Dawson v. Northwestern Contruction Co.

163 N.W. 772, 137 Minn. 352, 1917 Minn. LEXIS 736
CourtSupreme Court of Minnesota
DecidedJuly 6, 1917
DocketNos. 20,262, 20,392, 20,452 — (60, 209, 232)
StatusPublished
Cited by13 cases

This text of 163 N.W. 772 (Dawson v. Northwestern Contruction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dawson v. Northwestern Contruction Co., 163 N.W. 772, 137 Minn. 352, 1917 Minn. LEXIS 736 (Mich. 1917).

Opinion

Bunn, J.

Defendant Northwestern Construction Company, a copartnership, contracted with the county of Itasca for the construction of State Road No. 2. Plaintiff, L. W. Dawson, contracted with the construction company to build sections B and C of this road in accordance with the original plans and specifications, except that plaintiff was to receive 30 cents per cubic yard for earth moved 500 feet or less, and one cent per cubic yard for each 100 feet such earth was hauled over 500 feet. These prices were somewhat less than those specified to be received from the county-by the construction company. Plaintiff’s contract provided that the statement of quantities moved and work done made by the engineer in charge at the completion of the work should be final. [355]*355Defendant Maryland Casualty Company was the surety on the bond of the construction company.

The contract for the building of the road was completed December 11, 1915, and. the final estimate of the engineer as to quantities of earth moved and work done by plaintiff Dawson on sections B and C, showed 9,353 cubic yards of grading at 30 cents per cubic yard, amounting to $3,776.05; 1,385,196 cubic yards of overhaul at one cent, amounting to $13,851.96 and extra work amounting to $389.95, making a total for all work done by plaintiff according to the engineer’s estimate of $16,017, of which sum $3,838.70 was paid plaintiff, and the balance is admitted to be due him less certain offsets.

Plaintiff brought this action, alleging that he moved 11,340 cubic yards of earth, at the contract price of 30 cents per yard, that the overhaul amounted to $15,564.84, and the extra work being $389.95 as allowed. He credited the payment of $3,838.70, and demanded judgment for the balance of $15,489.09 with interest. The partnership Northwestern Construction Company, and the individuals composing it, the county of Itasca and its commissioners, and Maryland Casualty Company, were made defendants. On the coming in. of the answer of the county of Itasca and its board of county commissioners, and on the motion of these defendants, the court made an order permitting the county to pay into court the sum of $15,701.05, admitted to be due to the construction company, and substituting as defendants certain corporations and individuals having claims against the fund. These claimants were ordered to file their answers setting forth their claims to the fund within 30 days. The money was paid into court and the county discharged from all liability as ordered. The claimants answered. Insofar as their claims are involved on this appeal we will state what they áre later. Defendant Maryland Casualty Company, the surety on the bond of the construction company, answered the complaint of plaintiff and the claims of the impleaded defendants. The construction company also answered. Plaintiff replied to these answers.

It is sufficient to say, as to the case between plaintiff Dawson and these answering defendants, that the issues made by the pleadings and tried were these: (1) Was plaintiff bound by the statement of earth moved and work done made in the final estimate of the engineer? (3) If [356]*356not, what were the quantities of earth moved by plaintiff and the overhaul? These issues were tried to a jury. There was a verdict of $14,594.64 in favor of the plaintiff and against both defendants. This was somewhat less than claimed by plaintiff in his complaint, and over $2,400 in excess of the sum admitted by defendants, to be due plaintiff according to the engineer’s estimate. The verdict necessarily involved a finding by the jury that plaintiff was not bound by the engineer’s estimate, and that he had succeeded in proving the quantities of earth moved and the overhaul.

Defendants moved for judgment notwithstanding the verdict or for a .new trial, and appealed from the order denying this motion. The case as between the substituted or impleaded defendants, claimants, and the construction company and casualty company, was tried later before the court without a jury upon the evidence in the case tried by the jury and upon proofs and stipulations as to the respective claims. The court made findings of fact and conclusions of law, adopting the verdict of the jury as to plaintiff’s case, and deciding as to the various claims of the impleaded- defendants as will be hereafter stated. Defendants construction company and casualty company moved for amended findings and conclusions, and for a new trial in the event such motion Was denied. The court amended the findings in certain particulars, but otherwise denied the motion, and the defendants named appealed from the order. There are also appeals by two of the claimants.

