MEMORANDUM and ORDER
PECKHAM, District Judge.
Plaintiffs herein seek to enjoin construction of a Route 101 by-pass near Novato, California. The present Route 101 runs the length of the State of California and passes through the business section of Novato, where the traffic encounters low speed limits, three traffic signals, and congested conditions. Defendants have filed affidavits showing that a highway by-pass has been planned for over ten years, but various political misgivings about the exact route have prevented construction from taking place sooner. The project received location approval on March 2, 1967, and design approval on December 12, 1968.
Subsequent to the latter date there were minor changes in design involving a fence and the closing of a side street, but the court finds that design approval as described in the Department of Transportation regulations was granted on December 2,1968.
Plaintiffs have moved for an injunction pending appeal and for reconsideration of the court’s denial of their motion for a preliminary injunction. The basis of their motion for a preliminary injunction was the state defendants’ failure to file, and the federal defendants’ failure to require, an environmental impact statement, as described in Section 102(2) (C) of the National Environmental Policy Act, 42 U.S.C. § 4321 et seq. (NEPA).
The Act was passed by the United States Senate on December 20, 1969, and then became effective on January 1, 1970. The problem in the instant case concerns the significance of the date January 1, 1970. Defendants contend that no environmental impact statement is required for projects receiving design approval before January 1, 1970. Plaintiffs, on the other hand, seem to contend that if any harm to the environment is likely to take place, an environmental impact statement
must
be filed. The basic question in this case is the extent to which NEPA applies to an ongoing project.
The National Environmental Policy Act is a legislative expression of the
deep significance this society attaches to the preservation of the environment. Congress believed that for too many years environmental considerations had been ignored while federal projects blindly forged ahead, cutting through parks, streams, and forests, increasing various forms of pollution, destroying environmental resources, and, in many cases, upsetting the ever-delicate ecological balance in a geographic area. Congress responded to what many have characterized as an intensive and long-term ravaging of the environment with the NEPA. Though in the past Congress had enacted many bills directed towards environmental protection, the NEPA clearly represents the strongest legislative policy statement in this area. For example, the Act compels government agencies to take environmental considerations into account and to give them significant weight in the balancing of factors.
In light of this strong statement of policy, courts have been most active in assuring that the environment receives adequate protection.
The main foil of the NEPA policies is the Section 102(2) (C) requirement of impact statements. Congress recognized that without detailed studies it would be most difficult to identify and to evaluate the environmental ramifications of a project, particularly where the ecological balance may be affected. Section 102(2) (C) was enacted to force Government agencies to investigate and to consider these environmental ramifications, be they apparent or covert. Each agency hopefully will now have before it all the necessary data to adequately consider the harm to the environment.
The stated effective date of the statute, and more particularly Section 102 (2) (C), is January 1, 1970. It is most difficult to place a practical meaning on this statement, as most projects that are “major federal actions” are not constructed over night. Most highway projects, for example, take six to eight years from the time that location approval is sought until construction is completed. Many federal actions were in some stage of development — whether planning or construction — when the NEPA was passed, and a volatile dispute in the law has emerged on the extent to which NEPA, and particularly Section 102(2) (C), applies to an ongoing project. See, e. g., Brooks v. Volpe, 319 F.Supp. 90 (W.D.Wash.1970), motion for re-hearing denied, 329 F.Supp. 118 (1971), rev. on other grounds, 460 F.2d 1193 (9th Cir., 1972); Calvert Cliffs, Coordinating Committee, Inc. v. United States Atomic Energy Commission, 449 F.2d 1109 (D.C. Cir. 1971); Morningside-Lenox Park Association v. Volpe, 334 F.Supp. 132 (N.D.Ga.1971); Nolop v. Volpe, 333 F.Supp. 1364 (D.S.Dak.1971); Pennsylvania Environmental Council, Inc. v. Bartlett, 315 F.Supp. 238 (M.D.Pa.1970).
