Jonesboro United Methodist Church v. Mullins-Sherman Architects, L.L.P.

614 S.E.2d 268, 359 N.C. 593, 2005 N.C. LEXIS 643
CourtSupreme Court of North Carolina
DecidedJuly 1, 2005
Docket170PA04
StatusPublished
Cited by9 cases

This text of 614 S.E.2d 268 (Jonesboro United Methodist Church v. Mullins-Sherman Architects, L.L.P.) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jonesboro United Methodist Church v. Mullins-Sherman Architects, L.L.P., 614 S.E.2d 268, 359 N.C. 593, 2005 N.C. LEXIS 643 (N.C. 2005).

Opinion

MARTIN, Justice.

On 4 October 1999, defendant J.H. Batten, Inc. (Batten) entered into a contract (the construction contract) with plaintiff Jonesboro United Methodist Church (JUMC) whereby Batten agreed to act as general contractor for the construction of a Fellowship Hall addition on real property owned by JUMC in Sanford, North Carolina. According to allegations in JUMC’s complaint, JUMC had concerns about Batten’s workmanship throughout the construction project. Instances of Batten’s allegedly poor workmanship included problems relating to the alignment and ventilation of the roof, the puckering of roof shingles, defects in the mortar joints and masonry work, mislocated purlins, missing insulation, and other matters. During and after construction, disputes arose between JUMC and Batten concerning *595 both parties’ respective performances under the contract. The disputes centered around the balance owed for work performed, the completion of punch list items, and whether Batten was required to perform additional work under the terms of the contract or in satisfaction of warranties. The parties entered mediation in an effort to resolve these disputes.

On 6 August 2001, representatives of JUMC sent Batten a letter by facsimile transmission confirming a prior telephone agreement in which JUMC agreed to pay $101,000.00 to “satisfy the construction relationship” between JUMC and Batten. The letter thanked Batten for its “willingness to help us settle this today” and invited Batten to indicate its approval of the settlement agreement by signing and returning the letter by facsimile transmission. That same day, Batten’s managing agent, Harold Batten, signed the letter and returned it as requested to JUMC. At the bottom of the page, Batten wrote, “I agree that this is a complete settlement between [Batten] and [JUMC].”

On 14 August 2001, JUMC sent Batten another letter by facsimile transmission. The second letter stated that upon further review, JUMC “disagree[d] on the amount of payment outstanding.” On this basis, the letter purported to “rescind[]” the 6 August 2001 settlement offer.

After JUMC refused to pay the amount specified in the 6 August 2001 letter, Batten filed suit in Forsyth County Superior Court on 16 August 2001, seeking $101,000.00 in damages in satisfaction of the settlement agreement. In the event the trial court determined there was not a binding settlement agreement, Batten sought a declaratory judgment “to declare the relative rights and obligations between the parties pursuant to the Contract.” In its answer, JUMC denied that a binding settlement existed and moved to dismiss, to change venue, and to stay the proceeding pending arbitration. JUMC further asserted numerous affirmative defenses, including unclean hands, anticipatory breach, and estoppel based on Batten’s alleged failure to perform under the contract. JUMC did not file any counterclaims in the action. After some discovery, Batten filed a motion for summary judgment, which the trial court allowed on 6 February 2002.

JUMC appealed, and the Court of Appeals affirmed in an unpublished opinion filed 17 June 2003. The Court of Appeals concluded that the parties had entered a binding settlement contract and that no genuine issues of material fact remained to be litigated. JUMC filed a *596 petition for discretionary review, which this Court denied on 21 August 2003. J.H. Batten, Inc. v. Jonesboro United Methodist Church, 357 N.C. 460, 585 S.E.2d 765 (2003).

