Clifton v. Norden

226 N.W. 940, 178 Minn. 288, 67 A.L.R. 1227, 1929 Minn. LEXIS 1169
CourtSupreme Court of Minnesota
DecidedOctober 11, 1929
DocketNos. 27,252, 27,253.
StatusPublished
Cited by20 cases

This text of 226 N.W. 940 (Clifton v. Norden) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clifton v. Norden, 226 N.W. 940, 178 Minn. 288, 67 A.L.R. 1227, 1929 Minn. LEXIS 1169 (Mich. 1929).

Opinion

*289 Stone, J.

In this action upon a public contractor’s bond there was a verdict for plaintiffs. Defendant Norden was the contractor and does not appeal. The surety, defendant National Surety Company, appeals from an order denying its alternative motion for judgment notwithstanding or a new trial. Plaintiffs, having moved for an order for judgment notwithstanding for a larger amount than that allowed them by the verdict, or in the alternative for a new trial, also appeal from the order denying that motion.

Plaintiffs sue for the value of labor and materials used in the repair of motor trucks belonging to subcontractors which were employed by defendant Norden in the execution of a highway contract. The amount claimed is the cost for both labor and materials of installing a new main bearing, pistons, drive shaft, universal joints, cylinder blocks complete with pistons and rings, an oil gauge, main switch, springs, connecting rod, batteries and tires. The repairs ivere made during the course of the Avork, and there is no proof that any of the new parts were worn out on the job. The charge to the jury was that “the bonding company is only chargeable for the value of the repair, or for the Avork that they put into those things, where it is not greater than the reasonable value of the use of the article Avas upon the contract.” This instruction prevented plaintiffs’ getting the entire sum for Avhich they -sued and is assigned as error on plaintiffs’ appeal. They ask judgment for the total cost of the repairs. It is argued for defendant surety that none of the items are within the coverage of its bond. The bond, as required by G. S. 1923 (2 Mason, 1927) § 9700, is “for the use of the obligee [the county of Mahnomen] and of all persons doing Avork or furnishing skill, tools, machinery, or materials or insurance premiums or equipment or supplies for any camp maintained for the feeding or keeping of men and animals engaged under, or for the purpose of, such contract,” and is conditioned for the payment “of all just claims for such work, tools, machinery, skill, materials, insurance premiums equipment and supplies, for the completion of the contract in accordance Avith its terms.” So the question is one of statutory construction. Were the labor and new parts furnished *290 by plaintiffs, who maintained a public garage and shop near the work for the storage and repair of automobiles and motor trucks, embraced within the language of the statute? Were they or any of them “work * * tools, machinery, or materials”, furnished under or for the purpose of such contract or for its completion in accordance with its terms?

Decision is not controlled, as in case of the ordinary written contract, by what the parties themselves may have contemplated as being within the bond. Its language is that of statute, and the question, what did the legislature mean. As left by the revision of 1905 (R. L. 1905, § 4535) the law was in its present form except for the amendment by L. 1923, p. 534, c. 373, requiring a bond to protect, in addition to those doing work or furnishing skill, tools, machinery, materials or insurance premiums, those also who furnish “equipment or supplies for any camp maintained for the feeding or keeping of men and animals engaged under, or for the purpose of, such contract.” That amendment was designed to secure protection for those who furnished such things as food for horses and men, and camp supplies, which were not considered “materials” for the work under the old statute. Fay v. Bankers Surety Co. (1914) 125 Minn. 211, 146 N. W. 359, Ann. Cas. 1915C, 688; Westling v. Republic Cas. Co. 157 Minn. 198, 195 N. W. 796; Standard Oil Co. v. Remer, 170 Minn. 298, 212 N. W. 460; Hansen v. Remer, 160 Minn. 453, 200 N. W. 839. Our statute goes much further than many others in including “tools, machinery or materials.” See Franzen v. Southern Surety Co. 35 Wyo. 15, 246 P. 30, 46 A. L. R. 496. In consequence we have held that the rental of tools and machinery used on a public contract is within the coverage of the bond. Miller v. American Bonding Co. 133 Minn. 336, 158 N. W. 432. So also as to the rental of horses. Dawson v. N. W. Const. Co. 137 Minn. 352, 363, 163 N. W. 772. There has never been question but that coal (Fay v. Bankers Surety Co. 125 Minn. 211, 146 N. W. 359, Ann. Cas. 1915C, 688) and gasolene and oil (Bartles-Scott Oil Co. v. Western Surety Co. 161 Minn. 169, 200 N. W. 937) used in generating power for the performance of a contract, are within the bond.