The Council on Environmental Quality addressed this problem in its guidelines to other governmental agencies:
11. Application of Section 102(2) (c) procedure to existing projects and programs. To the maximum extent practicable the Section 102(2) (c) procedure should be applied to further major federal actions having a significant effect upon the environment even though they arise from projects or programs initiated prior to the enactment of the Act on January 1, 1970. Where it is not practicable to reassess the basic course of action, it is still important that further incremental federal actions be shaped so as to minimize adverse environmental consequences. It is also important in further action that account be taken of environmental consequences not fully evaluated at the outset of the project or program.
The CEQ Guidelines make a clear distinction between projects initiated
before
January 1, 1970 and projects
initiated
after
January 1, 1970.
For the latter an environmental impact statement is required “to the fullest extent possible” but for the former a statement is required only “to the maximum extent
practicable”.
This distinction is in concert with the legislative history and the general principles against retroactive application of statutes.
Plaintiffs contend that the NEPA should apply in toto to ongoing projects but fail to cite any persuasive authority that this was the intent of Congress.
The court agrees with the reasoning in Elliot v. Volpe, 328 F.Supp. 831 (D.Mass.1971) that one must distinguish between projects initiated before January 1, 1970 and projects initiated after January 1,1970.
The CEQ Guidelines, however, do not explain how the criterion of “to the maximum extent practicable” applies to federal actions, and particularly to highway projects.
Free access — add to your briefcase to read the full text and ask questions with AI
MEMORANDUM and ORDER
PECKHAM, District Judge.
Plaintiffs herein seek to enjoin construction of a Route 101 by-pass near Novato, California. The present Route 101 runs the length of the State of California and passes through the business section of Novato, where the traffic encounters low speed limits, three traffic signals, and congested conditions. Defendants have filed affidavits showing that a highway by-pass has been planned for over ten years, but various political misgivings about the exact route have prevented construction from taking place sooner. The project received location approval on March 2, 1967, and design approval on December 12, 1968.
Subsequent to the latter date there were minor changes in design involving a fence and the closing of a side street, but the court finds that design approval as described in the Department of Transportation regulations was granted on December 2,1968.
Plaintiffs have moved for an injunction pending appeal and for reconsideration of the court’s denial of their motion for a preliminary injunction. The basis of their motion for a preliminary injunction was the state defendants’ failure to file, and the federal defendants’ failure to require, an environmental impact statement, as described in Section 102(2) (C) of the National Environmental Policy Act, 42 U.S.C. § 4321 et seq. (NEPA).
The Act was passed by the United States Senate on December 20, 1969, and then became effective on January 1, 1970. The problem in the instant case concerns the significance of the date January 1, 1970. Defendants contend that no environmental impact statement is required for projects receiving design approval before January 1, 1970. Plaintiffs, on the other hand, seem to contend that if any harm to the environment is likely to take place, an environmental impact statement
must
be filed. The basic question in this case is the extent to which NEPA applies to an ongoing project.
The National Environmental Policy Act is a legislative expression of the
deep significance this society attaches to the preservation of the environment. Congress believed that for too many years environmental considerations had been ignored while federal projects blindly forged ahead, cutting through parks, streams, and forests, increasing various forms of pollution, destroying environmental resources, and, in many cases, upsetting the ever-delicate ecological balance in a geographic area. Congress responded to what many have characterized as an intensive and long-term ravaging of the environment with the NEPA. Though in the past Congress had enacted many bills directed towards environmental protection, the NEPA clearly represents the strongest legislative policy statement in this area. For example, the Act compels government agencies to take environmental considerations into account and to give them significant weight in the balancing of factors.
In light of this strong statement of policy, courts have been most active in assuring that the environment receives adequate protection.
The main foil of the NEPA policies is the Section 102(2) (C) requirement of impact statements. Congress recognized that without detailed studies it would be most difficult to identify and to evaluate the environmental ramifications of a project, particularly where the ecological balance may be affected. Section 102(2) (C) was enacted to force Government agencies to investigate and to consider these environmental ramifications, be they apparent or covert. Each agency hopefully will now have before it all the necessary data to adequately consider the harm to the environment.
