Environmental Defense Fund, Inc. v. Robert F. Froehlke, Secretary of the Army

477 F.2d 1033, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20383, 5 ERC (BNA) 1313, 1973 U.S. App. LEXIS 10390, 5 ERC 1313
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 20, 1973
Docket72-1628
StatusPublished
Cited by38 cases

This text of 477 F.2d 1033 (Environmental Defense Fund, Inc. v. Robert F. Froehlke, Secretary of the Army) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Defense Fund, Inc. v. Robert F. Froehlke, Secretary of the Army, 477 F.2d 1033, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20383, 5 ERC (BNA) 1313, 1973 U.S. App. LEXIS 10390, 5 ERC 1313 (8th Cir. 1973).

Opinion

HEANEY, Circuit Judge.

The primary issue on this appeal is-whether the trial court erred in refusing to enjoin the defendants from proceeding with all activities relating to the construction of the Harry S Truman Dam and Reservoir Project on the Osage River in Missouri, pending the filing of a *1035 final Environmental Impact Statement (E.I.S.) by the Corps of Engineers in accordance with § 102(2)(C) of the National Environmental Policy Act of 1969. 42 U.S.C. §§ 4321, 4332(2)(C).

The project was authorized by Congress in 1954. Its basic purpose was to alleviate the flooding of towns and farms along the Osage, Mississippi and Missouri Rivers. The project was reauthorized in 1962 to promote conservation, power development and recreation. The dam, if built according to present design, will consist of an earth-fill embankment about 5,000 feet in length, a concrete structure slightly less than 1,000 feet long, and a dike 7,500 feet in length. Maximum height of the dam will be ninety-six feet above the valley floor. The reservoir will inundate 209,300 acres at full flood control pool and 55,600 acres of land at conservation or multi-purpose level. The reservoir’s capacity is 5,202,000 acre-feet at flood control level. The dam will be located in the vicinity of Warsaw, Missouri, immediately upstream from the Lake of the Ozarks. The expected total cost of the project to the federal government is $234,692,000,'

The first contract was awarded on July 15, 1963, six years prior to the passage of NEPA. By June of 1972, $74,000,000 had been expended for planning, land acquisition, road relocation and construction.

In March of 1972, the plaintiffs initiated this action in the United States District Court for the Western District of Missouri, seeking to enjoin the defendants from proceeding with the project. They contended that the defendants were proceeding with the project in violation of NEPA, the Fish and Wildlife Coordination Act of 1934, 1 16 U.S.C. § 661 et seq.; the Environmental Improvement Act of 1970, 42 U.S.C. § 4371; the Water Bank Act of 1970, 16 U.S.C. § 1301 et seq.; various other statutes and the United States Constitution. The principal violation alleged was the failure to prepare and file an E.I.S. pursuant to § 102(e) of NEPA. The plaintiffs asked the court to enjoin road relocations, land acquisitions, construction activity and all other work on the project until a final E.I.S. was filed in accordance with NEPA.

Carefully directed pretrial proceedings were conducted by the court in March and April, 1972. In May of 1972, the court held an evidentiary hearing on the merits. Thereafter, the parties stipulated that the environmental impact of the project would be significant, particularly with respect to fish fauna, archaeological and paleontological sites, wildlife and waterfowl habitat, mussels, society, agriculture and economics.

The parties further stipulated that certain activities would be halted by the Corps of Engineers pending the completion of a final E.I.S. They agreed: (1) that a draft E.I.S. would be prepared by September 15, 1972, and a final E.I.S. by March 1, 1973; (2) that the plaintiffs could include data, comments and statements as appendices to the studies; and (3) that specified guidelines would be followed by the Corps in preparing the study. They were unable to agree on the crucial question of whether the Corps should be required to cease all activities until the final E.I.S. had been filed and reviewed. That question was left for the court to decide.

