Southern California Water Co. v. Federal Energy Regulatory Commission

433 F.3d 840, 369 U.S. App. D.C. 73, 2005 U.S. App. LEXIS 28988, 2005 WL 3555846
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 30, 2005
Docket04-1324
StatusPublished

This text of 433 F.3d 840 (Southern California Water Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern California Water Co. v. Federal Energy Regulatory Commission, 433 F.3d 840, 369 U.S. App. D.C. 73, 2005 U.S. App. LEXIS 28988, 2005 WL 3555846 (D.C. Cir. 2005).

Opinion

Opinion for the Court filed by Senior Circuit Judge WILLIAMS.

STEPHEN F. WILLIAMS, Senior Circuit Judge.

Southern California Water Company, a public utility that distributes electricity to retail customers in San Bernardino County, California, challenges two orders of the Federal Energy Regulatory Commission. It contends that the Commission misapplied the concept of “incremental cost” as used in the Western System Power Pool (‘WSPP”) Agreement; as a result, Southern California says, FERC incorrectly found that a sale of electricity by Southern California violated statutory filing requirements for the making of jurisdictional sales. See Federal Power Act, § 201, 16 U.S.C. § 824. Because the Commission failed to explain its interpretation of incremental cost adequately, we reverse and remand.

Hi H* H* # H* Hí

At the beginning of March 2001, Southern California was committed to buying electricity for its retail customers in two wholesale contracts: (1) a baseload contract with Dynegy Power Marketing for 12 megawatts (“MW”) of around-the-clock energy at $35.50 per megawatt-hour (“MWh”), and (2) a contract with Illinova Energy Partners (“IEP”) to meet any hourly demand in excess of 12 MW at “SP15,” a name given the spot market price in the “South of Path 15” zone, a common delivery point. (Dynegy later assumed IEP’s obligations, but for ease in distinguishing between the baseload and the spot-price contracts we refer to this as the IEP contract.) As the Dynegy contract was scheduled to expire on April 30, 2001, Southern California entered into a contract with Mirant Americas Energy Marketing on March 16 to purchase 15 MW of around-the-clock energy at a price of $95/MWh. The contract was under the WSPP Agreement, which the parties identified as the “enabling agreement.”

For reasons not entirely clear, the Mir-ant baseload contract was to start April 1, 2001, and thus overlapped with the Dynegy baseload contract for the month of April. To address this overlap, Southern California entered into a separate contract with Mirant on March 30, 2001, again under the WSPP Agreement, agreeing this time to sell Mirant 15 MW of around-the-clock energy for the month of April at a price of SP15 minus $20/MWh. Although the overlap of baseload contracts obviously occasioned Southern California’s interest in making such a sale, the one-month contract was not formally tied to or contingent on the Mirant baseload contract. In the immediate run-up to the March 30 contract, the SP15 price fluctuated between a peak high of about $280 and an off-peak low of about $80. These were historically high prices; March 2001 fell in the midst of California’s well-known electricity crisis.

At the time of the April 2001 sale, Southern California had no authority to sell energy at market-based prices. In July 2002, in a move unrelated to the April sale, it applied to the Commission for such authority. Mirant intervened, seeking a refund and contending that the April 2001 sale was itself at market-based rates. The Commission granted Southern California *842 the requested authority prospectively, Southern California Water Co., 100 FERC ¶ 61,373 (2002), but simultaneously initiated an inquiry into the April 2001 sale.

Southern California defended the sale on the ground that the rates were not “market-based” but cost-based, as they fell (it argued) within the WSPP Agreement’s cost-based limit — its provision that prices must not “exceed the Seller’s forecasted Incremental Cost” plus a so-called “adder.” It argued that the relevant incremental cost was SP15, the price that it would pay IEP for the last unit needed to meet the obligation to Mirant whenever its total sales commitments (i.e., the sum of (1) its retail customers’ demand, which typically ran between 12 and 17 MW, with occasional deviations in both directions, see Joint Appendix (“J.A.”) 310-23, and (2) the 15 MW needed for the April 2001 sale to Mirant) exceeded the 27 MW that it could count on from its baseload contracts with Dynegy and Mirant.

The Commission rejected this defense, classified the sale as having been at market-based rates and therefore unauthorized, and ordered a refund of the difference between the revenue collected under the contract and $95/MWh (the price under Southern California’s baseload contract with Mirant), plus interest. See 106 FERC ¶ 61,305 (2004) (“Compliance Order”), order on reh’g, 108 FERC ¶ 61,168 (2004) (“Rehearing Order”). In denying rehearing the Commission explained its rejection of the argument that SP15 equaled “incremental cost” under the WSPP Agreement, saying that SP15 “would only be [Southern California’s] incremental cost once the sale to Mirant is consummated,” Rehearing Order, 108 FERC at P 14, p. 62,022 (emphasis added). In addition, the Commission relied on the arguments that Southern California “simply resold” to Mirant the same energy that it bought, 106 FERC at P 17, p. 62,198, and that the incremental cost could not have been SP15 because SP15 exceeded its sale price of SP15 minus $20/MWh, 108 FERC at P 14, p. 62,022.

In a later order the Commission reduced the refund by the amount of an “adder,” which the WSPP Agreement allowed in excess of incremental costs for all sales under the Agreement that were not at market-based rates. The Commission explained that it now understood that the Agreement permitted sellers to charge the adder on top of the forecasted incremental cost, because the Agreement made “no distinction between owned resources and purchase contracts.” Southern California Water Company, 109 FERC ¶ 61,121 at P 12, p. 61,504 (2004).

Southern California challenges the Compliance Order and the Rehearing Order as being arbitrary and capricious, 5 U.S.C. § 706(2)(A), and as unsupported by substantial evidence, 16 U.S.C. § 825Z (b).

******

The crux of the case is whether the Commission coherently explained its conclusion that the price of Southern California’s April sale to Mirant exceeded the cost-based ceiling established by the WSPP Agreement-Southern California’s “forecasted Incremental Cost.” The Agreement defines that term as “[t]he forecasted expense incurred by the Seller in providing an additional increment of energy or capacity during a given hour.” Western Systems Power Pool Agreement § 4.9, J.A. 219.

The Commission’s prior orders have shed little interpretive light on the phrase. In initially approving the Agreement, the Commission said that “the seller’s incremental cost for setting ceiling prices should be forecasted at the time of specific transactions under an agreement to reflect the actual cost with greater certainty” and that “incremental cost may be forecasted hourly, weekly, or monthly,” Western Sys *843 terns Power Pool, 55 FERC ¶ 61,099 (1991) (“Western Systems Power Pool I ”), order on reh’g, 55 FERC ¶ 61,495 at 62,718 (1991) (“Western Systems Power Pool II”), aff'd sub nom., Environmental Action v. FERC,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
433 F.3d 840, 369 U.S. App. D.C. 73, 2005 U.S. App. LEXIS 28988, 2005 WL 3555846, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-california-water-co-v-federal-energy-regulatory-commission-cadc-2005.