On 23 April 2002, less than three months after the trial court entered summary judgment in Batten’s favor in the Forsyth County litigation, JUMC filed a complaint in Lee County. The complaint stated three claims against Batten: breach of contract, breach of express and implied warranty, and “Negligence/Malpractice.” Batten filed its answer on 7 June 2002. On 3 July 2002 and 30 July 2002, Batten filed motions for judgment on the pleadings, which asked the trial court to dismiss JUMC’s claims against Batten because those claims “ar[o]se from the same transaction or occurrence that was the subject of litigation between the parties in Forsyth County.” The trial court denied the motions on 30 August 2002, and Batten appealed. The Court of Appeals affirmed in an unpublished opinion. We reverse.

Rule 13(a) of the North Carolina Rules of Civil Procedure designates certain claims as “compulsory counterclaims” that must be raised in responsive pleadings. Specifically, Rule 13(a) provides that

[a] pleading shall state as a counterclaim any claim which at the time of serving the pleading the pleader has against any opposing party, if it arises out of the transaction or occurrence that is the subject matter of the opposing party’s claim and does not require for its adjudication the presence of third parties of whom the court cannot acquire jurisdiction.

N.C.G.S. § 1A-1, N.C. R. Civ. P. 13(a) (2003). A claim is not a compulsory counterclaim, however, if

(1) At the time the action was commenced the claim was the subject of another pending action, or
(2) The opposing party brought suit upon his claim by attachment or other process by which the court did not acquire jurisdiction to render a personal judgment on that claim, and the pleader is not stating any counterclaim under this rule.

Id.; see also N.C. R. Civ. P. 13(a) cmt.

As we have previously noted, the ultimate effect of a pleader’s failure to assert a compulsory counterclaim is not set forth in the rule itself. See Gardner v. Gardner, 294 N.C. 172, 176, 240 S.E.2d 399, 403 (1978). “Courts have, however, consistently held that a party who does not plead a compulsory counterclaim is, after determination of *597 the action in which it should have been pleaded, forever barred from bringing a later independent action on that claim.” Id. at 179, 240 S.E.2d at 404. This preclusive effect is necessary to effectuate the purpose of Rule 13(a), which “is to enable one court to resolve ‘all related claims in one action, thereby avoiding a wasteful multiplicity of litigation.’ ” Id. at 176-77, 240 S.E.2d at 403 (quoting 6 Charles Alan Wright & Arthur R. Miller, Federal Practice and Procedure § 1409, at 37 (1971)); see also Kemp v. Spivey, 166 N.C. App. 456, 458, 602 S.E.2d 686, 688 (2004); Winston-Salem Joint Venture v. Cathy’s Boutique, Inc., 72 N.C. App. 673, 675, 325 S.E.2d 286, 287 (1985); Twin City Apartments, Inc. v. Landrum, 45 N.C. App. 490, 494, 263 S.E.2d 323, 325 (1980). To permit a party who failed to assert a compulsory counterclaim to raise that claim in a later action undermines the “salutary procedural principle that litigation once precipitated ought to be concentrated insofar as practicable in one forum,” thereby “ ‘destroying] the effectiveness of Rule 13(a).’ ” Gardner, 294 N.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Britcher v. Assurance Grp., LLC
North Carolina Business Court, 2026
J. S. & Assocs., Inc. v. Stevenson
828 S.E.2d 183 (Court of Appeals of North Carolina, 2019)
Taylor v. Norfolk Southern Railway Co.
86 F. Supp. 3d 448 (M.D. North Carolina, 2015)
Steele v. Bowden
Court of Appeals of North Carolina, 2014
Holloway v. Holloway
726 S.E.2d 198 (Court of Appeals of North Carolina, 2012)
Julian v. Wells Fargo Bank, N.A.
2012 NCBC 30 (North Carolina Business Court, 2012)
Townsend v. Shook
708 S.E.2d 187 (Court of Appeals of North Carolina, 2011)
Hendrix v. ADVANCED METAL CORP.
672 S.E.2d 745 (Court of Appeals of North Carolina, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
614 S.E.2d 268, 359 N.C. 593, 2005 N.C. LEXIS 643, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jonesboro-united-methodist-church-v-mullins-sherman-architects-llp-nc-2005.