Miller v. American Bonding Co.

158 N.W. 432, 133 Minn. 336, 1916 Minn. LEXIS 922
CourtSupreme Court of Minnesota
DecidedJune 23, 1916
DocketNos. 19,804—(160)
StatusPublished
Cited by18 cases

This text of 158 N.W. 432 (Miller v. American Bonding Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miller v. American Bonding Co., 158 N.W. 432, 133 Minn. 336, 1916 Minn. LEXIS 922 (Mich. 1916).

Opinion

Holt, J.

On the twelfth of August, 1913, separate contracts were let by the county of Winona for the construction of two concrete state rural highways under the Elwell law to the partnership of Prinz & Carlson, and the defendant bonding company gave the statutory bonds. The contractors entered upon the work, but abandoned it in the fall of 1913, leaving unpaid a number of claims for labor, materials, tools and machinery procured in the performance of the work by themselves and subcontractors. Many of these claims were assigned to plaintiff, who herein seeks to enforce them against the bonding company. Crane & Ordway Company and R. D. Cone Company were permitted to become intervening plaintiffs, each setting up a cause of action for instrumentalities sold the contrac[338]*338tors to be used, and which were used in the construction of the roads. A demurrer was sustained to several of plaintiff’s claims, and, after a trial, the intervening plaintiffs were denied a recovery. The actions of the courts below — the sustaining of the demurrer by the late Judge Snow and the rejection of the claims of the two intervening plaintiffs by Judge Granger — now come up for review.

The Elwell Law (c. 254, p. 352, Laws 1911), requires the contractor’s bond to be conditioned as provided by chapter 230, p. 303, Laws 1905, in drainage proceedings, and in section 15 of the latter is found this requirement: “Every such contract shall embrace all the provisions provided by law for the giving of bond by contractors for public works and improvements,” etc. thus making applicable G. S. 1913, § 8245. The bond here involved is conditioned that Prinz & Carlson “shall pay, as they become due, all just claims for all work and labor performed and all tools, machinery, skill and materials furnished under, or for the purpose of, or in the execution of” the contract. This is in substantial conformity to said section 8245.

The two claims disallowed by Judge Granger, and many items in the different causes of action to which Judge Snow sustained the demurrer, depend upon the bonding company’s liability for the purchase price of tools and machinery sold to the contractors or subcontractors as proper equipment for the building of the highways.

As to the claims of Crane & Ordway Company the findings are, in substance, that at the request of the contractors the company in September, 1912, sold and delivered to them iron pipes, tees, plugs, hose nipples, clamps and hose of the reasonable value of $729 to be used and which were used by them in conveying water to the concrete mixer used in the construction of the highways. That the materials were not manufactured by the seller expressly for this purpose, but were ordinary materials carried in stock. As to the claim of the partnership of R. D. Cone Company, the court found that it sold and delivered 12 dump wagons to be used in hauling material for the construction of the highways, and they were so used. The balance unpaid on the wagons is $861.05. Both the piping and the wagons were found to have become a part of the general equipment of the contractors.

The contention of appellants is, that, under the plain reading of the [339]*339law/ one who furnishes tools or machinery for a public improvement may resort to the contractor’s bond for the payment of their market or agreed price. It is argued that, although it might be possible to give an interpretation to the statute so as to confine claims for machinery against a contractor’s bond to machines incorporated into or becoming a part of the works or improvement, the same may not be done in respect to tools which never can become a component part of a work or improvement — tools might here include both the piping and wagons without being unduly liberal in the interpretation of a statute designed to be remedial. It must be conceded that so far as the rights of a vendor of a tool to have recourse to a bond of this sort for its purchase price, use or repair, it must be the same as the rights of a vendor of machinery.

