In Re Taft Corners Associates, Inc.

632 A.2d 649, 160 Vt. 583, 1993 Vt. LEXIS 89
CourtSupreme Court of Vermont
DecidedApril 30, 1993
Docket92-215
StatusPublished
Cited by44 cases

This text of 632 A.2d 649 (In Re Taft Corners Associates, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
In Re Taft Corners Associates, Inc., 632 A.2d 649, 160 Vt. 583, 1993 Vt. LEXIS 89 (Vt. 1993).

Opinion

Gibson, J.

Appellant Taft Corners Associates, Inc. (TCA) appeals from a decision of the Environmental Board, claiming that the Board exceeded the scope of its authority by deciding issues that were not raised before the district commission. We hold that the Board had no jurisdiction to decide issues that were not before the commission and reverse.

In October 1986, TCA filed an application for a permit to develop a 223-acre commercial and industrial park at Taft Corners in Williston. On July 31, 1987, the district commission issued findings of fact and conclusions of law under Act 250, 10 V.S.A. §§ 6001-6092, and granted a permit (1987 permit) authorizing Phase I of the development. The 1987 permit allowed TCA to construct 4,400 feet of roads and utilities and to subdivide 10 to 14 lots of a planned 37-lot commercial and industrial subdivision. The commission approved Phase I provided that TCA complied with thirty-six conditions contained in the per *586 mit. Condition 5 allowed a maximum of 999 parking spaces and 145 peak-hour vehicle trips. Condition 6 provided:

Prior to the commencement of construction on any lot within this subdivision the Permittee, Taft Corners Associates, and any purchaser or tenant of any lot shall file an amendment application under criteria l(Air), 1(E), 1(B), 4, 7(fire services), 8 and 9(F). This amendment application shall be accompanied by evidence of conformance to the Findings under criteria 1(B), 2 and 3, 5 and 9(J) and shall file a cumulative impact statement.

Thus, the 1987 permit, known as an “umbrella permit” because it established conditions for the development as a whole, required TCA to obtain commission approval prior to construction on any lot in order to ensure that the conditions of the permit were fulfilled.

In January 1988, TCA filed a second application, requesting reconsideration of some conditions of the 1987 permit and approval for Phase II of the park. On April 27, 1988, the commission issued an amended umbrella permit (1988 permit) approving subdivision of the remaining lots and incorporating all conditions previously established, including the 1987 permit condition 6 that TCA obtain commission approval before construction on any lot. The 1988 permit amended condition 5, allowing 4,900 parking spaces (if there were no objections to the air quality permit, when filed) and 2,825 peak-hour vehicle trips.

In May 1991, TCA filed an amendment application seeking approval to construct a 114,513-square-foot Wal-Mart retail store and a 132,500-square-foot Sam’s Discount Price Club for warehouse sales. Williston Citizens for Responsible Growth (WCRG) petitioned for party status on criteria 5 (traffic), 8 (aesthetics), and 10 (conformance with local and regional plans). The petition was accompanied by a motion to apply criterion 10, alleging that TCA’s application constituted a significant change to the character of the development approved by the umbrella permit and did not comply with the revised town plan adopted after the permit was issued.

The district commission granted WCRG party status on criterion 8 (aesthetics), one of the criteria left open for consideration under amendment applications. The commission *587 determined, however, that WCRG would not materially assist the commission in determining whether the application was in conformance with criterion 5. Further, it concluded that the application proposed no “material change” in the project; thus, there were no grounds to reconsider criterion 10 beyond compliance with the umbrella permit. Accordingly, it denied WCRG’s request for party status on criteria 5 and 10.

On November 15, 1991, the district commission issued findings of fact and conclusions of law on the amendment application under all criteria set forth in condition 6 of the 1987 permit, and granted a permit (1991 permit) to construct Wal-Mart/ Sam’s subject to thirty-four conditions. WCRG appealed the decision to the Environmental Board and requested a de novo hearing on all ten Act 250 criteria. The City of Burlington moved for party status on several criteria.

Prior to an evidentiary hearing, the Board requested briefs on preliminary issues related to the scope of review. On March 31, 1992, the Board ruled that its Umbrella Permit Policy required specific identification of the type and character of activities proposed “so that the potential impacts can be meaningfully reviewed,” and that final approval under the Umbrella Permit Policy may be granted only on those aspects of a proposed project for which the impacts may be evaluated, such as natural resources at the site. Thus, the Board concluded that potential offsite impacts and impacts from individual uses cannot be addressed until the specific use of each tenant is identified. It determined that TCAs umbrella permit applications had not provided the specificity required by simply identifying a proposed project as “retail” or “major retail.”

The Board also ruled that the district commission had not properly reviewed the earlier applications under several criteria and that each of those criteria must be reconsidered. The Board disagreed with TCA’s argument that only those criteria listed in condition 6 of the 1987 permit were still open for review, maintaining that it had authority to “reopen[] parts of an umbrella permit in certain circumstances.” Further, the Board ruled that the amendment application constituted a substantial change to the development approved in the umbrella permit “because many of the potential impacts from this project were never considered.” Consequently, the Board remanded the *588 amendment application to the district commission to review under the criteria it had identified as inadequately reviewed during the umbrella permit application process.

TCA appeals from this decision, claiming that the Board exceeded its authority by addressing issues that were not raised before the district commission. It also argues that the Board (1) violated the doctrine of res judicata by overturning the umbrella permit, (2) offended due process by failing to provide notice that the permit was in jeopardy, and (3) disregarded rulemaking requirements by announcing that umbrella permits may not grant final approval on several criteria. Appellee Agency of Natural Resources (ANR) maintains that the Board’s authority is not limited to issues raised before the district commission and that the other issues TCA raises are not properly before this Court because they were not brought before the Board. Further, it argues that the Board’s determination that the amendment application proposed a substantial change to the umbrella permit was supported by substantial evidence, and that remanding to the district commission for review of the additional criteria was proper. Amici on both sides raise additional issues.

I.

We first address this Court’s authority to consider this appeal prior to an administrative decision on the merits. WCRG and the City of Burlington argue that the Court has no jurisdiction to consider the appeal because the order from which TCA appeals is not a final order. We agree that TCA has not exhausted all administrative remedies as the Board’s order remanded the case to the district commission for consideration of various criteria. See In re Pelham North, Inc., 154 Vt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Mathez Act 250 LU Permit (Sung-Hee Chung, Appellant)
2018 VT 55 (Supreme Court of Vermont, 2018)
In re Hinesburg Hannaford Act 250 Permit
179 A.3d 727 (Supreme Court of Vermont, 2017)
Northern Vermont Rentals, LLC Extension
Vermont Superior Court, 2017
Scott Farm Act 250
Vermont Superior Court, 2017
Mathez Act 250 LU Permit
Vermont Superior Court, 2017
Champlain Parkway Wetland CU Det
Vermont Superior Court, 2017

Cite This Page — Counsel Stack

Bluebook (online)
632 A.2d 649, 160 Vt. 583, 1993 Vt. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/in-re-taft-corners-associates-inc-vt-1993.