N.E. Materials Grp Act 250

CourtVermont Superior Court
DecidedMarch 11, 2016
Docket35-3-13 Vtec
StatusPublished

This text of N.E. Materials Grp Act 250 (N.E. Materials Grp Act 250) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
N.E. Materials Grp Act 250, (Vt. Ct. App. 2016).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Environmental Division Unit Docket No. 35-3-13 Vtec

N.E. Materials Group Amended A250 Permit DECISION ON THE MERITS

Twenty-six citizens, collectively known as “Neighbors for Healthy Communities” (Appellants), appeal a District 5 Environmental Commission (District Commission) decision approving the application of North East Materials Group, LLC (NEMG) and Rock of Ages Corporation (ROA) (collectively, Applicants) for a hot-mix asphalt plant at the ROA quarry in the Town of Barre, Vermont. NEMG and ROA cross-appeal.1 On May 4, 5, and 6, 2015, the Court held a three-day merits hearing at the Vermont Superior Court, Civil Division, Washington Unit in Montpelier, Vermont. During the final pre- trial conference in this matter all parties agreed that the Court need not conduct a site visit, as the Court had already performed a site visit in the related matter noted in footnote 1 below. Appearing at the merits hearing were Alan P. Biederman, Esq. and James P.W. Goss, Esq. representing the Applicants; Douglas A. Ruley, Esq.2 and Laura B. Murphy, Esq. representing the Appellants; Gregory J. Boulbol, Esq. representing the Natural Resources Board; and Elizabeth Lord, Esq. and Megan O’Toole, Esq. representing the Agency of Natural Resources (ANR). At the start of trial all parties provided a stipulation limiting the issues for trial to the following: 1 Appellants and NEMG are also parties to separate but related litigation over whether NEMG’s rock crushing operations on ROA’s quarry tract are subject to Act 250 jurisdiction. See In re N.E. Materials Grp. LLC A250 JO #5-21, No. 143-10-12 Vtec. In April 2014, this Court held that NEMG’s rock crusher was part of ROA’s grandfathered preexisting development, and not subject to Act 250 jurisdiction. In re N.E. Materials Grp. LLC A250 JO #5-21, No. 143-10-12 Vtec, slip op. at 14–15 (Vt. Super. Ct. Envtl. Div. Apr. 28, 2014) (Walsh, J.). Appellants appealed that decision, and the Vermont Supreme Court reversed and remanded for further findings. In re N.E. Materials Grp. LLC Act 250 JO #5-21, 2015 VT 79, ¶ 35. On remand we again held that the rock crusher was not a substantial change to NEMG’s preexisting development, and therefore that it was not subject to Act 250 jurisdiction. In re N.E. Materials Grp. LLC A250 JO #5-21, No. 143-10-12 Vtec, slip op. at 20–21 (Vt. Super. Ct. Envtl. Div. Dec. 23, 2015) (Walsh, J.). Appellants have again appealed that determination to the Vermont Supreme Court. 2 In a December 21, 2015 Notice of Withdrawal, attorney Ruley withdrew from this matter. Attorney Murphy continues to represent Appellants.

1 a. Air pollution under Criterion 1. b. Traffic under Criteria 5 and 9(k). c. Aesthetics under Criterion 8, with the understanding that “noise” as listed in Appellants’ Amended Statement of Questions includes only noise from trucks.

The stipulation also provides:

With respect to all other criteria under Act 250 not set forth [above], and all other provisions and requirements of Act 250, the parties agree as a matter of law and as a matter of fact that the decision(s) of the District Commission below may be incorporated into this Court’s decision and final order.

Thus, all other issues presented in the parties’ Statements of Questions, including NEMG’s challenge to the rolling average production limits imposed in its permit below, are outside the scope of our review.3 Based upon the evidence presented at trial, which was put into context by the site visit conducted in the related appeal, No. 143-10-12 Vtec, the Court renders the following findings of fact and conclusions of law.