A proper construction of the statutes here applicable is not free from difficulty. Chapter 354, p. 757, Laws 1895, was the first law exacting a bond from contractors upon public works and improvements to better secure the state, the public corporations and the parties performing labor and furnishing materials for such works or improvements. The first section, standing alone, might have covered labor performed and skill and material furnished in the execution of the contract to the same extent as under the mechanic’s lien statute; The fourth section, however, provides: "Whoever shall perform or cause to be performed any work or labor or furnish or cause to be furnished any skill or material including any work, labor, skill or material necessary in the repair of any tool or machine and including the use of any tool or machine or material furnished particularly for such contract and used ]herefor in the execution or [of] such contract at the request of the contractor * * * shall be considered a party in interest in said bond and may bring an action thereon for the reasonable value or agreed price as the case may be, of the work or labor performed or skill or material or tool or machine furnished in the performance' of such contract.” Section 4 applied, amplified and extended section 1 so that recourse might be had to the bond for work or material performed or furnished in the repair of any tool or machine, and for the use of any tool or machine furnished particularly for the contract "The reasonable value ot agreed price” therein mentioned must mean the reasonable value or agreed price for the repair or for the use, as the case may be, and not for the purchase of the tool or machine. These twf [340]*340sections were combined in the revision of 1905, (R. L. 1905, § 4535), and by the amendment of 1909 a proviso, of no bearing here, was added, so that the law upon the subject is now found in G. S. 1913, § 8245. A reasonable effect and meaning must be given to the words “tools” and “machinery” in the law as it now is. They should not be eliminated. Since the main purpose of the revision of 1905 was to rearrange and condense and not to abrogate or alter the meaning of existing laws, we may with propriety look to the original form of a statute for light in cases where the revision, in the effort to make the code terse and compact, has left the meaning somewhat obscured. It seems quite clear that the law, as it existed just prior to the taking effect of Revised Laws 1905, did not give a cause of action on the contractor’s bond for .the purchase price of a tool or a machine sold to the contractor to be used in a public work or' improvement. But it was given for the repair of a tool or machine, and for the value of the use in case the contractor rents it for the job. Where the work is of such character that the use of extensive and costly machines are required, it is reasonable to consider that the wear and tear of these machines is a necessary contribution to the work, or, in other words, the reasonable value of the use of the machines contributes as much to the construction in hand as does the reasonable value of the manual labor expended thereon. So also, in the performance of every improvement or work of any magnitude, the tools become dulled and out of repair, and the machines used thereon break or wear out parts; and, in order to proceed efficiently with the work, these matters must be attended to and require labor, skill and material.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trestle & Tower Engineering, Inc. v. Star Insurance
13 F. Supp. 2d 1166 (D. Kansas, 1998)
KLINE v. McMEEKIN CONST. CO.
67 S.E.2d 304 (Supreme Court of South Carolina, 1951)
Western Material Co. v. Deltener
264 N.W. 207 (South Dakota Supreme Court, 1935)
MacK-international Motor Truck Corp. v. Western Surety Co.
260 N.W. 869 (Supreme Court of Minnesota, 1935)
General Motors Truck Co. v. Phillips
254 N.W. 580 (Supreme Court of Minnesota, 1934)
American Surety Co. v. Corr Service Erection Co.
170 S.E. 325 (Court of Appeals of Georgia, 1933)
Yancey Bros. v. American Surety Co.
160 S.E. 100 (Court of Appeals of Georgia, 1931)
United States Fidelity & Guaranty Co. v. Benson Hardware Co.
132 So. 622 (Supreme Court of Alabama, 1931)
Western Material Co. v. Enke
228 N.W. 385 (South Dakota Supreme Court, 1929)
Clifton v. Norden
226 N.W. 940 (Supreme Court of Minnesota, 1929)
Dennis v. Enke
224 N.W. 925 (South Dakota Supreme Court, 1929)
Union Indemnity Co. v. State Ex Rel. R. S. Armstrong & Bro.
118 So. 148 (Supreme Court of Alabama, 1928)
Wiseman v. . Lacy
138 S.E. 121 (Supreme Court of North Carolina, 1927)
Franzen v. Southern Surety Co.
246 P. 30 (Wyoming Supreme Court, 1926)
Aldinger v. Close
201 N.W. 625 (Supreme Court of Minnesota, 1925)
Westling v. Republic Casualty Co. of Pittsburgh
195 N.W. 796 (Supreme Court of Minnesota, 1923)
Dawson v. Northwestern Contruction Co.
163 N.W. 772 (Supreme Court of Minnesota, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
158 N.W. 432, 133 Minn. 336, 1916 Minn. LEXIS 922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miller-v-american-bonding-co-minn-1916.