Gulf Power Company v. Federal Energy Regulatory Commission, Florida Public Utilities Company, Intervenor

983 F.2d 1095, 299 U.S. App. D.C. 281, 1993 U.S. App. LEXIS 986
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 22, 1993
Docket91-1354
StatusPublished
Cited by15 cases

This text of 983 F.2d 1095 (Gulf Power Company v. Federal Energy Regulatory Commission, Florida Public Utilities Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gulf Power Company v. Federal Energy Regulatory Commission, Florida Public Utilities Company, Intervenor, 983 F.2d 1095, 299 U.S. App. D.C. 281, 1993 U.S. App. LEXIS 986 (D.C. Cir. 1993).

Opinion

Opinion for the court filed by Circuit Judge KAREN LeCRAFT HENDERSON.

KAREN LeCRAFT HENDERSON, Circuit Judge:

I. Statutory Background

Under the Federal Power Act (FPA or Act), 16 U.S.C. §§ 824 et seq., a utility subject to the jurisdiction of the Federal Energy Regulatory Commission (FERC) must file with FERC a schedule of the rates it intends to charge its customers. 16 U.S.C. § 824d(c), (d). FERC reviews the rates to ensure that they are “just and reasonable”; the Act makes any rates that fall short of the just and reasonable standard unlawful. 16 U.S.C. § 824d(a).

When a utility wishes to change the rates it charges its customers, it must provide FERC with 60 days notice and file new rate schedules. 16 U.S.C. § 824d(d). Under the statute, FERC may waive the notice requirement for good cause. Id. Ordinarily, however, upon receiving the proposed schedules, the Commission decides whether to hold hearings to determine the reasonableness of the new rates and it may suspend the imposition of the rates for as long as five months while it decides on their reasonableness. 16 U.S.C. § 824d(e).

In order to give a utility the flexibility to respond efficiently to market fluctuations in costs, the statute allows it to include automatic adjustment clauses in its rate schedules to provide for “increases or decreases (or both), without prior hearing, in rates reflecting increases or decreases (or both) in costs incurred by an electric utility.” 16 U.S.C. § 824d(f)(4). Under this provision, FERC countenances a utility's practice of including fuel adjustment clauses (FACs) in its rate schedules to allow it to adjust the rates automatically for the changing costs of fuel. See 18 C.F.R. § 35.14.

FERC permits a utility to include, as part of the FAC, the costs of “[fjossil ... fuel consumed in the utility’s own plants.” 18 C.F.R. § 35.14(a)(2). These costs, however, “shall include no items other than those listed in Account 151_” 18 C.F.R. § 35.-14(a)(6). Account 151 limits allowable fuel costs, in part, to “excise taxes, purchasing agents’ commissions, insurance and other *1097 expenses directly assignable to the cost of fuel.” Account 151, 18 C.F.R. Part 101. Because, as it has recognized, FERC maintains less regulatory vigilance over the automatic adjustment clauses, it interprets narrowly the scope of costs a utility may include in the FAC. See, e.g., Southern California Edison Co., 3 Fed.Energy Reg. Comm’n (CCH) ¶ 61,075 (1978); Electric Cooperatives of Kansas, 14 Fed.Energy Reg.Comm’n (CCH) ¶ 61,176 (1981); Kansas City Power & Light Co., 42 Fed.Energy Reg.Comm’n (CCH) ¶ 61,249 (1988). It may, however, in its discretion, waive any of the regulations pertaining to the fuel adjustment clause. 18 C.F.R. § 35.19a.

II. Procedural Background

In 1986, as a result of a changing fuel market, Gulf Power Company (Gulf) was a party to a series of expensive long term coal purchasing contracts. Instead of continuing to purchase high priced coal and passing the cost on to its customers, Gulf voluntarily renegotiated the contracts from late 1986 to early 1988. The renegotiations resulted in Gulf agreeing to pay approximately $250 million in buyout costs to its coal suppliers and entering into new contracts projected to save Gulf approximately $600 million in coal costs over the life of the contracts.

On January 1, 1987, after effecting its first buyout, Gulf began passing the savings on to consumers by reducing the cost of coal in its FAC. At the same time, Gulf also began passing through to its customers the amortized cost of the buyout. Gulf believed it could pass this cost on to customers because the buyout expenses constituted “other expenses directly assignable to the cost of fuel” under Account 151. See Account 151, 18 C.F.R. Part 101. Although Gulf’s customers paid the buyout costs, the overall cost of fuel was still cheaper than before the buyout occurred; for Gulf’s wholesale customers, the net savings from the buyout were estimated at $4.3 million over the life of the contracts.

Other utilities also engaged in this buyout strategy in the 1980s. Mississippi Power Company, an affiliate of Gulf, 1 participated in some of the same buyouts at issue in this case. While performing a routine audit of Mississippi Power in August 1987, FERC informed that utility that it needed a waiver to pass buyout costs through the FAC because those costs were not included in Account 151. Mississippi Power applied for such a waiver in September 1987. The Commission granted Mississippi’s application and sua sponte made the waiver retroactive to January 1, 1987. Mississippi Power, 41 Fed.Energy Reg.Comm’n (CCH) 11 61,004 (1987).

In December 1988, FERC issued an order declaring that buyout costs fell outside the scope of Account 151 and thus could not be automatically included in the fuel adjustment clause. Kentucky Utilities, 45 Fed.Energy Reg.Comm’n (CCH) 1161,409 (1988). Nonetheless, in Kentucky Utilities FERC indicated that it would grant a waiver from the FAC regulations and allow the pass through of buyout costs if the utility could demonstrate that the buyout provided “ongoing benefits” to its customers. Id. at 62,293.

In the spring of 1989, as the result of another routine audit, FERC discovered that Gulf had been passing through buyout costs for over two years. FERC then notified Gulf that it had to seek a waiver of notice and fuel adjustment clause requirements. Before filing for a waiver, Gulf obtained from all of its wholesale customers written consent to the pass through of the buyout costs. Gulf then filed a waiver request identical to the one Mississippi Power had filed two years earlier. The Commission rejected Gulf’s waiver request because Gulf did not show that its buyout plan satisfied the ongoing benefits test of Kentucky Utilities. FERC letter of October 4, 1989 to Gulf, Gulf App. at 291.

In July 1990, Gulf filed a second waiver request in which it demonstrated compliance with

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Texas v. EPA
Fifth Circuit, 2024
Sierra Club v. EPA
939 F.3d 649 (Fifth Circuit, 2019)
Morall v. Drug Enforcement Administration
412 F.3d 165 (D.C. Circuit, 2005)
Metro-Goldwyn-Mayer Studios, Inc. v. Peters
309 F. Supp. 2d 48 (District of Columbia, 2004)
LA Pub Svc Cmsn v. FERC
174 F.3d 218 (D.C. Circuit, 1999)
Sierra Club v. U.S. Army Corps of Engineers
935 F. Supp. 1556 (S.D. Alabama, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
983 F.2d 1095, 299 U.S. App. D.C. 281, 1993 U.S. App. LEXIS 986, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gulf-power-company-v-federal-energy-regulatory-commission-florida-public-cadc-1993.