HM DG, Inc. v. Amini and Beizai

219 Cal. App. 4th 1100, 162 Cal. Rptr. 3d 412, 2013 WL 5299260, 2013 Cal. App. LEXIS 754
CourtCalifornia Court of Appeal
DecidedSeptember 20, 2013
DocketB242540
StatusPublished
Cited by28 cases

This text of 219 Cal. App. 4th 1100 (HM DG, Inc. v. Amini and Beizai) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
HM DG, Inc. v. Amini and Beizai, 219 Cal. App. 4th 1100, 162 Cal. Rptr. 3d 412, 2013 WL 5299260, 2013 Cal. App. LEXIS 754 (Cal. Ct. App. 2013).

Opinion

*1103 Opinion

HEESEMAN, J. *

INTRODUCTION

Plaintiffs and respondents HM DG, Inc., and Hassan Majd doing business as Majd Design Group (HMDG) sued defendants and appellants Farzad Etemad Amini and Pouneh Beizai (Defendants) in the superior court to recover allegedly unpaid progress payments under a construction contract for a high-end remodel of Defendants’ home. After HMDG refused Defendants’ demand to submit the dispute to arbitration, Defendants filed a petition to compel arbitration pursuant to an arbitration clause in the parties’ contract. The trial court denied the petition, holding that Defendants failed to establish the existence of a valid arbitration agreement on the ground that the “arbitration clause at issue is uncertain in that it does not specify before what agency o[r] person the matter will be arbitrated, [or] how the arbitrator will be selected, but merely sets for[th] alternative options for these terms.” The trial court also awarded HMDG its attorney fees incurred in opposing the petition to compel arbitration. We reverse.

Code of Civil Procedure section 1281.6 * 1 specifically contemplates the existence of an enforceable arbitration agreement even where the “arbitration agreement does not provide a method for appointing an arbitrator . . . .” The statute further provides that “[i]n the absence of an agreed method, or if the agreed method fails . . . , the court, on petition of a party to the arbitration agreement, shall appoint the arbitrator.” (Ibid.) As we shall explain, because the court has the power to appoint an arbitrator under section 1281.6 when the parties fail to agree upon a method for appointment, we conclude that neither the absence of a definite method, nor the presence of “alternative options,” for appointing an arbitrator renders an otherwise valid arbitration agreement unenforceable.

As we find the agreement to arbitrate is valid, and that Defendants demanded arbitration in accordance with the subject arbitration clause, we will reverse the trial court’s order. However, because the trial court did not reach the question of whether any other ground for denying the petition under section 1281.2 applies, we will remand the matter for the trial court to consider this issue.

*1104 FACTUAL SUMMARY

In early 2010, Defendants, husband and wife, approached HMDG about remodeling their home. After discussions regarding the project parameters, HMDG presented Defendants with a three-page “Project Proposal & Agreement” (Agreement).

A clause entitled “Arbitration Clause” located directly above the Agreement’s signature line provides:

“In the event a dispute shall arise between the parties to this contract, it is hereby agreed that the dispute shall be referred to [one of the following choices: (1) designate a specific TJSA&M office or alternate service by agreement of the parties; (2) provide a method of selecting the arbitrator and suits of the hearing, such as from the county wherein the manufacturing plant is located’; or for multi-jurisdictional disputes (3) insert ‘a TJSA&M office to be designated by TJSA&M National Headquarters’] for arbitration in accordance with the applicable United States Arbitration and Mediation Rules of Arbitration. The arbitrator’s decision shall be final and legally binding and judgment may be entered thereon.
“Each party shall be responsible for its share of the arbitration fees in accordance with the applicable Rules of Arbitration. In the event a party fails to proceed with arbitration, unsuccessfully challenges the arbitrator’s award, or fails to comply with the arbitrator’s award, the other party is entitled to costs of suit, including a reasonable attorney’s fee for having to compel arbitration or defend or enforce the award.” 2 (Original brackets & italics.)

