Crutchfield v. United States Army Corps of Engineers

214 F. Supp. 2d 593, 55 ERC (BNA) 1643, 2002 U.S. Dist. LEXIS 14640, 2002 WL 1836418
CourtDistrict Court, E.D. Virginia
DecidedAugust 7, 2002
DocketCIV.A. 3:02CV253
StatusPublished
Cited by6 cases

This text of 214 F. Supp. 2d 593 (Crutchfield v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crutchfield v. United States Army Corps of Engineers, 214 F. Supp. 2d 593, 55 ERC (BNA) 1643, 2002 U.S. Dist. LEXIS 14640, 2002 WL 1836418 (E.D. Va. 2002).

Opinion

MEMORANDUM OPINION

PAYNE, District Judge.

The County of Hanover, Virginia (the “County”) received from the United *598 States Army Corps of Engineers (the “Corps”) authorization to build a project, the purpose of which is to collect sewage, treat it, and then discharge the treated sewage into the Pamunkey River. As designed, the point of discharge (or “outfall”) would be located on property that Frances Broaddus Crutchfield and Henry Ruffin Broaddus (the “Plaintiffs”) own, and the discharge would be dispersed into the Pamunkey River by a diffuser that would be located in the Pamunkey River where the river abuts the Plaintiffs’ property.

The Virginia Department of Environmental Quality (the “DEQ”) has classified the Pamunkey River as “impaired” because the level of fecal bacteria extant therein exceeds that which is allowable under applicable water quality standards. 1 The Pamunkey River also suffers from shortage of dissolved oxygen and, for that reason, the DEQ has listed it as “threatened due to natural conditions.” See Administrative Record, at 1806-08.

In a previous action, the Court invalidated the Corps’ decision to verify that the County could construct a slightly different version of the project pursuant to several so-called Nationwide Permits (“NWPs”). The matter was remanded to the Corps, which, by a Memorandum for the Record (“MFR”) dated April 4, 2002 (the “April 4 MFR”), decided that the County could proceed with a modified version of its waste-water treatment project under a different set of NWPs. In this action, the Plaintiffs challenge that second permitting decision.

For a complete understanding of the previous litigation, it is advisable to refer to the Memorandum Opinions issued in Crutchfield v. United States Army Corps of Engineers, Civil Action No. 3:00ev525, on August 14, 2001, 2 November 2, 2001, 3 and December 12, 2001, 4 and to the Memorandum Order issued May 22, 2002 (collectively referred to as “Crutchfield I”). Those decisions provide a comprehensive review of the first dispute, resolution of which preceded, ahd forms the background of, this action. In the interests of brevity and completeness, the opinions in Crutch-field I are incorporated here, however, a summary review of the prior litigation is set forth in Section I.A.

Like Crutchfield I, this action was filed pursuant to the judicial review provisions of the Administrative Procedure Act, 5 U.S.C. § 551, et seq. (the “APA”). The Complaint alleges that, in addition to violating the APA, the decision-making process through which the Corps verified the County’s use of four NWPs as the authority under which to construct its revised sewage treatment project contravened the Clean Water Act (“CWA”), 33 U.S.C. §§ 1251 et seq.; the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321 et seq.; and the National Historic Preservation Act (“NHPA”), 16 U.S.C. §§ 470 et seq. The Plaintiffs contend that, for a second time, the Corps’ actions with respect to the County’s project were arbitrary, capricious, and not in accordance with law. 5 The parties have submitted *599 briefs in support of their respective positions on the merits of the Plaintiffs’ challenge, and, on July 10, 2002, oral argument was heard. For the reasons set forth below, the Corps’ decision to verify the NWPs, as articulated in the April 4 MFR, is set aside as arbitrary, capricious, and not in accordance with law.

I. STATEMENT OF FACTS

A. Crutchfield I

As stated above, the nature and evolution of this dispute can be appreciated fully only in perspective of the decisions in Crutchfield I, however, for present purposes, an abbreviated review of that case must suffice. Under the circumstances outlined exhaustively in the decisions issued in Crutchfield I, the County planned, and began construction of, a wastewater treatment project, several aspects of which implicated federal environmental laws and regulations, and, as such, required authorization by the Corps. That project, as it originally was conceived, involved construction of a wastewater treatment plant (the “WWTP”), an interceptor pipeline to carry untreated wastewater to the WWTP for treatment (which the parties referred to as the “TC Interceptor”), a discharge forcemain, and an outfall/diffuser structure. See generally Crutchfield, 154 F.Supp.2d at 881-86, 175 F.Supp.2d at 838-40, 192 F.Supp.2d at 447-51. Pursuant to the CWA and its implementing regulations, the Corps was called upon to decide what type of permits, if any, could issue to authorize the County to undertake certain activities (ie., dredging, filling, and construction) involving wetlands upon which components of that project were intended to be built. 6 On June 7, 2000, the Corps issued a Memorandum for the Record verifying that the County was authorized to proceed with construction of the WWTP, forcemain, and outfall pursuant to Nationwide Permits (“NWPs”) because those three components of the project would cause only minimal impacts to wetlands. However, the Corps also decided that the TC Interceptor needed to be assessed under the more stringent regulations applicable to individual permits because the impact on wetlands of that component would be more than minimal.

At the risk of oversimplification, there are two basic processes through which the Corps may confer its regulatory approval upon projects that affect wetlands which are subject to its jurisdiction. One is the general permit procedure, of which verification of an NWP authorization is one kind. The other is the issuance of an individual permit.

Projects that are permitted to proceed under NWPs undergo no significant environmental review under the CWA; that is because such a project qualifies for NWP status only upon a preliminary determination that it will have “minimal impacts” upon wetlands. In contrast, projects that must proceed pursuant to the individual permit process undergo a rigorous environmental review. Clearly, it is significantly advantageous for a permit applicant to be allowed to proceed under an NWP *600 and, thereby, avoid the expense and delay that attends the more thorough environmental scrutiny that is inherent in the individual permit process. Thus, the determination whether a project poses a greater than “minimal impact” on wetlands is of critical importance. And, as shown in Crutchfield

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
214 F. Supp. 2d 593, 55 ERC (BNA) 1643, 2002 U.S. Dist. LEXIS 14640, 2002 WL 1836418, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crutchfield-v-united-states-army-corps-of-engineers-vaed-2002.