Schenkel & Shultz, Inc. v. Hermon F. Fox & Associates

658 S.E.2d 918, 362 N.C. 269
CourtSupreme Court of North Carolina
DecidedApril 11, 2008
Docket631A06
StatusPublished
Cited by85 cases

This text of 658 S.E.2d 918 (Schenkel & Shultz, Inc. v. Hermon F. Fox & Associates) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Schenkel & Shultz, Inc. v. Hermon F. Fox & Associates, 658 S.E.2d 918, 362 N.C. 269 (N.C. 2008).

Opinion

TIMMONS-GOODSON, Justice.

We must determine in the present case whether the parties intended in their subcontract to incorporate by reference the terms of an express indemnification provision found in the primary contract. Because we conclude there exist genuine issues of material fact regarding the parties’ intent to indemnify, summary judgment was inappropriate. We therefore affirm the decision of the Court of Appeals.

I. Background

On 24 November 1998, the Charlotte-Mecklenburg Board of Education (Board) contracted with the architectural firm of Schenkel & Shultz, Inc. (Schenkel) to design a vocational technical high school in Mecklenburg County. The “Standard Form of Agreement Between Owner and Designer” (Prime Agreement) signed by the Board and Schenkel provided that Schenkel would retain outside consultants or engineers to perform those aspects of the project for which it did not have in-house expertise. The Prime Agreement includes the following indemnification provision:

12.4 In the event a claim, suit, or cause of action is made against the Owner [the Board] and/or Owner’s representatives for any personal injury, including death, or property damage (other than to the work its ell), or other loss or damage resulting solely from any negligent act or omission of the Designer [Schenkel] or out of the Designer’s breach of this Agreement, the Designer agrees to defend and hold the Owner, its agents, employees, servants, representatives, successors and assigns harmless and indemnified from and against any loss, costs, damages, expenses, attorneys fees and liability with respect to such claim, suit, or cause of action.

Schenkel in turn hired Hermon F. Fox & Associates, PC. (Fox), an engineering firm, to create the project’s structural steel design. The form contract between Schenkel and Fox was produced by The American Institute of Architects and titled “Standard Form of

*271 Agreement Between Architect and Consultant” (AIA Document C141 6th ed. 1987) (Subprime Agreement). Article 1 of the Subprime Agreement, “Consultant’s Responsibilities,” Section 1 describes the services to be performed by Fox under the Subprime Agreement. Section 1.1.2 provides that:

Consultant’s [Fox’s] services shall be performed according to this Agreement with the Architect [Schenkel] in the same manner and to the same extent that the Architect is bound by the attached Prime Agreement to perform such services for the Owner [the Board]. Except as set forth herein, the Consultant [Fox] shall not have any duties or responsibilities for any other part of the Project.

Construction began in the fall of 2000, but by the spring of 2001, project contractors, subcontractors, and consultants documented in correspondence with Schenkel their concerns regarding the integrity of the structural steel components of the project and requested that an independent assessment of the steel design be performed. The alleged steel design defects delayed the project, resulting in cost overruns. On 2 January 2002, the Board formally notified Schenkel of the design flaw allegations and cost overruns, as well as its potential claim against Schenkel for the cost of steel structure corrective work and associated delay costs. Schenkel then notified Fox of its intention to hold Fox responsible for any claim filed by the Board. Subsequent attempts by the parties to resolve the matter out of court were unsuccessful.

On 1 October 2004, Schenkel filed suit in Mecklenburg County against Fox, asserting claims for negligence, professional malpractice, breach of contract, breach of warranty, and indemnity for alleged errors in the project’s structural steel design. Fox made a pretrial motion for judgment on the pleadings, which the trial court converted to a motion for partial summary judgment. The trial court granted the motion by Fox and dismissed with prejudice, on statute of limitations grounds, the claims for negligence, professional malpractice, breach of contract, and breach of warranty brought by Schenkel. The trial court also granted subsequent motions by Fox for summary judgment on Schenkel’s indemnification claim and on a counterclaim by Fox against Schenkel for breach of contract. The trial court awarded Fox $37,787.50 on its counterclaim. Schenkel appealed from both the trial court’s entry of partial summary judgment and the summary judgments dismissing the indemnification claim and granting Fox’s counterclaim for breach of contract.