The District Court’s judgment, accompanied by a detailed and scholarly memorandum opinion, was entered on September 13, 1972. Environmental Defense *1036 Fund, Inc. v. Froehlke, 348 F.Supp. 338 (W.D.Mo.1972). The court held that the plaintiffs were entitled to judicial review of the defendants’ actions, and that the defendants were obligated to comply with the provisions of NEPA in completing the project, even though the project was well under way before NEPA was passed. 2 It found that the Corps had started the preparation of an E.I.S. prior to the commencement of this action and was completing it as fast as the circumstances permitted. It enjoined the defendants from proceeding with certain activities and contracts, including those which the defendants had agreed to defer, but permitted the defendants to continue certain on-going construction activities, road relocations, cemetery relocations, voluntary property acquisitions, and design contracts, pending the filing of a final E.I.S. Moreover, it retained jurisdiction of the matter pending the filing of the final E.I.S.

The court held, however, that the plaintiffs were not entitled to an injunction halting all work on the project pending a final E.I.S. It did so on the grounds that not every violation of NEPA gives rise to a right to blanket injunctive relief. The court stated:

“It is our judgment that the procedures provided for in the final judgment and decree, if and when complied with, will assure full compliance with NEPA and all other applicable law as promptly' as is practicable under the circumstances. It is further our judgment that the issuance of a blanket injunction stopping all construction would not speed the preparation or enhance the probabilities that a sufficient EIS will be prepared. Under these circumstances, we believe that a proper balancing of the factors which must be given appropriate consideration under general equity principles requires that the most substantial costs incident to the termination or suspension or work to an extent greater than that provided in the final judgment and decree should be avoided.”

Environmental Defense Fund, Inc. v. Froehlke, supra at 353. The court gave the following additional reasons for its action :

(1) The work, which will go forward pending the filing of an E.I.S., will only have a minimal environmental impact on the Osage Basin. No work will be done on the dam which will impede the free flow of the river and affect the fish, wildlife and wildfowl habitat in or along the river. The new roads will affect some wildlife habitat, but the old road sites will, in time, partially replace the habitat lost.

(2) The project was commenced six years prior to the passage of NEPA, and a number of contracts have been let pursuant to congressional authorization. Substantial cost would be involved in terminating these contracts. Additional costs would be incurred in start-up costs if the ultimate decision is to proceed. Moreover, the defendants were in various stages of acquiring land, and the cost involved in terminating such acquisitions would be substantial.

(3) The Corps of Engineers was acting in good faith in bringing the project into compliance with NEPA. It began the preparation of a preliminary E.I.S. prior to the initiation of this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Russell v. Astrue
626 F. Supp. 2d 921 (D. Minnesota, 2009)
Crutchfield v. United States Army Corps of Engineers
192 F. Supp. 2d 444 (E.D. Virginia, 2001)
Yankton Sioux Tribe v. United States Army Corps of Engineers
83 F. Supp. 2d 1047 (D. South Dakota, 2000)
Association Concerned About Tomorrow, Inc. v. Dole
610 F. Supp. 1101 (N.D. Texas, 1985)
Highland Cooperative v. City of Lansing
492 F. Supp. 1372 (W.D. Michigan, 1980)
Orange County v. Department of Transportation
265 S.E.2d 890 (Court of Appeals of North Carolina, 1980)
North Slope Borough v. Andrus
486 F. Supp. 326 (District of Columbia, 1979)
Barcelo v. Brown
478 F. Supp. 646 (D. Puerto Rico, 1979)
United Parcel Service, Inc. v. United States Postal Service
475 F. Supp. 1158 (E.D. Pennsylvania, 1979)
United States v. Underwood
577 F.2d 157 (First Circuit, 1978)
Rodney D. Driver v. Richard Helms
577 F.2d 147 (First Circuit, 1978)
United States v. Articles of Food & Drug
441 F. Supp. 772 (E.D. Wisconsin, 1977)
Aluli v. Brown
437 F. Supp. 602 (D. Hawaii, 1977)
Driver v. Helms
74 F.R.D. 382 (D. Rhode Island, 1977)
Kipperman v. McCone
422 F. Supp. 860 (N.D. California, 1976)
James J. Chick v. Carla A. Hills
528 F.2d 445 (First Circuit, 1976)
City of South Pasadena v. Volpe
418 F. Supp. 854 (C.D. California, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
477 F.2d 1033, 3 Envtl. L. Rep. (Envtl. Law Inst.) 20383, 5 ERC (BNA) 1313, 1973 U.S. App. LEXIS 10390, 5 ERC 1313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-defense-fund-inc-v-robert-f-froehlke-secretary-of-the-ca8-1973.