Hansen v. Remer

200 N.W. 839, 160 Minn. 453, 1924 Minn. LEXIS 780
CourtSupreme Court of Minnesota
DecidedOctober 31, 1924
DocketNos. 24,244-24,248, 24,254
StatusPublished
Cited by13 cases

This text of 200 N.W. 839 (Hansen v. Remer) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hansen v. Remer, 200 N.W. 839, 160 Minn. 453, 1924 Minn. LEXIS 780 (Mich. 1924).

Opinion

Lees, C.

This action was brought on a public contractor’s bond given by Emil F. Remer, who had a contract with the state for the construction of a highway between Bena and Ball Club in Cass county. Persons having claims against him and his subcontractors intervened. The liability of the surety on the bond for the payment of these claims was in issue in the court below and in this appeal, which is taken by the surety from the judgment against it.

SURETY COMPANY’S APPEAL.

In addition to the conditions mentioned in G-. S. 1913, § 8245, the bond was conditioned for the payment by the principal of claims for “camp supplies, equipment and equipment supplies furnished to said contractor and used in connection with said contract.”

Plaintiffs’ Claim.

Remer hired 30 horses from plaintiffs. The contract of hiring provided that the horses should not be taken off the job until it was completed and that Remer should then load the horses for shipment and pay the freight from Bena to Milaca. It also provided that he was to pay $30 a calendar month for the use of each team, payment to be made on the twentieth day of each month. On July 7, 1923, the state commissioner of highways notified Remer that he was in default in the performance of the contract and must cease work. He disregarded the notice and continued to work until July 21, but did no work after that date, and on August 14 the job was taken over by another contractor. The horses remained at Remer’s camp and were hired by the new contractor. Plaintiffs’ claim for their hire from July 21 to August 14 was disputed, but the court allowed it.

The application for the bond contained an assignment to appellant of Remer’s rights and interest in “all the tools, plant and [456]*456equipment and materials of every nature and description” that he might have at the place where the work was to be done, and appellant was authorized to take possession and make use thereof in case of a default in the performance of the contract.

On July 21 many of Renter’s employes struck because of his failure to pay their wages. One of the plaintiffs was a foreman employed by Remer. He remained at the camp where the horses were kept, and after a few days went to Duluth, called upon appellant’s agents and local attorneys and asked for instructions as to the disposition of the horses. They declined to give him any instructions, but did telephone to Remer about releasing the horses, and on August 7 he gave plaintiffs a release.

In Dawson v. N. W. Const. Co. 137 Minn. 352, 163 N. W. 772, it was held that the surety on a public contractor’s bond is liable for the rental value of horses necessarily used to do the work. Here the claim arose after the work ceased. As a general rule, a public contractor’s bond should not be interpreted so as to subject the surety to liability for labor claims arising after the work is abandoned. The bond is intended to secure the payment of such debts as are contracted in the performance of the contract. It does not necessarily follow that, because the claim is one the contractor must pay, the surety is also bound to pay it. If appellant is liable for the payment of the claim in question, liability must be based on the special terms of his contract with Remer and its conduct after it had notice that he had dropped the work. Plaintiffs seem to have doubted their right to take their horses away without getting the consent of either Remer or the appellant. At any rate Remer’s consent was obtained. If he had given it without appellant’s approval, he would have violated the contract between them, for appellant had the right to step in and take charge of the work and the equipment. It had notice that the horses were being kept at the camp, and the trial court has found that their use for the purpose of the contract did not cease until August 13. In effect the finding is that they were retained to fulfil the contract, although they did no work.

[457]*457In view of these special facts and circumstances, we conclude that the claim does not fall within the application of the general rule of nonliability of the surety for claims arising after the principal drops the work.

Claim foe Feed foe Horses.

The court found that, at Remer’s request, the intervener Joseph Carpenter furnished hay, between July 21 and August 4, 1923, to feed plaintiffs’ horses, and held that appellant must pay for it. The term “camp supplies,” as used in the bond, comprehends feed for horses kept at the camp. Remer had agreed that the horses should be fed and cared for while in his possession. The hay was furnished before he released them. If it had been furnished while the horses were working, there could be no doubt about appellant’s liability. It cannot be said that there was no liability for their feed after the work stopped, in view of our holding with respect to plaintiffs’ claim for their hire.