*272 The North Carolina Court of Appeals heard the case on 22 August 2006. The Court of Appeals affirmed the trial court’s entry of partial summary judgment for Fox on Schenkel’s claims of negligence, professional malpractice, breach of contract, and breach of warranty. Schenkel & Shultz, Inc. v. Hermon F. Fox & Assocs., P.C., 180 N.C. App. 257, 259, 636 S.E.2d 835, 838 (2006). The Court of Appeals reversed the trial court’s order granting summary judgment in favor of Fox on its counterclaim for breach of contract. Id. In a divided opinion, a majority of the Court of Appeals also reversed the trial court’s order granting summary judgment in favor of Fox on Schenkel’s claim for indemnification, concluding that there existed genuine issues of material fact as to whether the contract expressly provided for a right to indemnification. Id. The dissenting judge concluded that Fox did not expressly agree to indemnify Schenkel. 180 N.C. App. at 274, 636 S.E.2d at 846 (Tyson, J., dissenting). Alternatively, the dissent concluded that summary judgment was appropriate because Schenkel failed to timely designate an expert pursuant to the trial scheduling order and was therefore precluded from offering expert testimony on the standard of care applicable to Fox’s work as structural steel designers, which in turn would prevent Schenkel from establishing the underlying negligence or breach of contract the indemnity provision required. Id. at 272, 636 S.E.2d at 845. Fox appealed to this Court on the basis of the dissent.

II. Analysis

In reviewing an appeal based upon a dissent, we consider only those issues that were a point of dispute set out in the dissenting opinion of the Court of Appeals. See N.C. R. App. P. 16(b) (“Where the sole ground of the appeal of right is the existence of a dissent in the Court of Appeals, review by the Supreme Court is limited to a consideration of those questions which are [] specifically set out in the dissenting opinion as the basis for that dissent. . . .”).

The central issue in dispute here is whether Fox agreed to indemnify Schenkel in the Subprime Agreement. The Prime Agreement between Schenkel and the Board expressly provides for indemnification against loss arising from negligence or breach of contract. The Subprime Agreement between Fox and Schenkel requires Fox to perform its services “in the same manner and to the same extent that [Schenkel) is bound by the attached Prime Agreement to perform such services for [the Board].” Fox contends this language merely requires it to perform its services in the same manner and to the same *273

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yoder v. Verm
2025 NCBC 22 (North Carolina Business Court, 2025)
Jackson v. Mh Master Holdings, Lllp
2025 NCBC 21 (North Carolina Business Court, 2025)
Dane v. Commonwealth Partners LLC
E.D. North Carolina, 2025
Mirkin v. XOOM Energy, LLC
E.D. New York, 2023
McGriff Ins. Servs., Inc. v. Hudson
2023 NCBC 3 (North Carolina Business Court, 2023)
McClure v. Ghost Town in the Sky, LLC
2022 NCBC 78 (North Carolina Business Court, 2022)
Golden Triangle 3, LLC v. Rmp-Mallard Pointe, LLC
2022 NCBC 43 (North Carolina Business Court, 2022)
Aspen Specialty Ins. Co. v. Nucor Corp.
2022 NCBC 19 (North Carolina Business Court, 2022)
Galloway v. Snell
Court of Appeals of North Carolina, 2022
Emrich Enters., LLC v. Hornwood, Inc.
2022 NCBC 11 (North Carolina Business Court, 2022)
Banc of Am. Merch. Servs., LLC v. Arby's Rest. Grp., Inc.
2021 NCBC 41 (North Carolina Business Court, 2021)
Dodge v. Appalachian Energy, LLC
2021 NCBC 33 (North Carolina Business Court, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
658 S.E.2d 918, 362 N.C. 269, Counsel Stack Legal Research, https://law.counselstack.com/opinion/schenkel-shultz-inc-v-hermon-f-fox-associates-nc-2008.