I-291 Why? Association v. Burns

372 F. Supp. 223, 6 ERC 1275, 4 Envtl. L. Rep. (Envtl. Law Inst.) 20230, 6 ERC (BNA) 1275, 1974 U.S. Dist. LEXIS 12343
CourtDistrict Court, D. Connecticut
DecidedFebruary 7, 1974
DocketCiv. H-229
StatusPublished
Cited by41 cases

This text of 372 F. Supp. 223 (I-291 Why? Association v. Burns) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
I-291 Why? Association v. Burns, 372 F. Supp. 223, 6 ERC 1275, 4 Envtl. L. Rep. (Envtl. Law Inst.) 20230, 6 ERC (BNA) 1275, 1974 U.S. Dist. LEXIS 12343 (D. Conn. 1974).

Opinion

RULING ON MOTION FOR PRELIMINARY INJUNCTION

BLUMENFELD, Chief Judge.

Plaintiff is an unincorporated association of persons aggrieved by present plans for the construction of the southwest quadrant of 1-291, a multilane, controlled access, divided highway which would run for about 7.6 miles through Rocky Hill, Wethersfield, Newington, New Britain, and Farmington, Connecticut, linking 1-91 south of Hartford, Connecticut, with 1-84 west of Hartford. This quadrant was originally planned as only part of an entire circumferential beltway around metropolitan Hartford. The southwest quadrant (Rocky Hill to Farmington) of this beltway is the only portion thereof which is nearing construction, and is the only portion thereof which is directly in issue in this action. For convenience I will refer hereinafter to this southwest quadrant by its family name, “1-291.”

Plaintiff, whose standing to bring this action has not been challenged, has filed a complaint seeking injunctive and declaratory relief. Plaintiff asserts that this Court has jurisdiction over the action under 28 U.S.C. §§ 1331, 1337, 1361, 1391, 2201 and 2202. Alleged as separate causes of action are defendants’ 1 breach of four federal statutes. 2 In moving for a preliminary injunction to halt construction of 1-291, plaintiff has by agreement with defendants restricted its attack to its first cause of action: defendants’ alleged breach of the duties imposed on them by the National Environmental Policy Act of 1969 (NEPA), 42 U.S.C. § 4331 et seq. 3 Plaintiff enu *228 merates in five counts defendants’ alleged failure to comply with NEPA, four of the five counts touching directly or indirectly on the adequacy of the Environmental Impact Statement (EIS) on 1-291 prepared by defendants. The first count alleges that the air pollution and noise generated by 1-291, as indicated by defendants’ own studies made after completion of the EIS, will be so great as to violate the substantive mandate of section 101(b)(3) of NEPA, 42 U.S.C. § 4331(b)(3), directing federal agencies to act so as to “attain the widest range of beneficial uses of the environment without degradation, risk to health or safety, or other undesirable and unintended consequences.” The second count accuses defendants of failing to act in accordance with the “continuing responsibility” for environmental problems required of federal agencies-Niy section 101(b) of NEPA, insofar as they failed to incorporate air and noise pollution data obtained by them after completion and approval of the original EIS, into a supplemental EIS duly circulated among and approved by responsible public agencies. The third count alleges that the original EIS was not prepared in accordance with pertinent Federal Highway Administration (FHWA) guidelines, and count four alleges that the EIS lacked the adequacy and good faith preparation required by NEPA, and that the EIS was not prepared “by the responsible official” as directed by NEPA. The fifth count asserts that defendants violated their duty of “continuing responsibility” under NEPA by failing to file a supplemental EIS once it became apparent that the southwest quadrant of 1-291 would be the only portion of the entire Hartford metropolitan beltway to be *229 constructed in the foreseeable future. Issue was joined on these five counts at a hearing of several days’ duration on plaintiff’s motion for a preliminary injunction.

I.

