Walbridge Aldinger LLC v. Cape Fear Engineering, Inc.

CourtDistrict Court, E.D. North Carolina
DecidedJanuary 31, 2022
Docket7:21-cv-00057
StatusUnknown

This text of Walbridge Aldinger LLC v. Cape Fear Engineering, Inc. (Walbridge Aldinger LLC v. Cape Fear Engineering, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Walbridge Aldinger LLC v. Cape Fear Engineering, Inc., (E.D.N.C. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF NORTH CAROLINA SOUTHERN DIVISION

NO. 7:21-CV-57-FL

WALBRIDGE ALDINGER LLC, a Michigan ) Limited Liability Corporation authorized to ) do business in North Carolina, ) ) Plaintiff, ) ) v. ) ) CAPE FEAR ENGINEERING, INC., a North ) Carolina Corporation, ) ORDER ) Defendant/ ) Third-Party Plaintiff, ) v. ) ) BURNS & MCDONNELL ENGINEERING ) COMPANY, INC., ) ) Third-Party Defendant. )

This matter is before the court on third-party defendant’s motion to dismiss (DE 28) the third-party complaint filed by defendant/third-party plaintiff Cape Fear Engineering, Inc. (“defendant”). The motion has been briefed fully, and in this posture the issues raised are ripe for ruling. For the following reasons, the motion is granted in part and denied in part. STATEMENT OF THE CASE Plaintiff Walbridge Aldinger, LLC, (“plaintiff”) commenced this action in Brunswick County Superior Court on February 24, 2021, asserting a breach of contract claim against defendant arising out of defendant’s allegedly deficient surveying work completed as part of a federal construction project at Seymour Johnson Air Force Base (the “project”). Plaintiff seeks actual, contractual, statutory, punitive, or treble damages, plus interest, costs, and fees. Defendant filed a notice of removal on the basis of diversity jurisdiction and an answer, in April 2021. With leave of court, defendant thereafter filed a third-party complaint against third- party defendant, which is an engineering company that allegedly prepared plans for the project

that defendant used to conduct its surveying work under its contract with plaintiff.1 Defendant asserts claims for breach of standard of care (first claim), indemnity and contribution (second claim), and negligence (third claim). Defendant seeks damages, costs, and fees against third-party defendant. As relief, defendant also requests that plaintiff’s claims against defendant be dismissed, and that if plaintiff recovers against defendant, then defendant have and recover against third-party defendant by way of contribution and indemnity. Third-party defendant filed the instant motion to dismiss the third-party complaint pursuant to Federal Rule of Civil Procedure 12(b)(6). Defendant responded in opposition and third-party defendant replied.

STATEMENT OF THE FACTS The facts alleged in the complaint and the third-party complaint may be summarized as follows. The court provides a summary of the facts alleged in the complaint for background purposes only as pertinent to the instant motion. A. Complaint Plaintiff is a Michigan company that provides general contracting services on construction projects. Defendant is a North Carolina company that provides surveying services. The project at

1 In the meantime, the court entered a case management order setting a May 23, 2022, deadline for discovery and a July 22, 2022, deadline for dispositive motions. Seymour Johnson Air Force Base, involved the construction of a “Two Bay Corrosion/Fuel Cell Hanger.” (Compl. Ex. 1 (DE 1-1) at 13). On December 7, 2017, plaintiff and defendant entered into a “Consulting Subcontract” under which defendant agreed to provide “Surveying work for [the] project” (the “surveying contract”). (Compl. ¶¶ 11-12). The scope of work for the surveying contract included the

following work: Piling staking a. Stake the Test piles for the hanger 60-penny nails and numbered pin flags during 1 mobilization b. Stake the production piles for the hanger using 60-pennynails and numbered pin flags during 2 mobilizations c. Provide a post cut-off pile as-built, showing the location and elevation of each pile for use by others during 3 mobilizations d. Anchor bolt checks/verification during 4 mobilizations. (Id. ¶ 12). The surveying contract allegedly incorporated “Contract Documents” that included a “Structural Plan S001 General Notes at 1.G.,” providing: “ELEVATION 100’-0” CORRESPONDS TO MSL ELEVATION 103.50.” (Id. ¶ 13). According to the complaint, the surveying contract required defendant “to know the correct elevation to use to complete its work” in accordance with the surveying contract. (Id. ¶ 18). Defendant “began on-site surveying pile layout work on May 17, 2018.” (Id. ¶ 21). Defendant allegedly “was required to place pins at the design location for each pile to be drilled in accordance with the contractors [sic] sequence.” (Id. ¶ 22). “Each pin was to include a flag listing the pile number, the existing elevation of the pin at mean sea level, and the design pile cut off elevation.” (Id. ¶ 23). Defendant allegedly “placed pins with flags that contained the incorrect elevations at the design locations for 189 of 535 piles.” (Id. ¶ 24). “[O]f the 189 piles impacted by [defendant’s alleged] error in surveying and noting of the elevations, approximately 160 piles were installed at the incorrect elevation.” (Id. ¶ 25). Defendant allegedly “failed to adjust the elevations in performing its surveying to account for the Structural Plan S001 General Note l.G. which provided ‘ELEVATION 100’-0” CORRESPONDS TO MSL ELEVATION 103.50.’” (Id. ¶ 26).