Claims foe Wages After Woek Stopped.

One of Remer’s general foremen, barn foreman, two cooks and a cook’s helper remained in the camp and continued to do their work. A portion of the work consisted in feeding the strikers. The work was done at the request of a man Remer had placed in general charge of the job. The court held that appellant must pay the wages of the 5 men up to August 14, finding that Remer kept them at the camp with the knowledge of appellant to await the resumption of the work, and that it was advantageous to him, to appellant and to the state that they should be so kept. It is a fair inference that the work could be relet at k lower price if the expense of establishing a new camp and reassembling and organizing a crew of laborers could be avoided. The less the state had to pay to finish the work, the less would be appellant’s liability on its bond. There was evidence indicating that appellant knew of the situation. Here, as with the horses, the circumstances remove the case from the application of the general rule of nonliability on the part of the surety for services rendered to the principal after the work is no longer in progress.

[458]*458Claims for Oamp Supplies Furnished to Subcontractors.

Flemming and Davis were merchants who separately furnished certain supplies, including provisions, to Remer and to his subcontractors. Appellant contends that, while it may be liable for the supplies furnished to Remer, it is not liable for those furnished to subcontractors. It would not be liable if the bond contained only the statutory conditions. Westling v. Republic C. Co. of Pittsburgh, 157 Minn. 198, 195 N. W. 796. If liable at all, it is because of the language of the extra-statutory conditions. There may be a question as to the legal effect of a bond taken by the state, which provides for the payment of claims not within the scope of section 8245. The claimants are not parties to the bond and their right to resort to it may be debatable. However, no point is made as to this, and so we pass by the question and come directly to the point upon which appellant does rely.

The court found that the two claimants mentioned furnished to certain subcontractors, at their request and at the request of Remer, tools, materials and camp supplies and equipment, which were used under and for the purposes of the contract and the subcontracts. The nature of the supplies was such that they could not be incorporated into the road, but they were furnished in response to a request in which Remer joined, hence he could be held for the payment of the reasonable value of the goods furnished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Caldas v. Affordable Granite & Stone, Inc.
820 N.W.2d 826 (Supreme Court of Minnesota, 2012)
Kvidera v. Rotation Engineering & Manufacturing Co.
705 N.W.2d 416 (Court of Appeals of Minnesota, 2005)
O'BRIEN v. Boston & Maine Railroad
91 N.E.2d 218 (Massachusetts Supreme Judicial Court, 1950)
Mayes v. Byers
7 N.W.2d 403 (Supreme Court of Minnesota, 1943)
J.F. Tolton Inv. Co. v. Maryland Casualty Co.
293 P. 611 (Utah Supreme Court, 1930)
Union Indemnity Co. v. State Ex Rel. Haigler
127 So. 307 (Supreme Court of Florida, 1930)
Southern Surety Co. v. Eoff
22 S.W.2d 964 (Court of Appeals of Texas, 1929)
Clifton v. Norden
226 N.W. 940 (Supreme Court of Minnesota, 1929)
County of Blue Earth v. Bisballe Construction Co.
213 N.W. 30 (Supreme Court of Minnesota, 1927)
Fidelity & Deposit Co. of Maryland v. Milwaukee-Western Fuel Co.
210 N.W. 713 (Wisconsin Supreme Court, 1927)
Southern Surety Co. v. Hotchkiss
201 N.W. 986 (Wisconsin Supreme Court, 1925)
Bartles-Scott Oil Co. v. Western Surety Co.
200 N.W. 937 (Supreme Court of Minnesota, 1924)
Southern Surety Co. v. Metropolitan Sewerage Commission
187 Wis. 206 (Wisconsin Supreme Court, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
200 N.W. 839, 160 Minn. 453, 1924 Minn. LEXIS 780, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hansen-v-remer-minn-1924.