Guaranteed Gravel & Sand Co. v. Aetna Casualty & Surety Co.

219 N.W. 546, 174 Minn. 366, 1928 Minn. LEXIS 1154
CourtSupreme Court of Minnesota
DecidedMay 4, 1928
DocketNos. 26,662, 26,657, 26,658, 26,659, 26,660, 26,661, 26,663, 26,664.
StatusPublished
Cited by13 cases

This text of 219 N.W. 546 (Guaranteed Gravel & Sand Co. v. Aetna Casualty & Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Guaranteed Gravel & Sand Co. v. Aetna Casualty & Surety Co., 219 N.W. 546, 174 Minn. 366, 1928 Minn. LEXIS 1154 (Mich. 1928).

Opinion

*368 Wilson, C. J.

There are eight appeals from judgments against appellant in eight separate actions which have been consolidated in this court. With two exceptions, which will be mentioned, the cases are controlled by the same record.

In 1923 the high school building in Waseca was destroyed by fire. On October 30, 1923, the board made a contract with Oarlsted Brothers for the construction of a new schoolhouse at the price of $251,993. As surety to a public contractor within G-. S. 1923, § 9700, appellant became a third party to the contract.

The contract required the work to be completed on January 1, 1925. Subsequently the board agreed to pay $1,000 additional if classes could be held in the new building on October 1, 1921. This was done.

All the plaintiffs, except the Builders Mutual Casualty Company, which furnished workmen’s compensation insurance, furnished the contractor building materials which entered into the construction of the building.

No action shall be maintained on a public contractor’s bond unless within 90 days after the completion of the contract and acceptance of the building by the proper public authorities the plaintiff shall serve upon the principal and his sureties a written notice specifying the nature and amount of his claim and the date of the last item thereof. G. S. 1923, § 9705.

The several plaintiffs served notices between May 19 and June 30, 1925, inclusive, in an effort to comply with the statute. Were the notices timely and seasonably served? The trial court said they were. Because of appellant’s claim that a contrary inference of law results from the established facts, we will state the facts and circumstances ivhich it is claimed show the “completion of the contract and acceptance of the building.”

The use of the building for classes increased from October 1, 192á. The additional $1,000 was paid. The work continued through October. The contractor’s men had left the job by October 17. On October 28 representatives of the architect, the board and the con *369 tractor inspected the building. All agreed that the contractor was to meet the following:

“[1] Cement floor guarantee. [2] Roof guarantee by subcontractor countersigned by Carlsted Brothers. [3] Make all Astral window top sash reversible. [4] Painting — Paint diffuser blades, boiler room and fan room work, footwarmer ducts, oil gym floor, touch up Astral notches. [5] Blackboard — complete in Physics [room] and room 103. [6] Lead down footscrapers. [7] Get iron plate to put on door at door stops. [8] Stops for gym bale, doors. [9] Deliver six outside door keys and get six extra Yan Gurpin dogging keys. [10] Make statement of unpaid accounts. [11] Tie up attic hanger (furring). [12] Tighten friction arms on casement sash. [13] Adjustment for face brick.”

Thereupon $39,000 was paid to the contractor, leaving a balance of only $1,200.95, which was to be retained until such time as the building was completed. The value of the work and material necessary to overcome the above deficiencies was $500 to $600. On December 6, 1924, the secretary of the board, without the knowledge of the board members, wrote a letter to Smith & Wyman Company, saying : “The date that our school was accepted from the contractors, Carlsted Bros., was October 31, 1924.” The board never formally or expressly accepted it. Nor did the architect give any final certificate. All the requirements specified in the above list were fulfilled by February 15,1925, except (a) that the boiler room and area floor slabs which had cracked and through which water oozed up had never been corrected, this being what specification No. 1 had reference to; (b) plaintiffs were never paid; and (c) the roof work was not done until in August, 1925.

It is claimed that the work necessary on the roof was repair work covered by the guaranty but not due to a failure properly to construct in the first instance. This is disputed by plaintiffs. We think the evidence with special reference to a letter from J. Hen-ning & Son to the architect supports the apparent conclusion of the trial court that the roof work was necessary because of failure *370 properly and completely to construct and not a necessary repair attributable to or made necessary by use.

