Fay v. Bankers Surety Co.

146 N.W. 359, 125 Minn. 211, 1914 Minn. LEXIS 742
CourtSupreme Court of Minnesota
DecidedMarch 20, 1914
DocketNos. 18,490, 18489, 18,488 — (242, 243, 244)
StatusPublished
Cited by26 cases

This text of 146 N.W. 359 (Fay v. Bankers Surety Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fay v. Bankers Surety Co., 146 N.W. 359, 125 Minn. 211, 1914 Minn. LEXIS 742 (Mich. 1914).

Opinion

Philip E. Brown, J.

On April 4, 1910, one Jerry Sherwood entered into a contract with Bed Lake county, wherein he agreed to construct County Ditch No. 38 therein, and to pay, as they became due, all just claims for all work and labor performed and all skill and material furnished in its execution, and to save the county harmless from any cost, charge, or expense which might accrue on account of the doing of the work. On May 14, 1910, the same parties entered into a like contract for the construction of Ditch No. 43 in the same county. Sherwood, as principal, and defendant, as surety, executed bonds to the county in connection with both contracts, in adequate amounts, conditioned, among other things, that he would faithfully pay, “as they [became] due, all just claims for all work and labor performed and all skill and material furnished in the execution of [the] contract.” Sherwood thereafter entered upon performance of the work. Plaintiffs, directly in .their own behalf and claiming also as assignees of others, brought these three separate actions, seeking to recover the value of labor, [213]*213materials, etc., alleged to have been performed and furnished in construction of the ditches. Defendants denied liability, the causes were separately tried to the court, findings made, and judgments ordered for plaintiffs. In the McGinn case the court awarded a recovery for two axes, $2.40, two dozen saw-hack blades, $1.80, and coal, $6.18; also $56.06 for horse feed, provisions, and labor furnished and performed by one Rime, alleged to have been assigned to plaintiff. In the Prestegaard case the court gave plaintiff judgment for $20, for wood furnished by one Iverson, the claim for which being alleged to have been assigned to plaintiff. In the Pay case $224 was allowed for labor performed by plaintiff. Defendant appealed from orders denying its motions for amended findings and new trials.

1. The first question requiring consideration relates to the allowance for tools and coal in the McGinn case. G. S. 1913, § 5536, provides that bonds in cases like the present shall be taken for the use of all persons who may show themselves aggrieved or injured by any breach thereof or of the contract for which the bond is given, while section 5531 states that every ditch contract and bond shall embrace “all the provisions provided by law for the giving of bond by contractors for public works and improvements and for the better security of the contracting county or counties and of the parties performing labor and furnishing material in and about the performance of such contracts.” Bonds by contractors for public works and improvements are required by section 8245, the material portions of which being:

“No contract with the state, or with any municipal corporation or other public board or body thereof, for the doing of any public work, shall be valid for any purpose, unless the contractor shall give bond to the state or other body contracted with, for the use of the obligee and of all persons doing work or furnishing skill, tools, machinery, or- materials under, or for the purpose of, such contract, conditioned for the payment, as they become due, of all just claims for such work, tools, machinery, skill and materials, for the completion of the contract in accordance with its terms,-for saving the obligee harmless from all costs and charges that may accrue on ac[214]*214count of the doing of the work specified, and for compliance with the laws appertaining thereto.”

In Wilcox Lumber Co. v. School District No. 268 of Otter Tail County, 103 Minn. 43, 45, 114 N. W. 262, 263, it was declared:

“The purpose of this statute was the protection of laborers and materialmen performing labor or furnishing material for the execution of a public work to which the mechanic’s lien statute does not apply. The bond * * * stands as security for the payment of all obligations incurred by the contractor in the prosecution of the work, and the general rules and principles of the law of suretyship apply to and govern the rights of the parties.”

The same principle is restated in State v. Clark, 116 Minn. 500, 502, 134 N. W. 130, 39 L.R.A. (N.S.) 43. And while the rule of strict construction in favor of the surety does not apply to a surety company (Allen v. Eneroth, 118 Minn. 476, 479, 137 N. W. 16), the surety is bound in the manner and to the extent of his obligation and no further; but the bond, being given by virtue of statute, cannot be severed therefrom, and the parties are deemed to have contracted with reference thereto-. Such an instrument “must be construed in the light of the statute, and extended, as well as limited in its scope, to those cases contemplated by the statute, unless violence would be done to the language of the bond by such construction.” Fairmont Cement Stone Mnfg. Co. v. Davison, 122 Minn. 504, 509, 142 N. W. 899; Combs v. Jackson, 69 Minn. 336, 337, 72 N. W. 565. See also Union Sewer Pipe Co. v. Olson, 82 Minn. 187, 84 N. W. 756; Waterous Engine Works Co. v. Village of Clinton, 110 Minn. 267, 125 N. W. 269; Scott-Graff Lumber Co. v. Independent School District No. 1, 112 Minn. 474, 128 N. W. 672.