After reviewing the Agreement, which was prepared by HMDG, Defendants executed the Agreement without requesting any changes to the Arbitration Clause. Mr. Majd executed the Agreement on behalf of HMDG.

In mid-2011, a dispute arose between HMDG and Defendants regarding the quality of the remodeling work, Defendants’ requests to make substantial changes to the project’s scope, and Defendants’ alleged failure to make prompt progress payments as required by the Agreement. On July 9, 2011, *1105 HMDG made a proposal to resolve the dispute by having Defendants place funds sufficient to complete the remaining project items into an escrow account. Although HMDG’s proposal contained numerous references to arbitration, no formal demand for arbitration was made. When Defendants refused the proposal, HMDG served a 10-day stop work order and recorded a mechanic’s lien on the property.

On December 15, 2011, HMDG filed a complaint against Defendants in the superior court, asserting claims for breach of contract, a common count for money due under the contract, foreclosure of mechanic’s lien, unjust enrichment, and violation of the prompt payment statute—Civil Code former section 3260.1.

On February 21, 2012, Defendants’ counsel, Leo A. Schwarz, sent a letter to counsel for HMDG, James J. Hevener. Mr. Schwarz’s letter reads, in pertinent part:

“Please accept this letter as defendants’ demand that all of the claims raised by plaintiffs in their complaint in the Action, as well as the claims to be made by defendants, be arbitrated per the ‘Arbitration Clause’ found on Page 3 of the June 24, 2010 ‘Project Proposal and Agreement’. As USA&M, one of the designated potential arbitration providers, does not have a presence in Los Angeles County or the State of California, we propose that the parties avail themselves to Option No. 2 of the Arbitration Clause, where a method of selecting the arbitrator is provided. Defendants propose that: (1) the matter be heard by a retired judge with substantial construction and home improvement contract experience; (2) each party select two neutral such judges, with each party allowed to strike one of the other party’s selections; (3) the arbitrator is then randomly selected from the remaining two judges; (4) the California arbitration rules (C.C.P. [§] 1281 et seq.) be adopted as the rules of arbitration; (5) the terms set forth in the second paragraph of the Arbitration Clause remain in effect; and (6) the Action will be stayed pending the Arbitrator’s award, however, defendants’ right to seek expungement of the mechanic’s lien prior to the arbitration hearing shall not be stayed.” (Underscoring omitted.)

The next day, February 22, 2012, Mr. Hevener wrote back to Mr. Schwarz that HMDG found “[the] proposal unreasonable and not required by the Project Proposal and Agreement.” Mr. Hevener’s letter continued: “Please proceed with filing your responsive pleading today. [][] My client remains open to discussing settlement of this dispute including a reasonable process for alternative dispute resolution.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaufman v. Adani CA1/3
California Court of Appeal, 2024
Shruhan v. Apple Inc.
N.D. California, 2024
Pavel Fuks v. Yuri Vanetik
Ninth Circuit, 2024
Sawyer v. KeHE Distributors CA4/2
California Court of Appeal, 2023
Lopez v. Pacific Dental Services CA4/2
California Court of Appeal, 2023
Kwie v. San Jose Water CA6
California Court of Appeal, 2023
Murrey v. Superior Court
California Court of Appeal, 2023
Hill v. Quaid Harley-Davidson CA4/1
California Court of Appeal, 2022
Wong v. Restoration Robotics
California Court of Appeal, 2022
Ehrman v. Post CA2/2
California Court of Appeal, 2022
Nunn v. JPMorgan Chase Bank
California Court of Appeal, 2021
Urchasko v. Compass Airlines CA2/7
California Court of Appeal, 2016

Cite This Page — Counsel Stack

Bluebook (online)
219 Cal. App. 4th 1100, 162 Cal. Rptr. 3d 412, 2013 WL 5299260, 2013 Cal. App. LEXIS 754, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hm-dg-inc-v-amini-and-beizai-calctapp-2013.