findings and based on a correct interpretation of the law.” In re Southview Associates, 153 Vt. 171, 178, 569 A.2d 501, 504 (1989).

Killington first argues that the Board erred in admitting parties to the permit-approval proceeding that were not entitled to be included. At the outset, we must narrow this claim to the Town of Shrewsbury and the Shrewsbury Planning Commission (hereinafter Shrewsbury). The parties to which Killington objects, other than Shrewsbury, did not present evidence, cross-examine Killington’s witnesses, or otherwise participate in the hearings. In order to obtain relief on appeal, *211 Killington must show that an asserted error prejudiced its rights. See Cadel v. Sherburne Corp., 139 Vt. 134, 136, 425 A.2d 546, 547 (1980) (on appeal, burden is on appealing party to show that error resulted in prejudice). It has not done so with respect to these parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Killington Village Master Plan Act 250
Vermont Superior Court, 2014
Barefoot & Zweig Act 250
Vermont Superior Court, 2013
Union Bank Act 250
Vermont Superior Court, 2012
Lathrop Limited Parternship I
Vermont Superior Court, 2011
Losier Variance Application
Vermont Superior Court, 2010
Pion Sand & Gravel Pit
Vermont Superior Court, 2010
Champlain Marina Dock Expansion
Vermont Superior Court, 2010
Saladino CU Application
Vermont Superior Court, 2010
Big Spruce Road Act 250 Subdivision
Vermont Superior Court, 2010
JLD Property St. Albans Wal Mart
Vermont Superior Court, 2010
In Re Green Crow Corp.
2007 VT 137 (Supreme Court of Vermont, 2007)
In re Appeal of Clyde River Hydroelectric Project
2006 VT 11 (Supreme Court of Vermont, 2006)
Butson v. Department of Employment & Training
2006 VT 10 (Supreme Court of Vermont, 2006)
In Re Woodford Packers, Inc.
2003 VT 60 (Supreme Court of Vermont, 2003)
In Re Commercial Airfield
752 A.2d 13 (Supreme Court of Vermont, 2000)
In Re Wal Mart Stores, Inc.
702 A.2d 397 (Supreme Court of Vermont, 1997)
In Re MBL Associates
693 A.2d 698 (Supreme Court of Vermont, 1997)
Killington, Ltd. v. State
668 A.2d 1278 (Supreme Court of Vermont, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
616 A.2d 241, 159 Vt. 206, 1992 Vt. LEXIS 123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-killington-ltd-vt-1992.