Handex of the Carolinas, Inc. v. County of Haywood

607 S.E.2d 25, 168 N.C. App. 1, 2005 N.C. App. LEXIS 148
CourtCourt of Appeals of North Carolina
DecidedJanuary 18, 2005
DocketCOA03-1658
StatusPublished
Cited by26 cases

This text of 607 S.E.2d 25 (Handex of the Carolinas, Inc. v. County of Haywood) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Handex of the Carolinas, Inc. v. County of Haywood, 607 S.E.2d 25, 168 N.C. App. 1, 2005 N.C. App. LEXIS 148 (N.C. Ct. App. 2005).

Opinion

McCullough, Judge.

This appeal arises from the alleged breaches of duties owed by all parties under a contract for the extension of an existing landfill (“the landfill” or “the project”) site in the White Oak section of Haywood County. The extension was to create a new landfill cell, approximately ten acres in surface area, to meet the County’s solid waste disposal needs. Parties to the appeal are: County of Haywood (County), who solicited bids and then was contractually bound for the additional excavation of the landfill; Handex of the Carolinas, Inc. (Handex), who upon submitting the lowest bid was awarded the contract for the project by the County (“the contract”); and Municipal Engineering Services (“MES”), who was contracted by the County to provide a number of engineering services related to the bidding and performance of the project (the “County-MES contract”). Due to a number of problems arising from the performance of the contract, Handex brought suit against MES for professional negligence and breach of contract, and against the County for breach of contract. The County counterclaimed for breach of contract.

The Facts

I. The Bidding Process

The County-MES contract consisted of the following engineering services: providing design services, reviewing and obtaining lump-sum bids, administering contract performance, and reviewing and advising on change orders by the contractor. For the project, MES prepared the contract documents and specifications along with the lump-sum bid advertisement, instructions to bidders, and the bid form. This was made part of the contract. The bids were based on certain specifications, specifically that the site work for the project consisted of “approximately 160,000 cubic yards of spoil, excavation, compaction, tests, waste disposal, berm construction, etc.” The bid form and instructions called for a base bid portion, plus bids on Alternative 1 (utilizing a clay liner) and Alternative 2 (utilizing a synthetic liner). Handex was the low bidder for both alternatives and was awarded the contract for Alternative 1, as notified by letter 14 September 2000. In that letter, MES informed Handex that Notice to Proceed was expected for 21 September 2000, after a Permit to *6 Construct had been issued by North Carolina Waste Section (“NCWS”). MES informed Handex that a preconstruction meeting was required to be held.

II. Notice to Proceed

The preconstruction meeting was held with NCWS in mid-October 2000. The record indicates NCWS had recently modified their requirements, and was then allowing liner systems like that in the County’s advertised bid as Alternative 2. Handex’s bid for Alternative 2 was $8,960.00 less than their bid for Alternative 1. Testimony of the County Manager, Mr. Jack Horton (“Mr. Horton”), asserted that Handex insisted on Alternative 2, and that the contract had to be re-awarded. Mr. Horton testified further that he believed that the County accepted Alternative 2 because “Alternative 2 would actually be a lot quicker and shorten the time of construction as compared to Alternate 1.” Handex’s representative at the preconstruction meeting testified that it was an “open discussion” upon which Alternative 2 was generally decided. Alternative 2 was bid for a total lump-sum price of $2,272,343.61. The County and Handex entered into a written contract for the base bid work and Alternative 2 on or about 13 October 2000. In a letter dated 8 November 2000, MES gave Handex “Notice To Proceed” as of 13 November 2000.

III. Implementation of the Contract

The contract provided Handex 180 days from the Notice to Proceed to achieve Substantial Completion on the landfill, and 45 days from Substantial Completion to be ready for Final Payment. The date of Substantial Completion was to be 12 May 2001 and Final Completion 45 days thereafter. If Handex did not complete within those times, the contract allowed the County to retain $1,000.00 for each day Handex was late in reaching Substantial Completion, and $500.00 for each day until Final Completion. Under the contract, these were to be assessed as liquidated damages should Handex finish late, obligating the County to pay only the difference of monies owed under the contract upon Final Completion. Handex completed the work 93 days beyond the Substantial Completion date, and 10 days beyond Final Completion.