According to the complaint, defendant’s “surveying elevations were determined using the structural elevation of l00’-0” instead of converting the structural elevation to MSL elevation of 103.50” [sic].” (Id. ¶ 27). Defendant’s alleged “failure to use the correct elevation resulted in the surveying for 189 piles using an elevation that was 3.5” too low.” (Id. ¶ 28). Plaintiff allegedly notified defendant in writing on July 24, 2018, “of the incorrect pile cutoff elevations.” (Id. ¶ 29). According to the complaint, “incorrectly surveyed and installed piles had to be redesigned and required the use of 71 tons of rebar, 350 cubic yards of concrete, and 5,024 cubic yards of additional back fill which doubled the original contract scope for the impacted areas.” (Id. ¶ 30). “To correct the incorrectly surveyed and installed piles exposed

excavation and dewatering was required throughout the process.” (Id. ¶ 31). “The critical path for the project [allegedly] was impacted by [defendant’s] incorrectly surveyed and installed piles.” (Id. ¶ 32). “The impact on the critical path increased the project general conditions by at least [$3,300.00] each day.” (Id. ¶ 33). According to the complaint, defendant breached the surveying contract by “failing to use the degree of care and skill ordinarily exercised by surveyors by failing to account for the correct elevation for mean sea level,” “failing to be aware of Structural Plan S001 General Note 1.G,” “failing to complete its work in accordance with” the surveying contract, and in other ways which may be discovered. (Id. ¶¶ 36-40). As a result of defendant’s asserted breaches of the surveying contract, plaintiff suffered economic damages in excess of $25,000.00, “including but not limited to the cost to remediate the erroneous elevations for at least 160 piles, increased daily costs of construction, liquidated damages from the owner of the project, and delay claims from other subcontractors,” and plaintiff “has suffered and continues to suffer monetary losses.” (Id. ¶¶ 41, 42).

B. Third-Party Complaint According to the third-party complaint, defendant was engaged in providing surveying and consulting work on construction projects within North Carolina. Third-party defendant was an engineering company engaged in providing and preparing design plans and drawings for use on construction projects. Plaintiff and defendant entered into the surveying contract, under which defendant was to provide surveying work. “The plans that [defendant] used were prepared by” third-party defendant (hereinafter, the “plans”). (Third-Party Compl. ¶ 12).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
American Export Lines, Inc. v. John Revel
262 F.2d 122 (Fourth Circuit, 1958)
Nemet Chevrolet, Ltd. v. Consumeraffairs. Com, Inc.
591 F.3d 250 (Fourth Circuit, 2009)
Clemmons v. King
143 S.E.2d 83 (Supreme Court of North Carolina, 1965)
Schenkel & Shultz, Inc. v. Hermon F. Fox & Associates, P.C.
636 S.E.2d 835 (Court of Appeals of North Carolina, 2006)
Davidson & Jones, Inc. v. County of New Hanover
255 S.E.2d 580 (Court of Appeals of North Carolina, 1979)
Pinnix v. Toomey
87 S.E.2d 893 (Supreme Court of North Carolina, 1955)
Jonesboro United Methodist Church v. Mullins-Sherman Architects, L.L.P.
614 S.E.2d 268 (Supreme Court of North Carolina, 2005)
Hunsucker v. High Point Bending & Chair Co.
75 S.E.2d 768 (Supreme Court of North Carolina, 1953)
Schenkel & Shultz, Inc. v. Hermon F. Fox & Associates
658 S.E.2d 918 (Supreme Court of North Carolina, 2008)
Handex of the Carolinas, Inc. v. County of Haywood
607 S.E.2d 25 (Court of Appeals of North Carolina, 2005)
Fussell v. North Carolina Farm Bureau Mutual Insurance
695 S.E.2d 437 (Supreme Court of North Carolina, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Walbridge Aldinger LLC v. Cape Fear Engineering, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/walbridge-aldinger-llc-v-cape-fear-engineering-inc-nced-2022.