The stated effective date of the statute, and more particularly Section 102 (2) (C), is January 1, 1970. It is most difficult to place a practical meaning on this statement, as most projects that are “major federal actions” are not constructed over night. Most highway projects, for example, take six to eight years from the time that location approval is sought until construction is completed. Many federal actions were in some stage of development — whether planning or construction — when the NEPA was passed, and a volatile dispute in the law has emerged on the extent to which NEPA, and particularly Section 102(2) (C), applies to an ongoing project. See, e. g., Brooks v. Volpe, 319 F.Supp. 90 (W.D.Wash.1970), motion for re-hearing denied, 329 F.Supp. 118 (1971), rev. on other grounds, 460 F.2d 1193 (9th Cir., 1972); Calvert Cliffs, Coordinating Committee, Inc. v. United States Atomic Energy Commission, 449 F.2d 1109 (D.C. Cir. 1971); Morningside-Lenox Park Association v. Volpe, 334 F.Supp. 132 (N.D.Ga.1971); Nolop v. Volpe, 333 F.Supp. 1364 (D.S.Dak.1971); Pennsylvania Environmental Council, Inc. v. Bartlett, 315 F.Supp. 238 (M.D.Pa.1970).
The Council on Environmental Quality addressed this problem in its guidelines to other governmental agencies:
11. Application of Section 102(2) (c) procedure to existing projects and programs. To the maximum extent practicable the Section 102(2) (c) procedure should be applied to further major federal actions having a significant effect upon the environment even though they arise from projects or programs initiated prior to the enactment of the Act on January 1, 1970. Where it is not practicable to reassess the basic course of action, it is still important that further incremental federal actions be shaped so as to minimize adverse environmental consequences. It is also important in further action that account be taken of environmental consequences not fully evaluated at the outset of the project or program.
The CEQ Guidelines make a clear distinction between projects initiated
before
January 1, 1970 and projects
initiated
after
January 1, 1970.
For the latter an environmental impact statement is required “to the fullest extent possible” but for the former a statement is required only “to the maximum extent
practicable”.
This distinction is in concert with the legislative history and the general principles against retroactive application of statutes.
Plaintiffs contend that the NEPA should apply in toto to ongoing projects but fail to cite any persuasive authority that this was the intent of Congress.
The court agrees with the reasoning in Elliot v. Volpe, 328 F.Supp. 831 (D.Mass.1971) that one must distinguish between projects initiated before January 1, 1970 and projects initiated after January 1,1970.
The CEQ Guidelines, however, do not explain how the criterion of “to the maximum extent practicable” applies to federal actions, and particularly to highway projects. The Department of Transportation has the responsibility of setting out detailed guidelines for the state highway departments and for the courts on this problem, but Policy and Procedure Memorandum 90-1 offers little assistance in this matter.
Consequently, the court must determine its own standards of practicability.
The first matter to consider is the
most appropriate time
for filing the environmental impact statement. Ideally, one would prefer the environmental considerations to be taken into account at the planning stage. In the case of federal-aid highways, this would be pri- or to design approval.
The United States Court of Appeals for the Third Circuit addressed itself to the importance of design approval in the ease of Wildlife Preserves, Inc. v. Volpe, 443 F.2d 1273 (3rd Cir. 1971). Although that case concerned § 4(f) statements rather than NEPA statements,
the reasoning
on the importance of design approval is still applicable. The court in
Wildlife Preserves
held that design approval is the crucial planning stage for a highway project. All the planning, and all the environmental, economic, and social factors should be taken into account at this stage.
In other words, if an environmental impact statement is to be filed, it should be filed prior, to design approval, when all the planning has been done.
Thus, even if a project were initiated prior to January 1, 1970, if the planning phase of the project did not take place until after January 1, 1970, a NEPA statement is required. No balancing of factors can be permitted in such a case;
the state highway department
must
file a statement in compliance with Section 102(2) (C).
However, if all the planning for a project took place
prior
to January 1, 1970— that is, if design approval preceded the passage of NEPA — a Section 102(2) (C) statement is required only if “practicable”. The specific further criteria of practicability will be discussed below, but the court first desires to emphasize the significance of design approval.