*291 Literally, in its inclusion of equipment and machinery, the statute reaches the cost of new articles purchased by a contractor for use and used on a given work, even though they become part of his permanent and general equipment and will serve on other and perhaps many other contracts as well. But to conclude that the language was meant so literally would lead at once into absurdity. Plainly it was not intended that sureties for a $25,000 contract may be liable for the cost of a steam shovel outfit purchased, to be first used on that job, at a cost of possibly twice the contract price. So, as frequently happens, the language must be restricted within the reasonable limits easily found when applied to its subject matter. The law was not intended to permit a contractor to go onto a bonded job with a run-down outfit and have it rebuilt at the expense of his sureties. Public contracts require the contractors to furnish their own equipment. They imply that it shall come onto the job complete, ready for use, and without any obligation against the work arising from antecedent conditions. Moreover, they demand, expressly or by direct implication, that his equipment be maintained by the contractor in a workable condition to the end that the job may be done expeditiously and within the contract price. In consequence, no legislature has enacted, unless it be that of West Virginia [see Hicks v. Randich (W. Va.) 144 S. E. 887] and no court held, that the bondsmen shall be liable for the purchase price of contractors’ equipment, unless perchance it is of a kind which is to be used only on the job in question and is wholly consumed thereon, or at least consumed to the extent that there is no residual use or value except as salvage. Dennis v. Enke (S. D.) 224 N. W. 925.

If a motor truck purchased for immediate use on a public contract will in the normal course of things serve on others as well, its cost is not within the coverage of the contractor’s bond. So also if a truck break down on the job beyond possibility of repair or be completely wrecked and be replaced by a new one which will serve other jobs as well, the cost of the new machine is not within the bond. The same must be true of any part of a machine which *292 through use or casualty must be replaced. If it is such that it will normally not only serve the job in hand but others as well, its cost is not covered. That conclusion must be adopted and adhered to or else there is none which will serve as a guide in determining, as to tools and machinery and the cost of repairing the same, whether the contractor’s sureties are liable.

The foregoing does not overlook a class of repair work, minor in cost but of constant presence and importance, which may be within the bond on the job where it is done even though the contractor will have use of it on other work also.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morrow Crane Co. v. T. R. Tucker Construction Co.
373 S.E.2d 701 (Court of Appeals of South Carolina, 1988)
Cecil I. Walker MacHinery Co. v. Stauben, Inc.
230 S.E.2d 818 (West Virginia Supreme Court, 1976)
Nelson v. Hagen
146 N.W.2d 873 (North Dakota Supreme Court, 1966)
Arrow Contractors Equipment Co. v. Siegel
216 N.E.2d 181 (Appellate Court of Illinois, 1966)
Carpenter v. Seaboard Engineering Co.
183 A.2d 216 (Supreme Judicial Court of Maine, 1962)
Carpenter v. Susi
121 A.2d 336 (Supreme Judicial Court of Maine, 1956)
KLINE v. McMEEKIN CONST. CO.
67 S.E.2d 304 (Supreme Court of South Carolina, 1951)
Western Casualty & Surety Co. v. Fulton Supply Co.
4 S.E.2d 690 (Court of Appeals of Georgia, 1939)
MacK-international Motor Truck Corp. v. Western Surety Co.
260 N.W. 869 (Supreme Court of Minnesota, 1935)
Marion Steam Shovel Co. v. Union Indemnity Co.
75 S.W.2d 541 (Court of Appeals of Kentucky (pre-1976), 1934)
General Motors Truck Co. v. Phillips
254 N.W. 580 (Supreme Court of Minnesota, 1934)
Moore v. Standard Accident Insurance
173 S.E. 481 (Court of Appeals of Georgia, 1934)
Rhodes v. Riley
169 S.E. 525 (West Virginia Supreme Court, 1933)
Motor Power Equipment Co. v. Park Transfer Co.
247 N.W. 244 (Supreme Court of Minnesota, 1933)
Standard Acc. Ins. Co. v. Dodd
142 So. 574 (Supreme Court of Alabama, 1932)
Yancey Bros. v. American Surety Co.
160 S.E. 100 (Court of Appeals of Georgia, 1931)
United States Fidelity & Guaranty Co. v. Benson Hardware Co.
132 So. 622 (Supreme Court of Alabama, 1931)
Thoelke v. Norden
226 N.W. 943 (Supreme Court of Minnesota, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
226 N.W. 940, 178 Minn. 288, 67 A.L.R. 1227, 1929 Minn. LEXIS 1169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clifton-v-norden-minn-1929.