KLINE v. McMEEKIN CONST. CO.

67 S.E.2d 304, 220 S.C. 281, 1951 S.C. LEXIS 100
CourtSupreme Court of South Carolina
DecidedOctober 11, 1951
Docket16552
StatusPublished
Cited by4 cases

This text of 67 S.E.2d 304 (KLINE v. McMEEKIN CONST. CO.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
KLINE v. McMEEKIN CONST. CO., 67 S.E.2d 304, 220 S.C. 281, 1951 S.C. LEXIS 100 (S.C. 1951).

Opinion

Tayror, Justice.

This appeal involves liability of respondents to appellant for payment of the purchase price of four steel beams furnished during the construction of a bridge in the South Carolina Highway System. Appellant contends that respondents are indebted to it in the sum of $1,631.08, such being the unpaid purchase price for four steel beams, sixty feet long, delivered to Steel Erectors, Inc., for use in construction'of a bridge which respondent, McMeekin Construction Company, was under contract to construct for the South Carolina Highway Department. It appears that respondents entered into bond with the said Highway Department wherein it was agreed that they would “pay when and as due all lawful claims for labor performed or materials and supplies furnished for use in and about the construction of said highway or highway structures” and appellant contends that respondents are thereby liable for the purchase price of the aforesaid steel furnished. Respondents’ answer was a general denial.

The case came on to be heard before the. Honorable Steve C. Griffith and a jury in the Common Pleas Court for Richland County. At the close of appellant’s testimony respondents moved for a nonsuit which was overruled. At the close of all the testimony appellant and respondents each moved for directed verdicts. At this stage of the trial it was agreed between the parties that there was no disputed issue of fact to be submitted to the jury, as a resúlt of which the entire matter was submitted to the Trial Judge for determination, with both sides furnishing written briefs. Thereafter, on the 24th day of February, 1951, the Presiding *284 Judge filed his order granting respondents’ motion for a directed verdict and ordering the complaint dismissed.

Appellant now comes to this Court contending that the Trial Judge erred in finding that the steel beams furnished by appellant to the subcontractor upon the highway project in question were equipment of the subcontractor, whereas he should have found that the steel beams furnished were material furnished for use in and about the highway project in question and therefore within the meaning and purview of the contract and bond issued pursuant thereto.

It is not disputed that respondents entered into a contract with the South Carolina Highway Department for the construction of a steel superstructure over the Santee River on Route 511 near Jamestown, South Carolina, and that respondent sublet a part of that contract to Harvey Stewart Contracting Company, of Charlotte, North Carolina, who apparently sublet to Steel Erectors, Inc., the steel work necessary to the construction of the bridge. The Trial Judge concluded and so found that if Steel Erectors, Inc., was not a subcontractor, it was an employee and agent of Harvey Stewart Contracting Company, who was a subcontractor of McMeekin Construction- Company, and there is no appeal from this finding.

The pertinent language of the bond entered into by the McMeekin Construction Company appears as follows: “The condition of this obligation is such that if said bounden principal McMeekin Construction Company shall in all things well and truly perform all the terms and conditions of the foregoing contract to be by them/him performed and within the time provided, and shall pay when and as due all lawful claims for labor performed or materials and supplies furnished for use in and about the construction of said highway or highway structures * * *, then this obligation to be void; * *

In the construction of the bridge in question Steel Erectors, Inc., used a 100-foot mast and a 90-foot boom with the *285 four steel beams in question being used as outriggers. The respondents contended, and it was so held by the Trial Judge, that these steel beams thereby became an integral part of Steel Erectors’ permanent equipment, in that they became a part of the derrick which was, of course, an essential part of the subcontractor’s permanent equipment. Appellant contends, however, that these beams never attained such status, but were material furnished for use in and about the highway project.

We have been unable to find any case in this State that precisely fits the facts under consideration and counsel has cited none, but the rule appears to be that such incidentals as coal, gasoline, and current repairs to machinery, etc., should be included within the purview of the bond, these items being ancillary, but necessary to the prosecution of the work, while permanent additions to a contractor’s equipment which by their nature are. neither depreciated nor consumed on the contract are not. Standard Oil Company of New Jersey v. Powell Paving & Contracting Co., 139 S. C. 411, 138 S. E. 184; American Hardware & Equipment Co. v. Detroit Fidelity & Surety Co., 159 S. C. 263, 156 S. E. 770; Molony & Carter Co. v. Pennell & Harley, Inc., 169 S. C. 462, 169 S. E. 283; Cantey v. Newell Contracting Co., 175 S. C. 74, 178 S. E. 342; Miller v. Cornell-Young Co., 171 S. C. 228, 171 S. E. 790.

The underlying equities require discrimination between labor and materials consumed in the work or in connection therewith and those made use of in furnishing the so-called contractor’s plant and available not only for the particular contract but for other work. Tools, machinery and appliances used by the contractor, although worn out in the progress of the work, are not such labor and materials as are ordinarily contemplated by contractor’s bonds. 43 Am. Jur., Sec. 186, page 927.

The Supreme Court of Minnesota said in Clifton v. Norden, 178 Minn. 288, 226 N. W. 940, 941, 67 A. L. R. 1227:

*286 “If a motortruck purchase for immediate use on a public contract will in the normal course of things serve on others as well, its cost is not within the coverage of the contractor’s bond. So also if a truck break down on the job beyond possibility of repair or he completely wrecked and be replaced by a new one which will serve other jobs as well, the cost of the new machine is not within the bond. The same must be true of any part of a machine which, through use or casualty, must be replaced. If it is such that it will normally not only serve the job in hand but others as well, its cost is not covered. That conclusion must be adopted and adhered to, or else there is none which will serve as a guide in determining, as to tools and machinery and the cost of repairing the same, whether the contractor’s sureties are liable.
“There are minor things about machinery which are short-lived and subject to frequent destruction and replacement. The underlying equity requires discrimination ‘between labor and materials consumed in the work or in connection therewith, and labor and materials made use of in furnishing the so-called contractor’s plant, and available not only for this, but for other work. * * * It has, however, no necessary relation to repairs of an incidental and comparatively inexpensive character, made on the plant during the progress of the work, representing only * * * ordinary wear and tear’ or its equivalent. * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morrow Crane Co. v. T. R. Tucker Construction Co.
373 S.E.2d 701 (Court of Appeals of South Carolina, 1988)
Rish v. THEO BROS. CONSTRUCTION CO., INC.
237 S.E.2d 61 (Supreme Court of South Carolina, 1977)
South Carolina Supply & Equipment Co. v. James Stewart & Co.
119 S.E.2d 517 (Supreme Court of South Carolina, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
67 S.E.2d 304, 220 S.C. 281, 1951 S.C. LEXIS 100, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kline-v-mcmeekin-const-co-sc-1951.