We will first consider the case as between plaintiff Dawson and the defendants construction company and casualty company, then the claims of the respective impleaded defendants, claimants against the fund and the bond, and then the claims of the impleaded defendants which were disallowed by the trial court.

I

Plaintiff’s Case.

1. The first claim of appellants is that plaintiff cannot recover any sum in excess of that admitted to be due, as shown by the final estimate of the engineer. This claim is based upon the clause in the contract that it was “agreed that the statement of quantities moved [357]*357and work done issued by tbe engineer shall be final as between the parties hereto.” Plaintiff’s theory on the trial was that there was such gross mistake as' amounts to fraud in the estimate of the engineer as to the earth moved and the overhaul. He contends now that the evidence was sufficient to make this a question for the jury and to warrant the verdict. Defendants contend otherwise. Though counsel for plaintiff argues a question of pleading, the complaint not referring to the engineer’s report or alleging mistakes, we do not discover that appellants claim that it was necessary to allege mistake in the complaint. We certainly think they would not be justified in so claiming. The finality of the engineer’s report was defensive matter, and the issue on this raised in the answer was properly met by a reply alleging gross mistake.

Was there evidence reasonably tending to show such a gross mistake in the engineer’s estimate as under our decisions removes that bar to plaintiff’s recovery? There is no disagreement as to what the law is. The facts which the evidence tended to establish may be briefly stated as follows:

The discrepancy between the claims of plaintiff as to earth moved and overhaul, and the final estimate of the engineer amounted to more than $3,000. If plaintiff’s claims are correct or substantially so, it necessarily follows that there was a mistake in the engineer’s estimate, and a mistake so gross as to permit recovery for the work actually done notwithstanding the engineer’s estimate and the agreement that it should be final. Practically the entire discrepancy is over the quantities of earth removed from a certain pit, and the overhaul on that earth. This pit, unlike others from which earth was taken for the surfacing of the highway, extended out from the right of way of the road into private property for a considerable distance. The evidence showed that only that part of this pit that lay in the right of way was surveyed and cross-sectioned by the engineer. It warranted the jury in finding that the final estimate of the earth removed from this pit outside of the right of way and the overhaul thereon was at least partly guess work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Denney v. Spot Martin, Inc.
328 S.W.2d 399 (Missouri Court of Appeals, 1959)
McCree & Company v. State
91 N.W.2d 713 (Supreme Court of Minnesota, 1958)
American Surety Co. v. Corr Service Erection Co.
170 S.E. 325 (Court of Appeals of Georgia, 1933)
Clifton v. Norden
226 N.W. 940 (Supreme Court of Minnesota, 1929)
Union Indemnity Co. v. State Ex Rel. R. S. Armstrong & Bro.
118 So. 148 (Supreme Court of Alabama, 1928)
Wiseman v. . Lacy
138 S.E. 121 (Supreme Court of North Carolina, 1927)
Payseno v. Padgett Co.
212 N.W. 836 (North Dakota Supreme Court, 1927)
Fulghum & Union Indemnity Co. v. State
109 So. 644 (Supreme Court of Florida, 1926)
Franzen v. Southern Surety Co.
246 P. 30 (Wyoming Supreme Court, 1926)
Hansen v. Remer
200 N.W. 839 (Supreme Court of Minnesota, 1924)
Caldwell v. Steinfeld
294 F. 270 (Ninth Circuit, 1923)
State v. Equitable Surety Co.
167 N.W. 292 (Supreme Court of Minnesota, 1918)
Remington v. Sabin
157 N.W. 504 (Supreme Court of Minnesota, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
163 N.W. 772, 137 Minn. 352, 1917 Minn. LEXIS 736, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dawson-v-northwestern-contruction-co-minn-1917.