3 In granting Applicants’ land use permit, the District Commission limited NEMG’s asphalt production to an “average weekly production maximum of 4,500 tons as measured over a rolling 45 day period.” See Ex. 9 at 1 (Land Use Permit #5-W0966-6 (Altered)). Applicants challenged this rolling average production limit in their Statement of Questions, and Applicants continue to challenge this condition in their post-trial Proposed Findings of Fact and Conclusions of Law. But the parties’ stipulation, which, by its terms, applies to “issues to be considered by the Court in the above Appeal and Cross-Appeal,” did not preserve the issue of rolling average production limits. Stipulation Respecting Trial Issues, filed May 14, 2015 (emphasis added). We therefore consider this issue outside the scope of review. And, even if we were to consider this issue, we would uphold the condition. In keeping with the stipulation, Applicants introduced no evidence or argument at trial challenging the rolling average production limit. Indeed, the evidence NEMG submitted at trial to support its application includes evidence of how the Project has been operating for the last three years, while the rolling average production limit was in place, and we rely on this evidence in issuing positive findings in this decision. Specifically, in issuing positive findings under Criterion 1, we rely on the fact that ANR has not initiated enforcement proceedings during the Project’s operation; in issuing positive findings under Criterion 5 and 9(K), we rely on the fact that no accidents have occurred at the HCL section of Graniteville Road involving trucks while the Project has been operating; and, in issuing positive findings under Criterion 8, we rely on the fact that actual average and maximum truck trips per day while the Project has been operating do not cause undue noise from trucks. Because we base our positive findings in part on the Project’s actual impacts over the three years, while the rolling average production limit was in place, we would incorporate the limit even if the issue were preserved for our review.

2 Findings of Fact

I. The Project 1. NEMG and ROA seek Act 250 approval for construction and operation of a hot-mix asphalt plant and related fixtures and equipment (the Project). 2. The Project is to be located on the ROA quarry tract. 3. ROA is a quarrying operation comprised of several smaller individual quarries active from the late 1800s to current times, now all aggregated as a single parcel under ROA ownership and operation. 4. All total, ROA comprises approximately 930 acres in Barre, Vermont and 230 acres in Williamstown, Vermont. Several roads transect the ROA property, including Graniteville Road. Roads also connect work areas throughout the ROA property. 5. Graniteville Road runs northwest/southeast, and bisects the ROA tract into northern and southern portions. 6. The Project is on 3.46 acres on the south side of Graniteville Road in the Town of Barre, Vermont. The Project site is located in the interior of the ROA quarrying operation. 7. Graniteville Road connects the villages of Upper and Lower Graniteville (both part of Barre Town). Lower Graniteville is located northwest of and at a lower elevation than Upper Graniteville. 8. Lower Graniteville has a general store, senior center, playground, post office, church, school bus stop, and residences. 9. Upper Graniteville is mostly residential. 10. The zoning district for the Project location is “Industrial” pursuant to the Town of Barre Zoning Regulations. 11. The approved maximum operating capacity of the Project is 180 tons of asphalt per hour, while the maximum design operating capacity is 250 tons per hour. The land use permit approved by the District Commission included a rolling average production limit of 4,500 tons per week during any given 45-day period.4

4 The permit authorized NEMG to seek permission from the District Coordinator to exceed this rolling average limit “as appropriate . . . to address particular projects or circumstances.”

3 12. The Project will operate from May 1 through mid-November, Monday through Saturday, from 6:00 a.m. to 4:00 p.m. 13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rice v. Santa Fe Elevator Corp.
331 U.S. 218 (Supreme Court, 1947)
City of Burbank v. Lockheed Air Terminal, Inc.
411 U.S. 624 (Supreme Court, 1973)
Altria Group, Inc. v. Good
555 U.S. 70 (Supreme Court, 2008)
Dan's City Used Cars, Inc. v. Pelkey
133 S. Ct. 1769 (Supreme Court, 2013)
Keck v. Commonwealth Ex Rel. Golden
998 S.W.2d 13 (Court of Appeals of Kentucky, 1999)
In Re Eastview at Middlebury, Inc.
2009 VT 98 (Supreme Court of Vermont, 2010)
In Re Hawk Mountain Corp.
542 A.2d 261 (Supreme Court of Vermont, 1988)
In Re Pilgrim Partnership
572 A.2d 909 (Supreme Court of Vermont, 1990)
In Re Rinkers, Inc.
2011 VT 78 (Supreme Court of Vermont, 2011)
In Re Appeals of ANR Permits in Lowell Mountain Wind Project
2014 VT 50 (Supreme Court of Vermont, 2014)
In re Chaves A250 Permit Reconsider
2014 VT 5 (Supreme Court of Vermont, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
N.E. Materials Grp Act 250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ne-materials-grp-act-250-vtsuperct-2016.