Although the bonds are not conditioned in .terms in accordance with our present statute, but follow chapter 321, p. 535, Laws 1901, with these principles as guides, we are led to the conclusion that the bonds are valid as statutory obligations to the extent of the fair import of the language used in the conditions. Their effect cannot, however, be extended further. See Union Sewer Pipe Co. v. Olson, 82 Minn. 189, 84 N. W. 956.

While the proofs connecting the items mentioned with either of [215]*215the ditches is unsatisfactory, we deem it sufficient when the general manner in which these cases were presented to the court below is considered. But, aside from the coal, clearly none of them can be held “materials” within the meaning of the bond. Beals v. Fidelity & Deposit Co. 76 App. Div. 526, 527, 78 N. Y. Supp. 584, and cases cited, affirmed in 178 N. Y. 581, 70 N. E. 1095; Empire State Surety Co. v. Des Moines, 152 Iowa, 531, 548, 131 N. W. 870, 132 N. W. 837. Whether the coal, consumed in the performance of the contract, should be considered “material furnished in its execution,” is a question upon which the authorities are at variance. See Zipp v. Fidelity & Deposit Co. 73 App. Div. 20, 76 N. Y. Supp. 386; City Trust, Safe Deposit & Surety Co. v. U. S. 147 Fed. 155, 77 C. C. A. 397; National Surety Co. v. Bratnober Lumber Co. 67 Wash. 601, 122 Pac. 337; City of Alpena v. Title Guaranty & Surety Co. 168 Mich. 350, 134 N. W. 23; City of Philadelphia v. Malone, 214 Pa. St. 90, 63 Atl. 539; George H. Sampson Co. v. Com. 202 Mass. 326, 88 N. E. 911. With us, however, the lien laws, for which the statutes now under consideration are largely substituted, have always been given a broad and liberal construction, and no reason is perceived why such should not be applied here. Materials ordinarily required in performance of the work may properly be assumed to have been within the contemplation of the parties when the bond was executed. Power must usually be generated in ditching, and we think liability should not be restricted to items actually entering into the completed structure. It is sufficient if the materials be reasonably incident to the performance of the particular contract. Any other rule would exclude forms for concrete or lumber required for a temporary dam, without regard to the necessity of either, and other materials of like nature. We hold the item for coal was properly allowed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Healy Plumbing & Heating Co. v. Minneapolis-St. Paul Sanitary District
169 N.W.2d 50 (Supreme Court of Minnesota, 1969)
HEALY PLUMB. & HEAT. CO. v. Mpls.-St. Paul San. Dist.
169 N.W.2d 50 (Supreme Court of Minnesota, 1969)
Morris v. . Holshouser
17 S.E.2d 115 (Supreme Court of North Carolina, 1941)
Ceco Steel Products Corp. v. Tapager
294 N.W. 210 (Supreme Court of Minnesota, 1940)
Lucas v. Medical Arts Building Co.
291 N.W. 892 (Supreme Court of Minnesota, 1940)
General Motors Truck Co. v. Phillips
254 N.W. 580 (Supreme Court of Minnesota, 1934)
Murphy v. County of St. Louis
244 N.W. 335 (Supreme Court of Minnesota, 1932)
Clifton v. Norden
226 N.W. 940 (Supreme Court of Minnesota, 1929)
Lamberton Building & Loan Ass'n v. National Surety Co.
225 N.W. 724 (Supreme Court of Minnesota, 1929)
Guaranteed Gravel & Sand Co. v. Aetna Casualty & Surety Co.
219 N.W. 546 (Supreme Court of Minnesota, 1928)
State Ex Rel. Penn Lubric Oil Co. v. Lyle
5 S.W.2d 453 (Missouri Court of Appeals, 1928)
Franzen v. Southern Surety Co.
246 P. 30 (Wyoming Supreme Court, 1926)
Wiss v. Royal Indemnity Co.
282 S.W. 164 (Missouri Court of Appeals, 1926)
Smith v. Oosting
203 N.W. 131 (Michigan Supreme Court, 1925)
Standard Oil Co. v. Day
201 N.W. 410 (Supreme Court of Minnesota, 1924)
Bartles-Scott Oil Co. v. Western Surety Co.
200 N.W. 937 (Supreme Court of Minnesota, 1924)
Board of Trade Livery Co. v. Georgia Casualty Co.
200 N.W. 633 (Supreme Court of Minnesota, 1924)
Wight v. Baltimore & Ohio Railroad
125 A. 881 (Court of Appeals of Maryland, 1924)
Westling v. Republic Casualty Co. of Pittsburgh
195 N.W. 796 (Supreme Court of Minnesota, 1923)
Miller v. American Bonding Co.
158 N.W. 432 (Supreme Court of Minnesota, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
146 N.W. 359, 125 Minn. 211, 1914 Minn. LEXIS 742, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fay-v-bankers-surety-co-minn-1914.