The court is aware that some courts have held, in effect, that no environmental impact statement is required
at all
if design approval took place prior to January 1, 1970. See Investment Syndicates, Inc. v. Richmond, 318 F.Supp. 1038 (D.Or.1970); Brooks v. Volpe, 319 F.Supp. 90 (W.D.Wash.1970), motion for re-hearing denied, 329 F.Supp. 118 (1971), reversed on other grounds, 460 F.2d 1193 (9th Cir., 1972);
Pennsylvania Environmental Council, Inc. v. Bartlett, 315 F.Supp. 238 (M.D.Pa.1970). The court respectfully declines to follow these cases, as it believes these courts have not weighed sufficiently the strong federal policies protecting the environment. The National Environmental Policy Act and the legislative discussions preceding the passage of the Act demonstrate rather persuasively that Congress places an immense value on the preservation and protection of the environment. One would have to ignore the strength of these policy statements to assert that severe environmental or ecological harm can be permitted simply because all plan
ning had been completed before January 1, 1970. An environmental impact statement is still required if practicable.
On the other hand, the Act and the CEQ Guidelines clearly distinguish between projects initiated prior to January 1, 1970 and projects initiated after that date. Obviously, if the planning phase has not been completed, it is still practicable to file a statement. But plaintiffs urge this court to go further, to the point where an environmental impact statement should be required for
all
projects from which some deleterious effect to the environment may occur, even if the planning stage has been completed. In other words, plaintiffs believe that for most federal projects it is “practicable” to file a statement as long as construction did not commence prior to January 1, 1970.
Not only does the court find the commencing of construction an arbitrary cut-off point, but plaintiffs’ position ignores the distinction made in the Act itself and in the CEQ Guidelines.
The major question that remains, then, is when is it “practicable” for a state highway department to “re-plan” a highway project that received design approval before January 1, 1970. As was stated above, there is little guidance for deciding when it is practicable to require a statement, and the court is forced to develop its own standards. The court believes that four major factors should be taken into account in determining the practicability of requiring a NEPA statement after a project has passed the planning stage:
1. The participation of the local community in the planning of a project.
Community participation in the decision-making process is most important. Indeed, it is questionable if environmental (as well as social or economic) factors can be taken into account in any meaningful manner without community participation in the decision. The residents of the local community are the ones who must live with and tolerate a highway, a high-rise, a dam, or any other “major federal action”. In regard to highway projects, PPM 20-8 clearly acknowledges the importance of public hearings and local participation in the decision-making process.
2. The extent to which the state department involved has attempted to take environmental factors into account in regard to a particular project.
If, at the planning stage, the state has not attempted to take into account possible environmental ramifications, it may-in effect have frustrated strong federal policies against harming the environment. It does not seem burdensome to ask the state to attempt to consider the risks and harms from a project. If the decision-makers have made little or no attempt to take into account environmental factors, an environmental impact statement is most likely “practicable”.
3. The likely harm to the environment if the project is constructed as planned.
Obviously, it is difficult to assess accurately the exact harm to the environment without a comprehensive impact statement; indeed, that is the purpose of Section 102(2) (C). If, however, a plaintiff can show that significant damage to the environment may take place, an environmental impact statement may be quite “practicable”. The court would point out that the opportunity to utilize this factor rests almost entirely with the plaintiff; that is to say, this factor does not deserve much weight in the balance unless a plaintiff can establish that some environmental harm is likely to take place.
4. The cost to the state of halting construction while it compiles an environmental impact statement.
The practicability of an impact statement must depend, to a large extent, on the cost to the state of halting construction on the project. For example, if a state can show that suspending work on the project will impose a significant cost, then the plaintiffs must demonstrate rather strongly through the other three factors mentioned above why a statement is still practicable.
It is important to note that under the proposed test, the stage of progress of a particular project is significant only to the extent that the state will suffer some economic harm if work is halted while it gathers data on the environmental ramifications. Under the proposed balancing of factors approach, the court would halt a project presently under construction if the cost to the state would be outweighed by the possible harm to the environment, and/or if the plaintiffs could demonstrate that the state made little or no effort to take environmental factors into account, and/or if local participation in the decision-making process had been minimal.