BACKGROUND

The general location for an expressway such as 1-291 has been under consideration for some twenty years. 4 Public hearings on possible routes to be used were held in 1959 and 1961. 5 Public hearings on the design of the highway were held in 1969, 1970, and 1971. 6 The proposed highway was divided into two projects of roughly equal length, designated Conn. Projects Nos. 93-74 and 51-130. Design study reports on these projects were submitted to the FHWA, together with a request for design approval, in August, 1970, 7 and were resubmitted in revised form in December, 1970. 8 At this time the cost of constructing 1-291 was estimated to be $31,500,000. 9 If 1-291 is constructed as part of the federal interstate highway system, 90 per cent of the cost will be borne by the federal government, and 10 per cent by Connecticut. See 23 U.S.C. § 120(c).

It has not been disputed that FHWA supervision and funding of the planning and construction of 1-291 by the FHWA constitutes “a proposal for major federal action” within the purview of section 102(C) of NEPA, which became effective January 1, 1970. Thus on February I, 1971, the FHWA Division Engineer for Connecticut advised the Commissioner of the Connecticut Department of Transportation (CONNDOT) that an EIS would be required for I-291. 10 Personnel of CONNDOT’s Bureau of Highways accordingly prepared a rough draft of an EIS. 11 This rough draft was reviewed in February, 1971, by David Densmore, a field employee of the Connecticut division of the FHWA. 12 Defendant George Koch, then Chief of Design for the CONNDOT Bureau of Highways (until March, 1971), supervised preparation of a preliminary draft EIS based on the earlier rough draft and Densmore’s comments thereon. 13 During the preparation of the preliminary draft, Densmore and two other FHWA engineers spoke almost daily, in person or by telephone, with CONNDOT personnel concerning the draft EIS. 14 Defendant Koch testified that the resulting preliminary draft was based more on his experience and knowledge of the *230 project than on empirical data. 15 This preliminary draft was filed with the FHWA in June, 1971, 16 and circulated among other federal agencies, 17

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stuart & Sons, L.P. v. Curtis Publishing Co.
456 F. Supp. 2d 336 (D. Connecticut, 2006)
Becker v. Federal Railroad Administration
999 F. Supp. 240 (D. Connecticut, 1996)
County of Westchester v. Town of Greenwich, Conn.
793 F. Supp. 1195 (S.D. New York, 1992)
Stow v. US ON BEHALF OF SOIL CONSERVATION SERV.
696 F. Supp. 857 (W.D. New York, 1988)
Milwaukee Brewers v. DH&SS
387 N.W.2d 245 (Wisconsin Supreme Court, 1986)
Club v. Wisconsin Department of Health & Social Services
387 N.W.2d 245 (Wisconsin Supreme Court, 1986)
Association Concerned About Tomorrow, Inc. v. Dole
610 F. Supp. 1101 (N.D. Texas, 1985)
Adler v. Education Department of New York
760 F.2d 454 (Second Circuit, 1985)
Adler v. Education Department of State of New York
760 F.2d 454 (Second Circuit, 1985)
Walt Disney Productions v. Basmajian
600 F. Supp. 439 (S.D. New York, 1984)
Glen Head — Glenwood Landing Civic Council, Inc. v. Town of Oyster Bay
88 A.D.2d 484 (Appellate Division of the Supreme Court of New York, 1982)
Webster Associates v. Town of Webster
112 Misc. 2d 396 (New York Supreme Court, 1981)
Grazing Fields Farm v. Neil Goldschmidt
626 F.2d 1068 (First Circuit, 1980)
Atchison, Topeka & Santa Fe Railway Co. v. Callaway
459 F. Supp. 188 (District of Columbia, 1978)
Trinity Episcopal School Corp. v. Harris
445 F. Supp. 204 (S.D. New York, 1978)
Badoni v. Higginson
455 F. Supp. 641 (D. Utah, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
372 F. Supp. 223, 6 ERC 1275, 4 Envtl. L. Rep. (Envtl. Law Inst.) 20230, 6 ERC (BNA) 1275, 1974 U.S. Dist. LEXIS 12343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/i-291-why-association-v-burns-ctd-1974.