We are of the opinion that the record presented a question of fact as to whether the contract was completed and the building accepted. As between the contractor and the school board the contract ivas not completed for the simple reason that the bills incurred in the work were not paid. This was necessary “for the faithful performance” of the contract; as we have heretofore said that payment for material and labor used by a contractor is an essential element of the completion of the contract. Johnson v. Laurence, 171 Minn. 202, 214 N. W. 24. A contractor who agrees to furnish certain material agrees to pay therefor. Fidelity & Dep. Co. v. Milwaukee-Western F. Co. 191 Wis: 499, 210 N. W. 713. However we have here a different situation, in that the controversy arises not between the contractor and the owner, but between the contractor’s creditors and its surety. The surety has contracted to pay such creditors. Its liability is certain. In the absence of the provisions of the statute applicable, the same doctrine should apply between these parties. But the legislature has said that no action shall be maintained on this liability unless the notice above mentioned shall be given “within ninety days after the completion of the contract and acceptance of the building.” To apply the doctrine of Johnson v. Laurence, 171 Minn. 202, 214 N. W. 24, to a case of this character would completely destroy the provisions of § 9705. This fact leads us to the conclusion that when the legislature used the language “completion of the contract” they intended and meant the “completion of the building.” We so construe the statute. It follows that Johnson v. Laurence, 171 Minn. 202, 214 N. W. 24, is not controlling.

We conclude that the evidence supports the finding that the physical structure of the building was not completed 90 days prior to the service of the notice, nor had the contract been completed at thát time. There is an obvious distinction. Daniels Lbr. Co. v. Ottumwa S. & C. Co. (Iowa) 214 N. W. 481. Because of the statute, the important element here is the former.

It is urged that a substantial performance of the contract was had on October 31, 1924, or at least by February 15, 1925. We *371 are of the opinion that in a case of this character the doctrine of substantial performance has no application. That doctrine is wholesome as applied between the owner and the contractor where abatement may be had to the owner for deficiencies on the part of the contractor. But to hold that while the work is still proceeding the acceptance of it in an incomplete state is sufficient to put in operation the 90-day limitation in the statute in actions of this character would lead to unreasonable results never within the contemplation of the legislature. Millikin Bros. Inc. v. City of New York, 201 N. Y. 65, 94 N. E. 196, Ann. Cas. 1912A, 905, 908; Colon & Co. v. Smith, 226 N. Y. 102, 123 N. E. 78. There is some analogy in Heimbach Lbr. Co. v. Spear, 140 Minn. 276, 167 N. W. 1041.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spartan Mechanical, Inc. v. St. Paul Fire & Marine Insurance Co.
414 N.W.2d 476 (Court of Appeals of Minnesota, 1987)
United States Fidelity & Guaranty Co. v. Couch, Inc.
472 So. 2d 614 (Supreme Court of Alabama, 1985)
Alexander Construction Co. v. C & H Contracting, Inc.
354 N.W.2d 535 (Court of Appeals of Minnesota, 1984)
Anchor Casualty Co. v. Commissioner of Securities
107 N.W.2d 234 (Supreme Court of Minnesota, 1961)
Wheeler Lumber Bridge & Supply Co. v. Seaboard Surety Co.
16 N.W.2d 519 (Supreme Court of Minnesota, 1944)
Universal Electric Const. Co. of Alabama v. Robbins
194 So. 194 (Supreme Court of Alabama, 1940)
Kirkpatrick v. Douglas
65 P.2d 1169 (Montana Supreme Court, 1937)
State Ex Rel. Bozicevich v. City of Eveleth
265 N.W. 30 (Supreme Court of Minnesota, 1936)
Kunz Insurance Agency v. Phillips
255 N.W. 90 (Supreme Court of Minnesota, 1934)
Williamson v. Williams
247 N.W. 704 (Michigan Supreme Court, 1933)
National Exchange Bank of St. Paul v. Solberg
221 N.W. 677 (Supreme Court of Minnesota, 1928)
Moose Lake Sand & Gravel Co. v. American Surety Co.
220 N.W. 958 (Supreme Court of Minnesota, 1928)
State Bank of Brooten v. Forney
219 N.W. 546 (Supreme Court of Minnesota, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
219 N.W. 546, 174 Minn. 366, 1928 Minn. LEXIS 1154, Counsel Stack Legal Research, https://law.counselstack.com/opinion/guaranteed-gravel-sand-co-v-aetna-casualty-surety-co-minn-1928.