Applying the proposed test for practicability to the facts of the instant case, one sees that the balance of factors rests with the state.
Factor 1:
the participation of the local community in the planning of the project.
Defendants have submitted numerous exhibits and affidavits which show that the community in Novato was extremely
active in the planning and development of the proposed highway. See Defendants’ Exhibits H, I, and J, and Affidavit of Leo J. Trombatore. Indeed, the strong, active campaign of the newspapers has fostered a vigorous debate within the community on the pluses and minuses of various aspects of the proposed highway. While the extensive discussions have no doubt delayed the development of the project, the Novato Advance and various citizens groups involved must be commended for their efforts to inform the community and to assure that factors normally swept under the rug would be taken into account.
Factor 2:
the extent to which the state has attempted to take environmental factors into account.
The state highway department definitely has attempted to take environmental factors into account. On March 30, 1971 the California Highway Department submitted an environmental fact sheet which, although not nearly elaborate enough to pass as a satisfactory 102(2) (C) statement, nevertheless does show that the state has attempted to take environmental factors into account. Defendants’ Exhibit C. Moreover, as part of the process of applying for a permit from the Coast Guard to bridge Novato Creek, a 102(2) (C) statement for this portion of the highway was furnished to the Coast Guard. Subsequently, the state obtained from the Coast Guard a permit to bridge Novato Creek. (See Defendants’ Exhibit E.)
Factor 3:
the likely harm to the environment if the project is constructed as planned.
Unlike the situation in
La Raza Unida, supra,
or the
Army Corps of Engineers
(Florida) case,
supra,
this is not a situation where parklands will be destroyed or a delicate ecological balance will be drastically affected. The only possible harm to the environment alleged by plaintiffs is the supposed danger from excavation with the “waste and borrow” method of highway construction. See the two affidavits of Jerry A. Cannon, and affidavits of Arthur T. Knutson and Keith H. Bergman. Plaintiffs have conceded that their grievance is with the
method of construction,
not with the
route
of the proposed project. These affiants assert that alternative methods exist which may be less harmful to the environment. These assertions — and, to repeat, these are the
only
allegations of harm to the environment — are challenged by the affidavit of a state highway engineer, Mr. W. J. Zenoni, dated January 25, 1972. Mr. Zenoni asserts that the alternatives suggested by plaintiffs’ affiants were considered and rejected as either too expensive
or structurally unsound. Nevertheless, in this part of the balancing test we must assume that some harm to the environment will take place, in the form of massive excavation.
Factor
J: the cost to the state of halting construction while it compiles an environmental impact statement.
If an injunction were granted until the state compiles an environmental impact statement, there is a significant chance the state will suffer a severe economic loss. On oral argument, and with a supporting affidavit, counsel for the state defendants represented to the court that if an injunction were to issue, the state “very likely” would lose approximately $10.8 million in federal highway funds. Moreover, the state will be liable to various contractors for any loss the latter suffer as a result of the delay.
An over-view of the four factors taken collectively reveals that an environmental impact statement is simply not “practicable” at this time. The community has participated actively in the decision-making process; the state has made significant efforts to take environmental ramifications into account; and any alleged harm to the environment would seem to be outweighed by the cost to the state if an injunction were to issue. Consequently, the motion for a preliminary injunction and the motion for reconsideration must be denied.
This is not to say that in most highway cases where design approval was received before January 1, 1970 an environmental impact statement would not be required. Indeed, the court can envision many situations where a 102(2) (C) statement would be required even though design approval took place prior to January 1, 1970. For example, if a plaintiff could establish that the local community did not have an adequate opportunity to participate in the decision-making process; or that the state had ignored or not sufficiently considered the environmental ramifications of the project; or that the harm to the environment would be severe; or that the state would not incur a high cost if the highway project were enjoined, then an injunction should issue and the state should be required to submit an environmental impact statement. The situation presently before the court is simply not such a case.
Finally, under the test set forth in Schwartz v. Covington, 341 F.2d 537 (9th Cir. 1965), the motion for a stay pending appeal must be denied.