Crutchfield v. United States Army Corps of Engineers

230 F. Supp. 2d 673, 2002 U.S. Dist. LEXIS 21735, 2002 WL 31497283
District Court, E.D. Virginia·Decided October 31, 2002·No. CIV.A. 3:02CV253·Published·Cited by 3 cases

Opinion

MEMORANDUM OPINION

PAYNE, District Judge.

This action arises out of the ongoing efforts of Hanover County (the “County”) to provide capacity to treat and dispose of the forecast increases in wastewater expected to accompany forecast growth in certain areas of the County. Under the circumstances outlined fully in a Memorandum Opinion issued on August 7, 2002 (the “August 7 Opinion”), the County planned, and began construction of, a wastewater treatment project that would impact a small amount of wetlands, and therefore required authorization from the United States Army Corps of Engineers (the “Corps”). Crutchfield v. United States Army Corps of Engineers, 214 F.Supp.2d 593 (E.D.Va.2002) (“Crutchfield IP’).

The Corps initially authorized the County to proceed with the project under the authority of Nationwide Permits (“NWPs”). In Crutchfield v. United States Army Corps of Engineers, 154 F.Supp.2d 878, 906 (E.D.Va.2001) (“Crutchfield 1 ”), the Corps’ decision was set aside as arbitrary, capricious, and not in accordance with law. The matter was remanded to the Corps for reconsideration. 1 In April 2002, the Corps again au *675 thorized the County to proceed with the project under the authority of NWPs. The Plaintiffs again challenged the decision of the Corps, and the Corps’ decision again was set aside as arbitrary, capricious, and not in accordance with law. The matter was then remanded to the Corps for reconsideration. See Crutchfield II, 214 F.Supp.2d at 655.

In their Complaint, the Plaintiffs alleged that they were entitled to permanent in-junctive relief, if they prevailed on the merits. The Plaintiffs now seek an order enjoining the County from constructing, or allowing a third party to construct, any portion, component, or aspect of the project while the Corps reconsiders the matter on remand. For the reasons that follow, the Plaintiffs’ motion is denied.

BACKGROUND

The August 7 Opinion, along with the opinions in Crutchfield I, set forth the historical background respecting the County’s wastewater treatment project and the permitting decisions made by the Corps. Those opinions collectively describe the full course of the administrative process and the earlier litigation in the matter. The August 7 Opinion, in particular, describes the framework within which the issue of injunctive relief now under consideration arises; and therefore, it is incorporated here in the interest of brevity. Nonetheless, a brief outline of the facts relevant to the assessment of the request for injunctive relief is useful.

For some years, the County has pursued the project at issue here as a means of addressing a projected shortfall in waste-water treatment capacity. In its original iteration, this project consisted of a waste-water treatment plant (“WWTP”), an interceptor pipeline running along the Toto-potomoy Creek (the “TC Interceptor”) to collect sewage and transport it by gravity flow to the WWTP, a forcemain taking processed waste from the WWTP to the discharge location in the Pamunkey River adjacent the Plaintiffs’ family farm (“Newcastle Farm”), and an outfaU/diffuser structure where the waste actually discharges into the river. Because this project impacted wetlands, federal environmental statutes and regulations required the County to secure appropriate permits from the Corps.

As explained fully in Crutchfield I, 2 the Corps’ regulations delineate two broad categories of permits: a general permit, of which an NWP is one sub-type, and an individual permit. Use of an NWP is allowed following a form of approval known as “verification.” Use of an individual permit follows issuance of the individual permit. Verification to use an NWP necessitates a substantially less rigorous review of environmental issues than that which must precede issuance of an individual permit.

In June 2000, the Corps verified that the County could proceed, under the authority of three NWPs, with construction of all components of the project as then conceived, except the TC Interceptor, which the Corps decided to consider separately from the rest of the project under an application for an individual permit. The Plaintiffs challenged the decision .of the Corps to consider the TC Interceptor separately, a decision that freed the Corps of the responsibility to conduct environmental assessments that otherwise would have been required under the relevant federal environmental protection laws. On August 14, 2001, the Court held that the Corps’ decision to authorize construction of some of the components under those NWPs without considering the impact of the TC *676 Interceptor (which clearly was an integral part of a cohesive four part project) to be arbitrary, capricious and not in accordance with law. See Crutchfield I, 154 F.Supp.2d at 895-903. In so doing, the Court noted that the Corps, at the urging of the County, arrived at a “remarkably illogical conclusion” respecting whether WWTP, the force main, and the outfall/diffuser had “independent utility” from the TC Interceptor sufficient to justify separate consideration. See id. For that reason and others explained in Crutchfield I, the Corps’ decision to allow part of the project to proceed under three NWPs (while it considered the County’s application for an individual permit for the TC Interceptor) was vacated and the matter was remanded for reconsideration.

After prevailing on the merits in Crutch-field I, the Plaintiffs filed a motion for permanent injunction to halt construction on the project pending the Corps’ reconsideration on remand. 3 On November 2, 2001, the Court granted the Plaintiffs’ motion, finding, inter alia, that, if the County continued work, there was a “substantial probability” that further construction on the project would unduly influence the Corps, thereby rendering objective review of the environmental impacts impossible. See 192 F.Supp.2d 444, 455-66 (E.D.Va. 2001) (the “November 2 Injunction Opinion”).

In November 2001, the County reassessed the project and modified it to ex-elude the TC Interceptor, the component having the greatest impact on wetlands. Instead, the County proposed to collect and convey wastewater to the WWTP through the so-called Lee Davis Pump Station and forcemain, which consists of a pump station serving approximately five square miles of the County’s service area to the south of the Totopotomoy Creek watershed, and a forcemain connecting the pump station to the WWTP. The County then filed a Joint Permit Application (“JPA”) with the Corps on November 16, 2001. 4 In all respects other than the Lee Davis Pump Station and forcemain, the project was the same as originally proposed.

At a pre-application meeting held on November 9, 2001 between the County and the Corps, the County again urged the Corps to consider authorization of the project under NWPs. The Corps declined. In a November 16, 2001 Memorandum for the Record (the “November 16 MFR”), Ms. Pamela K.

Free access — add to your briefcase to read the full text and ask questions with AI

Crutchfield v. United States Army Corps of Engineers, 230 F. Supp. 2d 673, 2002 U.S. Dist. LEXIS 21735, 2002 WL 31497283 (E.D. Va. 2002).

230 F. Supp. 2d 673 (Crutchfield v. United States Army Corps of Engineers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

MARTIN v. SEABOLT
M.D. North Carolina, 2024
Orlando v. Smith
W.D. Virginia, 2023
MicroStrategy, Inc. v. Business Objects, S.A.
369 F. Supp. 2d 725 (E.D. Virginia, 2005)