The contract contained three sections: the General Conditions section, the General Specifications section, and the Project Specifications section. The Project Specifications section covers only requirements differing from what appears in the General *7 Specifications section. The contract required that, if Handex desired to make a claim during the course of the project as to one of its terms, or a Change Order for time or money, these claims would be submitted to MES. Section 9.09 of the General Conditions states in pertinent part:

A. ENGINEER will be the initial interpreter of the requirements of the Contract Documents and judge of the acceptability of the Work thereunder. Claims, disputes and other matters relating to the acceptability of the Work, the quantities and classifications of Unit Price Work, the interpretation of the requirements of the Contract Documents pertaining to the performance of the Work, and Claims seeking changes in the Contract Price or Contract Times will be referred initially to ENGINEER in writing, in accordance with the provisions of paragraph 10.05, with a request for a formal decision.
B. When functioning as interpreter and judge under this paragraph 9.09, ENGINEER will not show partiality to OWNER or CONTRACTOR and will not be liable in connection with any interpretation or decision rendered in good faith in such capacity.

Section 10.05 of the General Conditions of the contract provided:

A. Notice: Written notice stating the general nature of each Claim, dispute, or other matter shall be delivered by the claimant to ENGINEER and the other party to the Contract promptly (but in no event later than 30 days) after the start of the event giving rise thereto. Notice of the amount or extent of the Claim, dispute, or other matter with supporting data shall be delivered to the ENGINEER and the other party to the Contract within 60 days after the start of such event.

During the course of the project construction, there were eight attempts made to modify or change the contract terms or specifications. Of these, the County and MES approved only one, and MES recommended another be modified which was denied by the County. Handex appealed each of the seven denials by the County. Additionally, under the terms of the contract, Handex took issue with the delayed start time of the project, additional expenses absorbed by Handex in finishing the project, and timber removal from the project site by the County.

*8 III. Litigation/Judgment/Issues on Appeal

On 21 December 2001, Handex filed a complaint initiating this action against MES for professional negligence and breach of contract and against Haywood for breach of contract. MES filed their answer 8 March 2002.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cranes Creek, LLC v. Neal Smith Eng'g
Court of Appeals of North Carolina, 2023
Designee v. Honda Aircraft
Court of Appeals of Arizona, 2020
Potts v. Kel, LLC
2019 NCBC 60 (North Carolina Business Court, 2019)
Comput. Design & Integration, LLC v. Brown
2018 NCBC 128 (North Carolina Business Court, 2018)
Hamlet H.M.A., LLC v. Hernandez
821 S.E.2d 600 (Court of Appeals of North Carolina, 2018)
Allison v. Brown
Supreme Court of Virginia, 2017
Justus v. Rosner
802 S.E.2d 142 (Court of Appeals of North Carolina, 2017)
Bradley Woodcraft, Inc. v. Bodden
795 S.E.2d 253 (Court of Appeals of North Carolina, 2016)
State v. Stepp
753 S.E.2d 485 (Court of Appeals of North Carolina, 2014)
Russell v. N.C. Department of Environment & Natural Resources
742 S.E.2d 329 (Court of Appeals of North Carolina, 2013)
Pearson v. Gardere Wynne Sewell LLP
814 F. Supp. 2d 592 (M.D. North Carolina, 2011)
KHOMYAK EX REL. KHOMYAK v. Meek
715 S.E.2d 218 (Court of Appeals of North Carolina, 2011)
Jim Lorenz, Inc. v. O'HAIRE
711 S.E.2d 820 (Court of Appeals of North Carolina, 2011)
Kornegay v. Aspen Asset Group, LLC
693 S.E.2d 723 (Court of Appeals of North Carolina, 2010)
McDonnell v. Guilford County Tradewind Airlines, Inc.
670 S.E.2d 302 (Court of Appeals of North Carolina, 2009)
Michael v. Huffman Oil Co., Inc.
661 S.E.2d 1 (Court of Appeals of North Carolina, 2008)
Williamson v. WOODARD FUNERAL HOME, INC.
654 S.E.2d 832 (Court of Appeals of North Carolina, 2008)
Massey v. PRIME INTERNAL MEDICINE, PA
647 S.E.2d 689 (Court of Appeals of North Carolina, 2007)
Schenkel & Shultz, Inc. v. Hermon F. Fox & Associates, P.C.
636 S.E.2d 835 (Court of Appeals of North Carolina, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
607 S.E.2d 25, 168 N.C. App. 1, 2005 N.C. App. LEXIS 148, Counsel Stack Legal Research, https://law.counselstack.com/opinion/handex-of-the-carolinas-inc-v-county-of-haywood-ncctapp-2005.