Crutchfield v. United States Army Corps of Engineers

154 F. Supp. 2d 878, 53 ERC (BNA) 1761, 2001 U.S. Dist. LEXIS 12350, 2001 WL 935646
CourtDistrict Court, E.D. Virginia
DecidedAugust 14, 2001
DocketCiv.A. 300CV525
StatusPublished
Cited by9 cases

This text of 154 F. Supp. 2d 878 (Crutchfield v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crutchfield v. United States Army Corps of Engineers, 154 F. Supp. 2d 878, 53 ERC (BNA) 1761, 2001 U.S. Dist. LEXIS 12350, 2001 WL 935646 (E.D. Va. 2001).

Opinion

MEMORANDUM OPINION

PAYNE, District Judge.

In this action, Frances Broaddus Crutchfield and Henry Ruffin Broaddus challenge the authorization, under the Clean Water Act (“CWA”), by the United States Army Corps of Engineers (“the Corps”) of Nationwide Permits (“NWPs”) for the County of Hanover (“the County”). The NWPs verify the construction, without preparation of an Environmental Assessment or an Environmental Impact Statement as required by the National Environmental Policy Act (“NEPA”), of a wastewater treatment plant (“WWTP”), discharge force main, and an outfall 1 by the County. It is also alleged that the NWPs were unlawfully verified because the Corps did not first comply with the National Historic Preservation Act (“NHPA”). The challenges center around the relationship of the WWTP, force main and outfall components of a sewage treatment project to a sewer interceptor that is proposed to transport sewage to the WWTP and that, until recently, was referred to as a component of that sewage *881 treatment project. 2

Crutchfield and Broaddus challenge the NWPs under three substantive statutes and the Administrative Procedure Act (“APA”). Claim 1 alleges that the verification of the NWPs for the WWTP, force main, and outfall by the Corps violates the CWA, 33 U.S.C. §§ 1251 et seq., and the Corps’ regulations, 33 C.F.R. § 325.1 and 33 C.F.R. § 330.6. Claim 2 alleges that the verification of the NWPs violates NEPA, 42 U.S.C. §§ 4321 et seq. Claim 3 alleges that the verification of the NWPs violates the NHPA, 16 U.S.C. § 470 et seq.

The gravamen of each claim is that, in verifying the NWPs, the Corps improperly failed to take into account the impact of the planned Totopotomoy Creek Sewer Interceptor (hereinafter the “TC Interceptor”) on the environment and on historic resources. Broaddus and Crutchfield argue that the TC Interceptor is simply another component of a complete project that includes, as its other components, the WWTP, force main, and outfall. The parties agree that a project may not proceed under an NWP if the Corps concludes that it has “more than minimal individual or cumulative net adverse effects on the environment or otherwise may be contrary to the public interest.” C.F.R. § 330.1(d). It is undisputed that the entire project, i.e. the WWTP, force main and outfall and the TC Interceptor, if considered as a whole, was expected to have more than a minimal impact and that the Corps did not find otherwise. It is undisputed that the impact of the WWTP, force main and outfall is quite small and that the TC Interceptor, standing alone, was expected to have a more than minimal impact. 3

Broaddus and Crutchfield contend that the Corps acted arbitrarily and capriciously and in violation of law and regulation when, on a contrived, irrational basis, it did not take into account the impact of the TC Interceptor in verifying the NWPs here at issue. This, say the Plaintiffs, was the result of the improper manipulation of the permit process and the applicable permit regulations by the Corps and the County.

For the reasons set forth below, the action of the Corps verifying NWPs for the WWTP, force main, and outfall is found to be arbitrary, capricious and unlawful and, therefore, is set aside.

THE FACTS OF RECORD

Review of the Corps’ decisions must be based on the record. Hence, the facts in the record are set forth in detail.

A. Early Days

Many years ago, the County identified its growing wastewater treatment needs and developed a sewage treatment project, the components of which were a WWTP, force main, outfall, and interceptor, to meet those needs. “Construction of the wastewater treatment plant is critical to the County implementing its Comprehensive Plan where growth is directed into the ‘Suburban Service Area’ in order to preserve the rural character of the remainder *882 of Hanover County.” R426. 4 Although a WWTP in the general vicinity of the proposed WWTP has been part of the County’s comprehensive plan since 1972, R426, the County did not purchase the site for the proposed WWTP until 1997. R593. The County’s plans envision that the sewage treated in the WWTP is to be transported by a discharge force main to an outfall which will discharge the treated effluent into the Pamunkey River approximately 43,500 feet from the plant. R426-27. The TC Interceptor, like the WWTP, has “been shown in the [County’s] Comprehensive Plan for many years.” R426.

B. The Developments in 1997,1998 and Early 1999

The TC Interceptor here at issue is the fourth phase of a sewer interceptor, the first phase of which was designed in 1983 and placed in service in 1985. The fourth phase TC Interceptor is the link between the existing interceptor and the WWTP.

The County’s long-term plan began to jell when, in 1997, it settled on the exact location of the WWTP. In a report dated February 10, 1997, the County’s outside consulting engineering firm, Timmons, recommended that the current location of the TC Interceptor be where it is today. R247-51. In that report (Totopotomoy Basin Wastewater Transport Options Letter Report), Timmons outlined the Basis of Analysis animating its recommendation. Among the “assumptions” used for those recommendations were:

• Totopotomoy Creek WWTP will be completed by 2002.
• Flow from pump station # 5 (Atlee High School) needs to be conveyed to the new WWTP at the time of its opening to provide sufficient flow for proper operation.

R248 (emphasis added). Thus, the record shows that the flow from the TC Interceptor is linked to the WWTP not only as the source of supply for the raw material that is to be treated at the WWTP, but also to assure proper operation of the WWTP itself. Even though site selection for the WWTP was not complete in 1997, the assumed site for the plant in February 1997 was the one on which the WWTP actually will be located. The February 1997 Letter Report on sewage transport options discusses three alternative modes for the proposed interceptor:

• Alternative A: Single Gravity Sewer
• Alternative B: Parallel Gravity Sewer
• Alternative C: Force Main.

R248^49. However, that report makes no mention of a location for the proposed TC Interceptor other than the one here at issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
154 F. Supp. 2d 878, 53 ERC (BNA) 1761, 2001 U.S. Dist. LEXIS 12350, 2001 WL 935646, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crutchfield-v-united-states-army-corps-of-engineers-vaed-2001.